This document is a Table of Contents for the Leavenworth National Cemetery Maintenance Building Bid Documents (Addendum 01), located in Leavenworth, Kansas. The comprehensive specification covers multiple construction divisions, including architectural, structural, mechanical, electrical, and site utility systems for a maintenance building project. The document details specifications across 33 divisions, ranging from general requirements and existing conditions to specialized areas like plumbing, HVAC, communications, electronic safety, earthwork, and exterior improvements, with most sections dated from 10-23 to 11-16. The project is being executed for the Department of Veterans Affairs (VA) under project number 897CM3024, indicating a federal government construction initiative for a national cemetery facility.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Leavenworth National Cemetery VA Project 897CM3024
Maintenance Building Bid Documents (Addendum 01)
Leavenworth, KS 66048
TABLE OF CONTENTS
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
NCA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 05-10
DIVISION 01 - GENERAL REQUIREMENTS
01 00 02 General Requirements (Minor NCA Projects) 10-23
01 32 16.13 Network Analysis Schedules (NCA) 10-23
01 33 23 Shop Drawings, Product Data, and Samples 10-23
01 42 19 Reference Standards 10-23
01 45 29 Testing Laboratory Services 10-23
01 57 19 Temporary Environmental Controls 10-23
01 74 19 Construction Waste Management 10-23
01 81 13 Sustainable Construction Requirements 10-23
01 91 00 General Commissioning Requirements 10-23
DIVISION 02 – EXISTING CONDITIONS
02 21 00 Site Surveys 10-23
02 41 10 Demolition and Site Clearing 10-23
02 83 33.13 Lead-Based Paint Removal and Disposal 10-23
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 10-23
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 10-23
04 05 16 Masonry Grouting 10-23
04 20 00 Unit Masonry 10-23
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 10-23
05 31 00 Steel Decking 10-23
05 40 00 Cold-Formed Metal Framing 10-23
05 50 00 Metal Fabrications 08-18
DIVISION 06 – WOOD,PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-23
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
Leavenworth, KS 66048
TABLE OF CONTENTS
00 01 10-2
07 13 00 Sheet Waterproofing 10-23
07 13 52 Modified Bituminous Sheet Waterproofing 10-23
07 21 13 Thermal Insulation 10-23
07 22 00 Roof and Deck Insulation 10-23
07 27 26 Fluid-Applied Membrane Air Barriers, Vapor Permeable 01-21
07 40 00 Siding Panels 10-23
07 41 13 Standing Seam Metal Roofing 10-23
07 60 00 Flashing and Sheet Metal 10-23
07 71 00 Roof Specialties 10-23
07 84 00 Firestopping 10-23
07 92 00 Joint Sealants 10-23
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 10-23
08 31 13 Access Doors and Frames 10-23
08 33 00 Coiling Doors 10-23
08 41 13 Aluminum-Framed Entrances and Storefronts 10-23
08 71 00 Door Hardware 10-23
08 80 00 Glazing 10-23
08 90 00 Louvers and Vents 10-23
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 22 16 Non-Structural Metal Framing 10-23
09 29 00 Gypsum Board 10-23
09 30 00 Specialty Moldings and Trims
09 30 13 Tiling 10-23
09 51 00 Acoustical Ceilings 10-23
09 65 13 Resilient Base and Accessories 10-23
09 65 19 Resilient Tile Flooring 10-23
09 65 36.13 Static-Dissipative Resilient Flooring
09 67 23 Resinous Flooring 10-23
09 72 16 Vinyl-Coated Fabric Wall Coverings 01-21
09 91 00 Painting 10-23
09 96 00 High-Performance Coatings
DIVISION 10 – SPECIALTIES
10 14 00 Exterior Signage 10-23
10 14 05 Interior Signage 10-23
10 21 13 Toilet Compartments 10-23
10 28 00 Toilet and Bath Accessories 10-23
10 44 13 Fire Extinguisher Cabinets 10-23
10 51 13 Metal Lockers 10-23
10 51 13.13 High-Density Polyethylene (HDPE) Storage Cubbies 06-25
10 56 13 Steel Shelving 10-23
DIVISION 11 - EQUIPMENT
10-23
11 11 14 Motor Vehicle Lifts 10-23
Leavenworth, KS 66048
TABLE OF CONTENTS
00 01 10-3
11 11 16 Vehicle Service Equipment 10-23
11 11 26 Vehicle Washing Equipment 10-23
11 83 02 Geodata 10-23
DIVISION 12 – FURNISHINGS
12 24 00 Window Shades 10-23
12 32 00 Manufactured Wood Casework 10-23
12 36 00 Countertops
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 19 Metal Building Systems 06-14
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 11-16
22 05 12 General Motor Requirements for Plumbing Equipment 11-16
22 05 19 Meters and Gages for Plumbing Piping 11-16
22 05 23 General-Duty Valves for Plumbing Piping 11-16
22 07 11 Plumbing Insulation 09-19
22 08 00 Commissioning of Plumbing Systems 12-15
22 11 00 Facility Water Distribution 11-16
22 11 23 Domestic Water Pumps 11-16
22 13 00 Facility Sanitary and Vent Piping 11-16
22 13 23 Sanitary Waste Interceptors 11-16
22 14 00 Facility Storm Drainage 11-16
22 15 00 General Service Compressed-Air Systems 11-16
22 34 00 Fuel-Fired Domestic Water Heaters 11-16
22 40 00 Plumbing Fixtures 11-16
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 11-16
23 05 12 General Motor Requirements for HVAC Equipment 11-16
23 05 93 Testing, Adjusting, and Balancing for HVAC 11-16
23 07 11 HVAC Insulation 11-16
23 08 00 Commissioning of HVAC Systems 12-15
23 09 23 Direct-Digital Control System for HVAC 11-16
23 11 23 Facility Natural-Gas Piping 11-16
23 13 23 Concrete Above Ground Fuel Storage
23 23 00 Refrigerant Piping 11-16
23 31 00 HVAC Ducts and Casings 11-16
23 34 00 HVAC Fans 11-16
23 36 00 Air Terminal Units 11-16
23 37 00 Air Outlets and Inlets 11-16
23 55 23 Gas-Fired Radiant Heaters 11-16
23 55 33 Fuel-Fired Unit Heaters 11-16
23 81 43 Air-Source Unitary Heat Pumps 11-16
DIVISION 25 – INTEGRATED AUTOMATION
Leavenworth, KS 66048
TABLE OF CONTENTS
00 01 10-4
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 04-23
26 05 13 Medium Voltage Cables 11-22
26 05 19 Low-Voltage Electrical Power Conductors and Cables 04-23
26 05 26 Grounding and Bonding for Electrical Systems 04-23
26 05 33 Raceway and Boxes for Electrical Systems 04-23
26 05 41 Underground Electrical Construction 04-23
26 05 73 Overcurrent Protective Device Coordination Study 04-23
26 08 00 Commissioning of Electrical Systems 04-23
26 09 23 Lighting Controls 11-22
26 12 19 Pad-Mounted, Liquid Filled, Medium-Voltage
Transformers
11-22
26 13 16 Medium Voltage Fusible Interrupter Switches 11-22
26 24 13 Distribution Switchboards 04-23
26 24 16 Panelboards 04-23
26 27 26 Wiring Devices 04-23
26 29 11 Motor Controllers 04-23
26 29 21 Enclosed Switches and Circuit Breakers 04-23
26 32 13 Engine Generators 04-23
26 36 00 Transfer Switches 04-23
26 41 00 Facility Lightning Protection 04-23
26 43 13 Surge Protection Devices 11-22
26 51 00 Interior Lighting 04-23
26 56 00 Exterior Lighting 04-23
DIVISION 27 – COMMUNICATIONS
27 05 26 Grounding and Bonding for Communications Systems 12-22
27 05 33 Conduits and Backboxes for Communications Systems 12-22
27 05 53 Identification for Communications Systems 12-22
27 10 00 Structured Cabling 12-22
27 11 16 Communications Cabinets, Racks, Frames, and Enclosures 12-22
27 11 19 Communications Termination Blocks and Patch Panels 12-22
27 11 26 Communications Rack Mounted Power Protection and Power
Strips
12-22
27 13 13.13 Communications Copper Cable Splicing and Terminations 12-22
27 13 23 Communications Optical Fiber Backbone Cabling 12-22
27 15 13 Communications Copper Horizontal Cabling 12-22
27 16 19 Communications Patch Cords, Station Cords, and Cross-
Connect Wire
12-22
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results For Electronic Safety and Security 10-18
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 08 00 Commissioning of Electronic Safety and Security
Systems
04-18
28 13 00 Physical Access Control System 10-11
28 23 00 Video Surveillance 09-11
Leavenworth, KS 66048
TABLE OF CONTENTS
00 01 10-5
28 31 00 Fire Detection and Alarm 09-11
DIVISION 31 – EARTHWORK
31 20 11 Earth Moving (Short Form) 11-16
31 23 19 Dewatering 11-16
31 23 23.33 Flowable Fill
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 11-16
32 12 16 Asphalt Paving 11-16
32 17 23 Pavement Markings 11-16
32 31 13 Chain Link Fences and Gates 11-16
32 33 00 Site Furnishings 01-17
32 90 00 Planting 11-16
DIVISION 33 – UTILITIES
33 10 00 Water Utilities 11-16
33 30 00 Sanitary Sewerage Utilities 11-16
33 40 00 Storm Sewer Utilities 11-16
33 41 13 Foundation Drainage 01-17
33 51 00 Natural-Gas Distribution 11-16