802-NRM19-05_Full_Specifications_red_12-28-18.pdf
PDF 4 MB Posted
- Solicitation number
- 36C78619B0002
About this file
36C78619B0002 802-NRM19-05 Full Specifications red 12-28-18.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78619B0002-0004000.docx | DOCX document | |
| 36C78619B0002-0003011.pdf | ||
| 36C78619B0002-0003003.pdf | ||
| 36C78619B0002-0003005.pdf | ||
| 36C78619B0002-0003006.pdf | ||
| 36C78619B0002-0003004.pdf | ||
| 36C78619B0002-0003009.pdf | ||
| 36C78619B0002-0003001.pdf | ||
| 36C78619B0002-0003012.pdf | ||
| 36C78619B0002-0003007.pdf | ||
| 36C78619B0002-0003000.docx | DOCX document | |
| 36C78619B0002-0003008.pdf | ||
| 36C78619B0002-0003002.pdf | ||
| 36C78619B0002-0003013.pdf | ||
| 36C78619B0002-0003010.pdf | ||
| 36C78619B0002-0002000.docx | DOCX document | |
| 802-NRM19-05_Treatment_Plan.pdf | ||
| 36C78619B0002_0001.docx | DOCX document | |
| 802-NRM19-05_Hazardous_Materials_Investigation.pdf | ||
| 802-NRM-19-05_SOW_Summary_-_12-28-18.pdf | ||
| 36C78619B0002.docx | DOCX document | |
| 802-NRM19-05_Full_Drawings.pdf | ||
| 36C78619B0002_Presol.docx | DOCX document |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Baltimore National Cemetery 5501 Frederick Avenue Baltimore, Maryland 21228
“Administration Building Repairs and Life Safety Improvements”
VA Project Number: 802-NRM18-03
100 Percent Construction Documents Final
November 27, 2018
U.S. Department of Veterans Affairs – North Atlantic Region
Baltimore National Cemetery Architura Corporation Administration Building Repairs and Life Safety Improvements VA Project Number:
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
SEALS PAGE 00 01 07 - 1
DOCUMENT 00 01 07 - SEALS PAGE
1.1 DESIGN PROFESSIONALS OF RECORD
ARCHITECT ARCHITURA
Michael F. Conly Maryland Architect #19379 Expires: 3/15/2020
END OF DOCUMENT 00 01 07
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
SEALS PAGE 00 01 07 - 2
THIS SHEET LEFT INTENTIONALLY BLANK
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
TABLE OF CONTENTS 00 01 10 - 1
DOCUMENT 00 01 10 - TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 01 TITLE SHEET
00 01 07 CERTIFICATION PAGE
00 01 10 TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
01 00 02 GENERAL REQUIREMENTS
01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
01 42 19 REFERENCE STANDARDS
01 45 29 TESTING LABORATORY SERVICES
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 CONSTRUCTION WASTE MANAGEMENT
DIVISION 02 – EXISTING CONDITIONS
02 41 10 DEMOLITION AND SITE CLEARING
TREATMENT PLAN
LIMITED HAZARDOUS MATERIAL SURVEY REPORT
02 83 33.13 LEAD BASED PAINT REMOVAL AND DISPOSAL
DIVISION 03 – CONCRETE
03 30 53 CAST-IN-PLACE CONCRETE
DIVISION 04 – MASONRY
04 05 13 MASONRY MORTARING
04 05 16 MASONRY GROUTING
04 05 31 MASONRY TUCK POINTING
04 43 00 NATURAL STONE VENEER
DIVISION 05 – METALS
05 50 00 METAL FABRICATIONS
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 31 26 SLATE SHINGLES – ALTERNATE BID NO. 1
07 60 00 FLASHING AND SHEET METAL – ALTERNATE BID NO. 1
07 92 00 JOINT SEALANTS
DIVISION 08 – OPENINGS
08 11 13 HOLLOW METAL DOORS AND FRAMES
08 14 00 INTERIOR WOOD DOORS – ALTERNATE BID NO. 2
08 33 00 COILING DOORS AND GRILLES
08 71 00 DOOR HARDWARE
5501 Frederick Avenue 802-NRM18-03
TABLE OF CONTENTS 00 01 10 - 2
Baltimore, Maryland 21228
08 80 00 GLAZING
DIVISION 08 – OPENINGS (Continued)
08 89 00 LOUVERS AND VENTS
DIVISION 09 – FINISHES
09 24 00 09 91 13
PORTLAND CEMENT PLASTERING
EXTERIOR PAINTING
DIVISION 10 – SPECIALTIES (Not Used)
DIVISION 11 – EQUIPMENT (Not Used)
DIVISION 12 – FURNISHINGS (Not Used)
DIVISION 13 – SPECIAL CONSTRUCTION (Not Used)
DIVISION 14 – CONVEYING EQUIPMENT (Not Used)
DIVISION 15-21 (Not Used)
DIVISION 22 - PLUMBING (Mot Used)
DIVISION 23 – HEATING VENTILATING AND AIR CONDITIONING (Not Used)
DIVISION 24-25 (Not used)
DIVISION 26 – ELECTRICAL
26 05 11 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS
26 05 33 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS
26 56 00 EXTERIOR LIGHTING
DIVISION 27-30 (Not Used)
DIVISION 31 – EARTHWORK (Not Used)
DIVISION 32 – UTILITIES
32 05 23 CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS
32 12 16 ASPHALT PAVING
32 90 00 PLANTING
DIVISION 33 – EXTERIOR IMPROVEMENTS (Not Used)
DIVISION 34 – 49 (Not Used) -
END OF DOCUMENT 00 01 10
SECTION 01 00 02 GENERAL REQUIREMENTS (MINOR NCA PROJECTS)
TABLE OF CONTENTS
1.1 GENERAL INTENTION
1.2 STATEMENT OF BID ITEM(S)
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.4 CONSTRUCTION SECURITY REQUIREMENTS…………………………………………4
1.5 FIRE SAFETY
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 ENVIRONMENTAL CONTROLS………………………………………………………….14
1.9 DISPOSAL AND RETENTION
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.11 RESTORATION
1.12 PHYSICAL DATA
1.13 LAYOUT OF WORK
1.14 AS-BUILT DRAWINGS
1.15 USE OF ROADWAYS
1.16 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.17 TEMPORARY TOILETS…………………………………………………………………..21
1.18 AVAILABILITY AND USE OF UTILITY SERVICES
1,19 TESTS………………………………………………………………………………………23
1.20 INSTRUCTIONS
1.21 CONSTRUCTION DIGITAL IMAGES……………………………………………..…….25
1.22 FINAL ELEVATION PHOTOGRAPHS
1.23 HISTORIC PRESERVATION
1.24 PROJECT HEALTH AND SAFETY PLAN
file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619571 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619572 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619573 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619574 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619575 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619576 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619577 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619578 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619578 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619579 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619580 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619582 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619583 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619584 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619585 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619587 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619588 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619595 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619596 file:///C:/Users/Jack/Downloads/010002GenReqMinor-%20TR-11.docx%23_Toc357619597
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 1
PART 1 - GENERAL
1.1 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor, materials, equipment and services and perform and complete all work for the Administration Building Repairs and Life Safety Improvements, Baltimore National Cemetery, 5501 Frederick Drive, Baltimore, MD 21228 as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by permission of the Cemetery Director.
C. Offices of ARCHITURA CORPORATION, 9880 Westpoint Drive, Suite 400, Indianapolis, IN
46250, as Architect-Engineers (A/E), may render certain technical services during construction.
Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Project
Engineer/Contracting Officers Representative (RE/COR) or his duly authorized representative.
D. Project Engineer/Contracting Officer’s Representative (RE/COR) is Rico Silvetti. His contact information is as follows:
Rico Silvetti
Department of Veteran Affairs
National Cemetery Administration
North Atlantic District
5500 Wissahickson Ave.
Philadelphia, PA 19144
Rico.Silvetti@va.gov
215-381-3787 ext. 4050
Rico.Silvetti@va.gov
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 2
E. Director of the Baltimore National Cemetery is Michael Brophy. His contact information is as follows:
Michael Brophy, Director
Baltimore National Cemetery
5501 Frederick Avenue
Baltimore, MD. 21228 michael.brophy@va.gov
410-644-9696
F. Architect for the Project is Michael Conly. His contact information is as follows:
Michael Conly, AIA, NCARB
Architura Corporation
9880 Westpoint Drive, Suite 400
Indianapolis, IN 46250 michaelconly@archituracorp.com
317-348-1000
G. All Testing Laboratory services will be retained and paid for by the Contractor (see Spec Section
01 45 29, Testing Laboratory Services). However, the Department of Veterans Affairs may elect to retain its own Testing Laboratory for any purpose. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the RE/COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the RE/COR.
H. All employees of general contractor and subcontractors shall comply with VA security management program, security requirements as established by the RE/COR, and be identified by name and employer. They shall be restricted from unauthorized access.
I. Prior to commencing work, general contractor shall provide proof that a OSHA certified
“competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
michael.brophy@va.gov michaelconly@archituracorp.com%20
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 3
J. Training:
1. All employees of general contractor or subcontractors shall, at the minimum, have successfully completed the 10-hour OSHA certified Construction Safety course and/or other relevant competency training, as determined by VA CP.
2. Submit OSHA training records of all employees for approval before the start of work.
1.2 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Installation of all work shown on the plans and described in the specifications including but not limited to:
1. PROJECT DESCRIPTION.
a. Exterior Building Repairs:
1) Existing exterior doors will be replaced as noted and new hardware.
Provide automatic door hardware as noted.
2) Replacement of existing overhead coiling doors. Provide and new openers.
3) Restoration and repainting of all existing wood windows, metal louvers, and trim.
4) Restoration of existing wood portico. Includes repair and replacement of all exterior architectural woodwork identified as being in poor condition.
5) Repaint all existing architectural woodwork remaining.
6) Repair and repaint existing stucco.
b. Interior Building Repairs:
1) Reverse swing of doors and hardware where noted to assist with exiting path.
2) Cut opening for new metal door and frame as noted.
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 4
B. ALTERNATE NO.1:
1. Work includes all exterior work repairs and replacement of some areas of existing slate roof.
2. Work includes providing new ice and water shield around perimeter of roof.
3. Work includes providing new copper or bronze flashing to replace existing.
C. ALTERNATE NO. 2:
1. Work associated with the replacement and installation of new wood door and frame under the new Portico.
2. Work includes replacing all existing exterior doors, frames, and hardware.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. AFTER AWARD OF CONTRACT, one bond paper set of specifications and drawings will be furnished. These drawings and specifications will consist of those returned by prospective bidders.
B. Additional sets of drawings may be made by the Contractor, at Contractor's expense, from Bond and digital files furnished by the Issuing Office.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 5
1. General Contractor’s employees shall not enter the site without following the procedures approved by the RE/COR. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the “regular hours” as defined in the contract, The General Contractor shall give 3 days notice to the RE/COTR so that appropriate arrangements can be provided for the Cemetery employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the RE/COTR.
4. VA reserves the right to close down or shut down the project site and order General
Contractor’s employees off the premises in the event of a national emergency. The General
Contractor may return to the site only with the written approval of the RE/COR.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the RE/COR for the purpose of security inspections of every area of project including tool boxes and parked machines, and to take any necessary emergency action.
CI. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law
Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the RE/COTR upon request.
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 6
4. These security documents shall not be removed or transmitted from the project site without the written approval of RE/COR.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify RE/COR immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in a specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies. Authorization includes where vehicles are parked, deliveries are made, and construction storage areas.
1.5 FIRE SAFETY
A. Applicable Publications: Publications listed below form part of this Article to the extent referenced. Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
E84-2009a Surface Burning Characteristics of Building Materials
2. National Fire Protection Association (NFPA):
10-2010 Standard for Portable Fire Extinguishers
30-2008 Flammable and Combustible Liquids Code
51B-2009 Standard for Fire Prevention During Welding, Cutting and Other
Hot Work
70-2008 National Electrical Code
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 7
241-2009 Standard for Safeguarding Construction, Alteration, and
Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926 Safety and Health Regulations for Construction
B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR
1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to RE/COR/Cemetery Director for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP
DRAWINGS, PRODUCT DATA AND SAMPLES. Prior to any worker for the contractor or subcontractor’s beginning work, they shall undergo a safety briefing provided by the General
Contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of NCA equipment, etc. Documentation shall be provided to the RE/COR that individuals have undergone the Contractor’s safety briefing.
C. Site and Building Access: Maintain free and unobstructed access to emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.
D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet).
E. Temporary Construction Measures:
1. Install and maintain temporary construction barriers for dust control. Wood frames with polyethylene are to be erected in separate work areas from other occupied areas. Temporary construction fences are to be erected in separate areas of exterior work from areas not disturbed.
F. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29
CFR 1926, NFPA 241 and NFPA 70.
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 8
G. Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with RE/COR/Cemetery Director.
H. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily.
Report findings and corrective actions weekly to RE/COR.
I. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926, NFPA 241 and NFPA 10.
J. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR
1926, NFPA 241 and NFPA 30.
K. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly.
Coordinate with, and report findings and corrective actions weekly to RE/COR.
L. Smoking: Smoking is prohibited in and adjacent to construction areas inside existing buildings and additions under construction. In separate and detached buildings under construction, smoking is prohibited except in designated smoking rest areas.
M. Dispose of waste and debris in accordance with NFPA 241. Remove from building daily and site weekly.
N. Perform other construction, alteration and demolition operations in accordance with 29 CFR
1926.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the RE/COR. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage trailers) and utilities may be erected by the Contractor only with the approval of the RE/COR and shall be built with labor and materials furnished by the
Contractor without expense to the Government. The temporary buildings and utilities shall
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 9
remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.
C. The Contractor shall, under regulations prescribed by the RE/COR, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the RE/COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the RE/COR with agreement of the Cemetery. Contractor parking will be only in areas and on roadways designated and agreed to by the RE/COR in agreement of the Cemetery.
E. Workmen are subject to rules of the Cemetery applicable to their conduct.
F. Execute work to interfere as little as possible with normal functioning of Cemetery as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by the Cemetery in quantities sufficient for not more than two work days. Provide unobstructed access to the Cemetery areas required to remain in operation.
3. Where access by Cemetery personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements. All such actions shall be coordinated with the Utility Company involved:
a. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 10
G. Building will be occupied during performance of work; but immediate areas of alterations will be vacated. Access of areas will as be coordinated with the RE/COR.
1. The Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Cemetery’s operations will not be hindered. The Contractor shall permit access to Cemetery personnel through other construction areas which serve as routes of access to such affected areas and equipment.
Coordinate alteration work in areas occupied by Cemetery Staff so that Cemetery operations will continue during the construction period.
I. Construction Fence: Before construction operations begin, the Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. The temporary fencing shall encompass the construction work area(s) to serve as a pedestrian barrier to alert cemetery patrons of the construction site. Remove the fence when directed by RE/COR. Areas affected will be the existing Portico area and the area of the overhead coiling doors.
J. When a building is turned over to Contractor, Contractor shall accept entire responsibility therefore.
1. The Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. The Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, the Contractor shall make arrangements for pre-inspection of the site with Fire Department or Company (Department of Veterans
Affairs or municipal) whichever will be required to respond to an alarm from the Contractor's employee.
K. Utilities Services: Maintain existing utility services for the Cemetery at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 11
services. Where necessary to cut existing water, sewer or air pipes, or conduits, wires, cables, etc.
of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by RE/COR. All such actions shall be coordinated with the Utility
Company involved.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of RE/COR.
Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the RE/COR, and Cemetery Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS
FOR ELECTRICAL INSTALLATIONS for additional requirements.
2. The Contractor shall submit a request to interrupt any such services to both RE/COR and the
Cemetery Director in writing, 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. The Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Cemetery.
Interruption time approved by the Cemetery and RE/COR may occur at other than
Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the RE/COR.
5. In case of a contract construction emergency, service will be interrupted on approval of
RE/COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the
Contractor.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged. The lines shall not be capped in finished areas, but shall be
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 12
removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of Cemetery traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the RE/COR.
N. Coordinate the work for this contract with other construction operations as directed by RE/COR.
This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
O. Coordination of Construction with Cemetery Director: The burial activities at a National
Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the RE/COR, in arranging construction schedule to cause the least possible interference with Cemetery activities in actual burial areas.
Construction noise during the committal services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period.
1. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.
2. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the areas in a clean, neat condition.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the
RE/COR of building areas in which alterations occur, areas which are anticipated routes of
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 13
access, and furnish a signed report, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls, and other surfaces not required to be altered throughout affected areas.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and
RE/COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of RE/COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by the Contractor with new items in accordance with specifications which will be furnished by the Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and
"CHANGES" (FAR 52.243-4 and VAAR 852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and
RE/COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing of doors, windows, and other surfaces as compared with conditions of same as noted in first condition survey report.
1. Re-survey report shall also list any damage caused by the Contractor to such flooring and other surfaces, despite protection measures; and, will form the basis for determining extent of repair work required of the Contractor to restore damage caused by the Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 14
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protect the interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor, and any indicated surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 ENVIRONMENTAL CONTROLS
A. In general, following preventive measures shall be adopted during construction to keep down dust and prevent mold.
1. Dampen debris to keep down dust and provide temporary construction partitions in existing structures where directed by RE/COR. Block off ducts and diffusers to prevent circulation of dust into occupied areas during construction.
B. Vacuum and wet mop all transition areas from construction to the occupied Cemetery buildings at the end of each workday.
C. Final Cleanup:
1. Upon completion of the project, or as work progresses, remove all construction debris from above ceiling, vertical shafts and utility chases that have been part of the construction.
2. All new air ducts shall be cleaned prior to final inspection.
1.9 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by RE/COR.
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 15
2. Items not reserved shall become property of the Contractor and be removed by Contractor from the Cemetery.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
4. Copies of the following listed CFR titles may be obtained from the Government Printing
Office:
40 CFR 261 Identification and Listing of Hazardous Waste
49 CFR 172 Hazardous Material tables and Hazardous Material
Communications Regulations
49 CFR 173 Shippers - General Requirements for Shipments and Packaging
49 CRR 173 Subpart A General
49 CFR 173 Subpart B Preparation of Hazardous Material for Transportation
49 CFR 173 Subpart J Other Regulated Material; Definitions and Preparation
TSCA Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the
RE/COR.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 16
should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the RE/COR may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General
Conditions. A National Pollutant Discharge Elimination System (NPDES) permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate NCA Central/Cemetery) office. The contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair;
2. Providing waste receptacles at convenient locations and provide regular collection of wastes;
3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
5. Providing adequately maintained sanitary facilities.
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 17
1.11 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work.
Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, water/irrigation or electric work without approval of the RE/COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the RE/COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, landscape stone, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At the Contractor's own expense, the Contractor shall immediately restore to service and repair any damage caused by the Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services, communications systems (including telephone), and power which are indicated on drawings and which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE
CONDITIONS" (FAR 52.236-2).
1.12 PHYSICAL DATA
A. Data and information furnished or referred to below is for the Contractor's information. The
Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by KCI dated June 20, 2018.
(FAR 52.236-4)
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 18
B. The Government does not guarantee that other materials will not be encountered, nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine the site of work and logs of borings and, after investigation, decide for themselves the character of materials and make their bids accordingly.
Upon proper application to the Department of Veterans Affairs, including approved scheduling bidders will be permitted to make subsurface explorations of their own at site.
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks indicated on the drawings and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at the Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The
Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the RE/COR. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the RE/COR until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the RE/COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
B. Establish and plainly mark center lines for each building and/or addition to each existing building, lines for each gravesite control monument, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, parking lots, gravesite control monuments, are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. The Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 19
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the RE/COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
D. During progress of work, the Contractor shall have lines, grades, locations and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the RE/COR before any major items of concrete work are placed. In addition, furnish to the RE/COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each building and/or addition.
2. Elevations of bottoms of footings and tops of floors of each building and/or addition.
3. Lines and elevations of sewers and of all outside distribution systems.
4. Lines of grave plot documentation.
5. Lines of elevations of all swales and interment areas.
6. Lines and elevations of roads, streets and parking lots.
7. Northing/Easting coordinate locations and elevation depth below finished grade of all water, sanitary, storm, gas and irrigation structures, directional fittings, control wire and lines.
E. Upon completion of the work, the Contractor shall furnish the RE/COR with reproducible drawings, in AutoCAD form, at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying Services".
1.14 AS-BUILT DRAWINGS
A. The Contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, which will include all contract changes, modifications and clarifications.
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 20
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the RE/COR's review, as often as requested.
C. The Contractor shall deliver two approved completed sets of as-built drawings to the RE/COR within 15 calendar days after acceptance of the project by the RE/COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 USE OF ROADWAYS
A. For hauling, use only established public roads and designated permanent roads on Cemetery property and, when/ indicated or authorized by the RE/COR, such existing or Contractor constructed and/or modified temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed or modified by the Contractor at the Contractor's expense following approved plans that include: construction, operation, maintenance and restoration.
B. When new permanent roads are to be a part of this contract, the Contractor may construct them immediately to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.
C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at the time set for completion of such buildings or parts thereof.
1.16 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to compliance with the following provisions:
1. Permission to use each unit or system must be given by RE/COR. If the equipment is not installed and maintained in accordance with the following provisions, the RE/COR will withdraw permission for use of the equipment.
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 21
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, and their overload elements shall be properly sized, coordinated and adjusted. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use;
maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government. Burners, pumps, feedwater heaters and auxiliary equipment must be operated as a complete system and be fully maintained by operating personnel. Burner water must be given complete and continuous chemical treatment.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
1.17 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections, or when approved by RE/COR provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
Baltimore National Cemetery Architura Corporation
5501 Frederick Avenue 802-NRM18-03 Baltimore, Maryland 21228
GENERAL REQUIREMENTS 01 00 02 - 22
B. Contractor may have for use of the Contractor's workmen, such toilet accommodations as may be assigned to the Contractor by the Cemetery. The Contractor shall keep such places clean and be responsible for any damage done thereto by the Contractor's workmen.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.