These are electrical construction documents for infrastructure upgrades at the VA Pittsburgh Healthcare System (VAPHS) H.J. Heinz Campus 32, located at 1010 Delafield Road, Pittsburgh, PA 15215. The documents include a basement-level electrical plan (32-EN100) and electrical schedules (32-EN302) dated June 27, 2025, prepared by Awen Solutions Group and IMEG as the architect/engineer of record under Project Number 646A-22-700. The project represents the final bid documents phase and is fully sprinklered.
The electrical plans detail existing equipment to remain and new installations for data center cooling and power distribution infrastructure. Key electrical components include multiple PDU (Power Distribution Unit) panels designated PDU-A through PDU-E, CRAC (Computer Room Air Conditioning) units numbered 1 through 6 serving different floor sections, ACCU (Accumulator) units, UPS (Uninterruptible Power Supply) systems with batteries, an emergency generator, an automated transfer switch (ATS), and switchboards. The electrical schedules specify circuit details including breaker amperage ratings (ranging from 15A to 125A), wire gauges, voltage drops, and load calculations for panels A1, B1, PDU-B/D, and PDU-D/D located in the Computer Room (BA120) and Active Storage (BA117) areas. Total estimated demand loads include 28 kVA for PDU panels and 154.488 kVA for HVAC cooling systems at 480 volts delta configuration. The existing Emergency Power-Off (EPO) system will remain unchanged with testing before and after construction, and new receptacles for the Main Distribution Area (MDA) will be mounted in junction boxes between the raised floor and concrete floor.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
E
E
E
E
E
E
E
E
E
F
R
R
R R
R
R
E E EE E E
E
E
E
E
E
E
E
E
E
F
R
R
R R
R
R
E E EE E E
EMERGENCY
GENERATOR
BA116A
MECHANICAL
ROOM
BA116
ACTIVE STORAGE
BA117
INACTIVE
STORAGE
BA118
VISN INACT
STORAGE
BA119
COMPUTER ROOM
BA120
EQUIPMENT
SETUP & R&D LAB
BA120A
LOADING
BC4
UPS ROOM
BA118A
HELP DESK
BA101A
HELP DESK
BA101
VESTIBULE
BA100
LAN CLO
BA102
MALE TLT
BA103
HAC
BA104
FEMALE
LOUNGE
BA105
PROGRAMMING
BA106
OFFICE
BA107
MECH EQUIP
BA108
IT SUPPORT
BA110
MECHANICAL
EQUIPMENT
BA111
OFFICE
BA110C
OFFICE
BA110D
OFFICE
BA110E
OFFICE
BA110F
OFFICE
BA110B
NEW TR
BA110A
STORAGE
BA109
CORRIDOR
BC2
SOFTWARE
LIBRARY
BA115
TAPE VAULT
BA115A
TLT
BA114
TLT
BA112
ELEV
MACH RM
BA102A
CORRIDOR
BC1
CORRIDOR
BC3
FEMALE TLT
BA105A
OFFICE
BA107A
MECH
BA106C
PBX EXIST
BA110A.2
32-EN402
C1
EXISTING PBX BA110A TO
REMAIN
DP
PANEL NA
AIR DIST. PANEL
PANEL ECC PANEL NC
RD
B1
A1
NEAC
EM. GEN.
EMPD
NE1A
MDP
ATS-B
SWBD-B
ATS-A
SWBD-B
UPS-A
UPS-B
A
PDU-D/D
B
PDU-B/D
MBP PNL-A
MBP PNL-B
TAB-E
B32ANE2A
32TC
FSCP-E
PDU-D PDU-B STS-C PDU-C PDU-A PDU-E
CRAC-4/A1-14,16,18
CRAC-3/B1-14,16,18
CRAC-6/A1-26,28,30
CRAC-2/B1-2,4,6
CRAC-1/A1-2,4,6
CRAC-5/B1-26,28,30
SS-32-B/NE2T1-7,9
SS-32-1/EBT-7,9
SS-32-2/ECT-7,9
EPO-CRAC
EPO-UPS
GANN
ATS-ANN
UPS-ANN
FA-ANN
MTS-A
MTS-B
PDU-D/D-19,21,23
PDU-B/D-20,22,24
PDU-D/D-13,15,17
PDU-B/D-14,16,18
PDU-D/D-7,9,11
PDU-B/D-8,10,12
PDU-D/D-1,3,5
PDU-B/D-2,4,6
PDU-B/D-26,28,30
PDU-D/D-38,40,42
PDU-B/D-32,34,36
PDU-D/D-37,39,41
PDU-B/D-38,40,42
PDU-D/D-31,33,35
PDU-B/D-37,39,41
PDU-D/D-25,27,29
EPO-UPS
FDS-75 KVA SEC
TR-75
UPS BATT.MAINT.
UPS BATT.MAINT.
W/AT-8
FDS-SS-32-B
30A
FDS-SS-32-1
30A
FDS-SS-32-2
30A
EPO-UPS
32EA
(TYP.)
ACCU-1/A1-8,10,12 ACCU-2/B1-8,10,12 ACCU-3/B1-20,22,24 ACCU-6/A1-32,34,36 ACCU-5/B1-32,34,36 ACCU-4/A1-20,22,24
W/AT-8 W/AT-8
FIRE BARRIER, 3 HOUR
FIRE BARRIER, 2 HOUR
FIRE BARRIER, 1 HOUR
SMOKE BARRIER
NEW PARTITION
EXISTING PARTITION
DEMOLITION
PARTITION LEGEND
623 26TH AVENUE
ROCK ISLAND, IL 61201
P: 309.788.0673 F: 309.786.5967 www.imegcorp.com
PROJECT #23002990.00
CONSTRUCTION DOCUMENT SUBMISSION
5 5 10 15 20
1/8" = 1'-0"
FEETSCALE
P L A
N N
O R
T H
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FINAL BID DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMP
321 4 5 6 7 8 9 10
GENERAL NOTES:
SHEET NOTES:
Awen Solutions Group
215 N. Payne Street, Suite 122
Alexandria, VA 22314
A u to d e s k D o c s /H e in z V
A M
C E
H R
M
V
/6
A -2
-7
.3
.E
.I M
E G
H
N Z
C
.r v t
/2
/2
:0
:5
P
M
32-EN100
BASEMENT PLAN - ELECTRICAL
06.27.2025
EHRM INFRASTRUCTURE
UPGRADES - VAPHS H.J. HEINZ
CAMPUS 32
1010 DELAFIELD RD
PITTSBURGH, PA 15215
646A-22-700
EZ JF
A. REFER TO E000 FOR GENERAL NOTES.
B. ALL ELECTRICAL EQUIPMENT IS EXISTING TO REMAIN UNLESS OTHERWISE NOTED.
C. ALL HVAC EQUIPMENT IS EXISTING TO REMAIN UNLESS OTHERWISE NOTED.
1. THE EXISTING EPO SYSTEM WILL REMAIN UNCHANGED. TESTING OF THE CURRENT SYSTEM AND ITS OPERATION WILL TAKE PLACE BEFORE CONSTRUCTION BEGINS AND AFTER. THE EPO CIRCUITS FOR THE UPS AND CRACS WILL BE DISCONNECTED AND RECONNECTED AFTER THE INSTALLATION OF THE
NEW EQUIPMENT. TYPICAL FOR ALL.
2. RECEPTACLES TO SERVE MDA SHALL BE MOUNTED IN A J-BOX IN THE SPACE BETWEEN THE RAISED
FLOOR AND CONCRETE FLOOR. REFER TO SHEET 32-EN300 FOR MORE INFORMATION.
Revisions: Date:
ADDENDA DATA CENTER COOLING, Q.56 07/24/2026
623 26TH AVENUE
ROCK ISLAND, IL 61201
P: 309.788.0673 F: 309.786.5967 www.imegcorp.com
PROJECT #23002990.00
CONSTRUCTION DOCUMENT SUBMISSION
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FINAL BID DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMP
321 4 5 6 7 8 9 10
Awen Solutions Group
215 N. Payne Street, Suite 122
Alexandria, VA 22314
A u to d e s k D o c s /H e in z V
A M
C E
H R
M
V
/6
A -2
-7
.3
.E
.I M
E G
H
N Z
C
.r v t
/2
/2
:0
:5
P
M
32-EN302
ELECTRICAL SCHEDULES
06.27.2025
EHRM INFRASTRUCTURE
UPGRADES - VAPHS H.J. HEINZ
CAMPUS 32
1010 DELAFIELD RD
PITTSBURGH, PA 15215
646A-22-700
EZ JF
CIRCUIT KEY NOTES: 1 - PROVIDE NEW BREAKER.
*TOTAL DEMAND CALCS SUBTRACT ANY REDUNDANT LOAD AND THE SMALLER OF ANY NONCOINCIDENT HVAC LOADS. THIS CALC IS DONE AT EACH PANEL.
TOTAL ESTIMATED DEMAND AMPS: 77.7 A
TOTAL CONNECTED AMPS: 77.72 A
TOTAL ESTIMATED DEMAND LOAD: 28 kVA
TOTAL CONNECTED LOAD: 28.00 kVA
Power 28 kVA 100.00% 28 kVA
LOAD CLASSIFICATION CONNECTED LOAD DEMAND FACTOR ESTIMATED DEMAND
TOTALS*
LOAD SUMMARY
Total Amps: 77.78 77.78 77.78
Total Load: 9.33 kVA 9.33 kVA 9.33 kVA
-- 41 -- -- -- -- -- -- -- 1.17 1.17 -- -- -- -- -- -- -- 42 --
-- 39 -- -- -- -- -- -- -- 1.17 1.17 -- -- -- -- -- -- -- 40 --
1 37 MDA B-2 (BUS A) 20 A 3 12 12 12 0.37 1.17 1.17 0.42 12 12 12 3 20 A MDA B-1 (BUS A) 38 1
-- 35 EXISTING LOAD 20 A 1 -- -- -- 0 1.17 -- -- -- -- -- -- -- 36 --
-- 33 -- -- -- -- -- -- -- 0 1.17 -- -- -- -- -- -- -- 34 --
-- 31 EXISTING LOAD 30 A 2 -- -- -- 0 1.17 0.46 12 12 12 3 20 A FDSS-2 (BUS A) 32 1
-- 29 -- -- -- -- -- -- -- 0 1.17 -- -- -- -- -- -- -- 30 --
-- 27 EXISTING LOAD 30 A 2 -- -- -- 0 1.17 -- -- -- -- -- -- -- 28 --
-- 25 -- -- -- -- -- -- -- 0 1.17 0.49 12 12 12 3 20 A FDSS-1 (BUSA) 26 1
-- 23 EXISTING LOAD 30 A 2 -- -- -- 0 1.17 -- -- -- -- -- -- -- 24 --
-- 21 -- -- -- -- -- -- -- 0 1.17 -- -- -- -- -- -- -- 22 --
-- 19 EXISTING LOAD 30 A 2 -- -- -- 0 1.17 0.56 12 12 12 3 20 A SPARE (BUS A) 20 1
-- 17 -- -- -- -- -- -- -- 0 1.17 -- -- -- -- -- -- -- 18 --
-- 15 -- -- -- -- -- -- -- 0 1.17 -- -- -- -- -- -- -- 16 --
-- 13 EXISTING LOAD 60 A 3 -- -- -- 0 1.17 0.52 12 12 12 3 20 A SEC/JBA (BUS A) 14 1
-- 11 -- -- -- -- -- -- -- 0 1.17 -- -- -- -- -- -- -- 12 --
-- 9 -- -- -- -- -- -- -- 0 1.17 -- -- -- -- -- -- -- 10 --
-- 7 EXISTING LOAD 60 A 3 -- -- -- 0 1.17 0.48 12 12 12 3 20 A MDA A-1 (BUS A) 8 1
-- 5 -- -- -- -- -- -- -- 0 1.17 -- -- -- -- -- -- -- 6 --
-- 3 -- -- -- -- -- -- -- 0 1.17 -- -- -- -- -- -- -- 4 --
-- 1 EXISTING LOAD 60 A 3 -- -- -- 0 1.17 0.44 12 12 12 3 20 A MDA A-2 (BUS A) 2 1
K E Y
CKT
NO. LOAD DESCRIPTION
OCPD
AMPS P
WIRE
SIZE
H N G
VD
A B C VD
WIRE
SIZE
G N H
OCPD
P AMPS LOAD DESCRIPTION
CKT
NO.
K E Y
NOTES: MATCH EXISTING SCCR.
ISC UNKNOWN 0.00 kA
SCCR: EXISTING
LOCATION: COMPUTER ROOM BA120 WIRE: 4
FED FROM: 0 A/0P @ GROUND BUS PHASE: 3
ENCLOSURE: NEMA 1 SOLID NEUTRAL VOLTS: 120/208 Wye
MOUNTING: SURFACE SINGLE TUB MAIN: 225 A MLO
EXIST. PNL: PDU-B/D
CIRCUIT KEY NOTES:
*TOTAL DEMAND CALCS SUBTRACT ANY REDUNDANT LOAD AND THE SMALLER OF ANY NONCOINCIDENT HVAC LOADS. THIS CALC IS DONE AT EACH PANEL.
TOTAL ESTIMATED DEMAND AMPS: 0 A
TOTAL CONNECTED AMPS: 0.00 A
TOTAL ESTIMATED DEMAND LOAD: 0 kVA
TOTAL CONNECTED LOAD: 0.00 kVA
Power 0 kVA 0.00% 0 kVA
LOAD CLASSIFICATION CONNECTED LOAD DEMAND FACTOR ESTIMATED DEMAND
TOTALS*
LOAD SUMMARY
Total Amps: 0.00 0.00 0.00
Total Load: 0.00 kVA 0.00 kVA 0.00 kVA
-- 41 -- -- -- -- -- -- -- 0 0 -- -- -- -- -- -- -- 42 --
-- 39 -- -- -- -- -- -- -- 0 0 -- -- -- -- -- -- -- 40 --
37 FDSS-2 (BUS B) 20 A 3 12 12 12 0 0 12 12 12 3 20 A FDSS-1 (BUS B) 38
-- 35 -- -- -- -- -- -- -- 0 -- -- -- -- 1 -- SPACE 36 --
-- 33 -- -- -- -- -- -- -- 0 0 -- -- -- -- -- -- -- 34 --
31 MDA B-1 (BUS B) 20 A 3 12 12 12 0 0 -- -- -- 2 0 A SPARE 32 --
-- 29 -- -- -- -- -- -- -- 0 0 -- -- -- -- -- -- -- 30 --
-- 27 -- -- -- -- -- -- -- 0 0 -- -- -- 2 30 A SPARE 28 --
25 MDA B-1 (BUS B) 20 A 3 12 12 12 0 0 -- -- -- -- -- -- -- 26 --
-- 23 -- -- -- -- -- -- -- 0 0 -- -- -- 2 30 A SPARE 24 --
-- 21 -- -- -- -- -- -- -- 0 0 -- -- -- -- -- -- -- 22 --
19 SPARE (BUS B) 20 A 3 12 12 12 0 0 -- -- -- 2 30 A SPARE 20 --
-- 17 -- -- -- -- -- -- -- 0 0 -- -- -- -- -- -- -- 18 --
-- 15 -- -- -- -- -- -- -- 0 0 -- -- -- -- -- -- -- 16 --
13 SEC/JBA (BUS B) 20 A 3 12 12 12 0 0 -- -- -- 3 60 A SPARE 14 --
-- 11 -- -- -- -- -- -- -- 0 0 -- -- -- -- -- -- -- 12 --
-- 9 -- -- -- -- -- -- -- 0 0 -- -- -- -- -- -- -- 10 --
7 MDA A-1 (BUS B) 20 A 3 12 12 12 0 0 -- -- -- 3 60 A SPARE 8 --
-- 5 -- -- -- -- -- -- -- 0 0 -- -- -- -- -- -- -- 6 --
-- 3 -- -- -- -- -- -- -- 0 0 -- -- -- -- -- -- -- 4 --
1 MDA A-2 (BUS B) 20 A 3 12 12 12 0 0 -- -- -- 3 60 A SPARE 2 --
K E Y
CKT
NO. LOAD DESCRIPTION
OCPD
AMPS P
WIRE
SIZE
H N G
VD
A B C VD
WIRE
SIZE
G N H
OCPD
P AMPS LOAD DESCRIPTION
CKT
NO.
K E Y
NOTES: MATCH EXISTING SCCR.
ISC UNKNOWN 0.00 kA
SCCR: EXISTING
LOCATION: COMPUTER ROOM BA120 WIRE: 4
FED FROM: 0 A/0P @ GROUND BUS PHASE: 3
ENCLOSURE: NEMA 1 SOLID NEUTRAL VOLTS: 120/208 Wye
MOUNTING: SURFACE SINGLE TUB MAIN: 225 A MLO
EXIST. PNL: PDU-D/D
Revisions: Date:
BID RFI 06/25/2026
ADDENDA DATA CENTER COOLING, Q.56 07/24/2026
CIRCUIT KEY NOTES: 1 - PROVIDE NEW BREAKER
*TOTAL DEMAND CALCS SUBTRACT ANY REDUNDANT LOAD AND THE SMALLER OF ANY NONCOINCIDENT HVAC LOADS. THIS CALC IS DONE AT EACH PANEL.
TOTAL ESTIMATED DEMAND AMPS: 185.8 A
TOTAL CONNECTED AMPS: 185.82 A
TOTAL ESTIMATED DEMAND LOAD: 154.488 kVA
TOTAL CONNECTED LOAD: 154.49 kVA
HVAC Cooling Only 154.488 kVA 100.00% 154.488 kVA
LOAD CLASSIFICATION CONNECTED LOAD DEMAND FACTOR ESTIMATED DEMAND
TOTALS*
LOAD SUMMARY
Total Amps: 185.82 185.82 185.82
Total Load: 51.50 kVA 51.50 kVA 51.50 kVA
-- 41 -- -- -- -- -- -- -- 0 -- -- -- -- -- -- -- -- 42 --
-- 39 -- -- -- -- -- -- -- 0 -- -- -- -- -- -- -- -- 40 --
-- 37 EXISTING LOAD 15 A 3 -- -- -- 0 -- -- -- -- 3 -- SPACE 38 --
-- 35 -- -- -- -- -- -- -- 0 1.25 -- -- -- -- -- -- -- 36 --
-- 33 -- -- -- -- -- -- -- 0 1.25 -- -- -- -- -- -- -- 34 --
-- 31 EXISTING LOAD 25 A 3 -- -- -- 0 1.25 0.36 12 -- 12 3 15 A ACCU-6 32 1
-- 29 -- -- -- -- -- -- -- 0 9.56 -- -- -- -- -- -- -- 30 --
-- 27 -- -- -- -- -- -- -- 0 9.56 -- -- -- -- -- -- -- 28 --
-- 25 EXISTING LOAD 35 A 3 -- -- -- 0 9.56 0.89 10 -- 8 3 50 A CRAC-6 26 1
-- 23 -- -- -- -- -- -- -- 0 2.47 -- -- -- -- -- -- -- 24 --
-- 21 -- -- -- -- -- -- -- 0 2.47 -- -- -- -- -- -- -- 22 --
-- 19 EXISTING LOAD 15 A 3 -- -- -- 0 2.47 0.84 12 -- 12 3 20 A ACCU-4 20 1
-- 17 -- -- -- -- -- -- -- 0 17.87 -- -- -- -- -- -- -- 18 --
-- 15 -- -- -- -- -- -- -- 0 17.87 -- -- -- -- -- -- -- 16 --
-- 13 EXISTING LOAD 125 A 3 -- -- -- 0 17.87 1.03 8 -- 3 3 90 A CRAC-4 14 1
-- 11 -- -- -- -- -- -- -- -- 2.47 -- -- -- -- -- -- -- 12 --
-- 9 -- -- -- -- -- -- -- -- 2.47 -- -- -- -- -- -- -- 10 --
-- 7 SPACE -- 3 -- -- -- -- 2.47 0.53 12 -- 12 3 20 A ACCU-1 8 1
-- 5 -- -- -- -- -- -- -- -- 17.87 -- -- -- -- -- -- -- 6 --
-- 3 -- -- -- -- -- -- -- -- 17.87 -- -- -- -- -- -- -- 4 --
-- 1 SPACE -- 3 -- -- -- -- 17.87 0.45 8 -- 3 3 90 A CRAC-1 2 1
K E Y
CKT
NO. LOAD DESCRIPTION
OCPD
AMPS P
WIRE
SIZE
H N G
VD
A B C VD
WIRE
SIZE
G N H
OCPD
P AMPS LOAD DESCRIPTION
CKT
NO.
K E Y
NOTES: MATCH EXISTING SCCR.
ISC UNKNOWN 0.00 kA
SCCR: EXISTING
LOCATION: ACTIVE STORAGE BA117 WIRE: 3
FED FROM: 0 A/0P @ GROUND BUS PHASE: 3
ENCLOSURE: NEMA 1 VOLTS: 480 Delta
MOUNTING: SURFACE SINGLE TUB MAIN: 400 A MCB
EXIST. PNL: A1
CIRCUIT KEY NOTES: 1 - PROVIDE NEW BREAKER.
*TOTAL DEMAND CALCS SUBTRACT ANY REDUNDANT LOAD AND THE SMALLER OF ANY NONCOINCIDENT HVAC LOADS. THIS CALC IS DONE AT EACH PANEL.
TOTAL ESTIMATED DEMAND AMPS: 185.8 A
TOTAL CONNECTED AMPS: 185.82 A
TOTAL ESTIMATED DEMAND LOAD: 154.488 kVA
TOTAL CONNECTED LOAD: 154.49 kVA
HVAC Cooling Only 154.488 kVA 100.00% 154.488 kVA
LOAD CLASSIFICATION CONNECTED LOAD DEMAND FACTOR ESTIMATED DEMAND
TOTALS*
LOAD SUMMARY
Total Amps: 185.82 185.82 185.82
Total Load: 51.50 kVA 51.50 kVA 51.50 kVA
-- 41 -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- 42 --
-- 39 -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- 40 --
-- 37 SPACE -- 3 -- -- -- -- -- -- -- -- 3 -- SPACE 38 --
-- 35 -- -- -- -- -- -- -- -- 2.47 -- -- -- -- -- -- -- 36 --
-- 33 -- -- -- -- -- -- -- -- 2.47 -- -- -- -- -- -- -- 34 --
-- 31 SPACE -- 3 -- -- -- -- 2.47 0.81 12 -- 12 3 20 A ACCU-5 32 1
-- 29 -- -- -- -- -- -- -- 0 17.87 -- -- -- -- -- -- -- 30 --
-- 27 -- -- -- -- -- -- -- 0 17.87 -- -- -- -- -- -- -- 28 --
-- 25 EXISTING LOAD 15 A 3 -- -- -- 0 17.87 0.73 8 -- 3 3 90 A CRAC-5 26 1
-- 23 -- -- -- -- -- -- -- 0 2.47 -- -- -- -- -- -- -- 24 --
-- 21 -- -- -- -- -- -- -- 0 2.47 -- -- -- -- -- -- -- 22 --
-- 19 EXISTING LOAD 0 A 3 -- -- -- 0 2.47 0.69 12 -- 12 3 20 A ACCU-3 20 1
-- 17 -- -- -- -- -- -- -- 0 17.87 -- -- -- -- -- -- -- 18 --
-- 15 -- -- -- -- -- -- -- 0 17.87 -- -- -- -- -- -- -- 16 --
-- 13 SPARE 125 A 3 -- -- -- 0 17.87 0.71 8 -- 3 3 90 A CRAC-3 14 1
-- 11 -- -- -- -- -- -- -- 0 1.25 -- -- -- -- -- -- -- 12 --
-- 9 -- -- -- -- -- -- -- 0 1.25 -- -- -- -- -- -- -- 10 --
-- 7 EXISTING LOAD 15 A 3 -- -- -- 0 1.25 0.32 12 -- 12 3 15 A ACCU-2 8 1
-- 5 -- -- -- -- -- -- -- 0 9.56 -- -- -- -- -- -- -- 6 --
-- 3 -- -- -- -- -- -- -- 0 9.56 -- -- -- -- -- -- -- 4 --
-- 1 EXISTING LOAD 25 A 3 -- -- -- 0 9.56 0.56 10 -- 8 3 50 A CRAC-2 2 1
K E Y
CKT
NO. LOAD DESCRIPTION
OCPD
AMPS P
WIRE
SIZE
H N G
VD
A B C VD
WIRE
SIZE
G N H
OCPD
P AMPS LOAD DESCRIPTION
CKT
NO.
K E Y
NOTES: MATCH EXISTING SCCR.
ISC UNKNOWN 0.00 kA
SCCR: EXISTING
LOCATION: ACTIVE STORAGE BA117 WIRE: 3
FED FROM: 0 A/0P @ GROUND BUS PHASE: 3
ENCLOSURE: NEMA 1 VOLTS: 480 Delta
MOUNTING: SURFACE SINGLE TUB MAIN: 400 A MCB
EXIST. PNL: B1
| Sheets |
| 32-EN100 - BASEMENT PLAN - ELECTRICAL |
| 32-EN302 - ELECTRICAL SCHEDULES |
File details come from the government source that posted it. Updated .