Attachment 01- Tech Questions Tracker - Pitts-Heinz Partial.docx
DOCX document 256 KB Posted
- Solicitation number
- 36C77626R0071
About this file
This is a Technical Questions and Solicitation Responses Tracking Sheet for Solicitation 36C77626R0071, EHRM Infrastructure Upgrades at Pittsburgh-Heinz, PA, managed by the Department of Veterans Affairs Technology Acquisition Center Austin. The document compiles 150 contractor questions and corresponding responses from the design team, contracting officer, and facility representatives, addressing technical clarifications across multiple disciplines including security systems, HVAC, telecommunications, electrical, fire protection, civil/site work, and architectural finishes.
Key substantive responses address critical project parameters: card access systems and camera work will utilize existing Miller Information Systems infrastructure; all new data cabling shall be Category 6A with no new Category 5e installation; fire extinguisher cabinets require Class C extinguishers; new fiber backbone will be provided to residential villas (Buildings 63-68) with no interior work required; the project schedule is not required with the proposal; UPS systems are Powerware 9315 units (480V, 3-phase); handhole specifications require 36"x26"x26" for less than four 4-inch conduits and 48"x48"x36" for four or more conduits; duct bank concrete encasement should be 2500 PSI per telecommunications details; contractors must assume 20% of outlets will require new pathways due to 40% conduit fill limitations and 25% will require surface mount raceways for fished cable locations; all hazmat abatement should carry equivalent allowances across bidders; and the proposal due date was extended to July 7, 2026. Numerous questions remain marked "VA to advise" regarding security system specifics, after-hours work requirements, utility outage procedures, site staging logistics, temporary cooling during HVAC cutover, and other operational parameters pending facility clarification.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL QUESTIONS AND
| SOLICITATION #: |
| 36C77626R0071 |
| RESPONSES TRACKING SHEET |
| PROJECT TITLE: |
| 646A4-22-700 | EHRM Infrastructure Upgrades Pittsburgh-Heinz, PA |
| # |
| CONTRACTOR QUESTION |
| VA RESPONSE |
| 1 |
| Is the card access system on site, on prem or cloud? |
| Awen: VA to advise. |
| 2 |
| What type of Acre card access system is onsite? (example access it, DNA fusion, ac tyro, omnis, act365, premisys, or matrix frontier) |
Awen: VA to advise.
| 3 |
| Will all of the card access and camera work be going through Miller Information Systems? |
Awen: VA to advise.
| 4 |
| Please provide location of condensing units being removed and replaced as indicated by sheet notes 6 & 7 on DWG 51-MN400 and sheet notes 1& 2 on DWGs 51-MN401, 51-MN402, & 51-MN403. Neither the existing condensing units or the existing refrigerant piping is shown. Notes indicate to demo existing refrigerant piping and install new refrigerant piping in place of existing piping which is not shown. |
IMEG: The split system replacement scope in rooms which do not show the associated condensing unit or pipe routing was added at the end of the project and we did not have the locations of those units verified at that time.
| 5 |
| Please provided HVAC Equipment schedule drawings. |
IMEG: Please see sheet 00-MG600.
| 6 |
| Can you please confirm that a project schedule is not needed for the bid proposal and is only needed post-award? |
| No project schedule is required |
| 7 |
| Specification 087100 Door Hardware, Section 3.05 refers to a hardware |
consultant. Is this consultant to be provided by the Owner, or should the door vendor include the consultant in their pricing.
Door vendor to include in their consultant pricing.
| 8 |
| Specification 087100 Door Hardware, Please provide the types of cores |
and keyways that are to be provided for this project. Is the subcontractor to provide the final cores and keying, or is there an existing keying system.
Awen: GC to provide Standard Core Best Access System door cores to match existing Facility Standards to VA Locksmith for final keying and station coordination.
| 9 |
| Specification 087100 Door Hardware: Can more information be provided |
on the door hardware sets, as some of the provided information is vague.
Specifically, Integral Hinge Guard Channel, Adjust-Screws, and In-Hinge Access Panel, and the BHMA numbers.
Awen: Integral Hinge Guard Channel = is a feature that comes with a Continuous Hinge that protects the assembly, Adjust-Screws = Adjustable Screws, In-Hinge Access Panel = Concealed raceway in the door’s hinge for an electrified lock, BHMA numbers = confirm with VA to match existing Facility Standards
| 10 |
| Specification 104413 Fire Extinguisher Cabinets: Please provide if white |
enamel will work instead of primed for exterior of cabinets?
Awen: VA to provide.
| 11 |
| Specification 104413 Fire Extinguisher Cabinets: This specification does |
not reference fire extinguishers, nor is there a specification specifically for fire extinguishers. Please clarify who is responsible for procuring the fire extinguishers. If the CM is responsible, please provide specification and / or size requirements.
Utilize Class C Fire Extinguisher
| 12 |
| Drawing 50-AE401 & 50-AE601: Details on 50-AE401 show rooms |
GA130A New TR and GA130B New Storage. The Room Finish Schedule on 50-AE601 only reference room GA130A. Please provide room finishes for room GA130B New Storage.
Awen: GA130B confirm with VA to match existing VA Facility Standard to match existing Storage Rooms standards.
| 13 |
| Drawing 70-AE401: In Detail E4 of the floor plan, Note A10 shows a |
section in the CMU wall fill; however, the referenced detail shows a stud wall. Please advise which material should be used.
Awen: New wall fill should match adjacent existing wall material and finishes. Align with adjacent wall faces.
| 14 |
| Specification 090600 – Schedule for Finishes: Please provide additional |
information regarding the linoleum flooring.
Awen: Reference the Project Manual for 090600 Schedule of Finishes for BOD VCT.
| 15 |
| Due to the size and nature of this job, we kindly request an extension of |
the RFI submission date and bid submission date of two weeks each.
The proposal due date has been extended to 7/7/2026.
| 16 |
| Will Special Inspections for firestop (078400) will be contracted to the General Contractor, or would this be directly to the VA? |
| Awen: VA to advise. |
| 17 |
| Once the New Fiber enters the building are we providing new 4” Conduit and Maxcell to the TR’s. |
| IMEG: 4” conduit and textile innerduct are for underground and exterior to interior pathway transitions only. Interior 4” conduits are not required. Corrugated innerduct is acceptable for interior pathways. |
| 18 |
| General Note 3 on Drawing 00-TS101 states that on any new Conduit runs there will be 2 spare conduits there are several places it only calls for 2 Conduits. Steam Tunnell. Building 52,Building 53,Building 49 with no spares. |
| IMEG: The main ring underground pathway will account for spare capacity. Conduit pathways that branch off the ring for building entry pathways are reduced to (2) 2” conduits. |
| 19 |
| The drawings state that the cable will be run in cable tray is all the cable tray existing as the drawings show no new cable tray except in the TR’s. |
| IMEG: Intent is to utilize existing cable tray within corridors to the fullest extent possible. Supplement pathways with new non-continuous supports, as necessary. |
| 20 |
| On the Legend on drawing 00-TG700 it calls for all voice cabling to be Cat5E.How and where is this cabling being terminated. |
| IMEG: All active voice/analog cabling shall remain in place. All inactive voice/analog cabling shall be removed in full. Voice cabling in patient rooms will remain, in lieu of Technology Cabling Plan on 00-TG000 stating to remove and replace. Telecommunications Outlet Schedule on 00-TG700 does not indicate installation of new Category 5e cable. |
| 21 |
| In the Data Center there is no designation what type of Cabinet’s or Rack’s should be used. Are they SC-CAB-1, SC-ER-1,SC-ER-3. |
| IMEG: New cabinets shown on 32-TN401 are SC-CAB-1 on 00-TG700. |
| 22 |
| Looking through the documents, it seems to me that the lab testing will be hired by the General Contractor. Can you confirm that this is correct? |
| Awen: Confirmed necessary lab testing to be hired by the GC. |
| 23 |
| EHRM Infrastructure Upgrades Pittsburgh-Heinz, PA project requires BIM services. Do you mind sending me a list of bidders for the project? |
| Amendment 0002 has list of site visit attendees. |
| 24 |
| Will this project be tax exempt? If so, will the government provide a certificate? |
| Awen: VA to advise. |
| 25 |
| Page 9 of 81 of the solicitation, paragraph 2.B references submitting a project schedule, but the remaining proposal instructions and evaluation criteria don't mention submitting a schedule with the technical proposal. Please confirm a project schedule is not required to be submitting with our technical proposal. |
| Statement in Amendment 0004 says that portion has been removed. No project schedule is required to be submit with proposal. |
| 26 |
| While CAT 6A or Category 6A (6a) appears in multiple places in both the Specifications and the Drawings, CAT 5E or Category 5E (5e) does not appear in the 27xxxx sections of the Specifications and only on Sheet 00-TG700 of the drawings dated 06/27/2025. Are CAT 5E (5e) cables to be installed for Voice, or are all cables to be CAT 6A? |
| IMEG: No new Category 5e cabling will be installed for Voice. All new cabling will be Category 6A for data ports. |
| 27 |
| If the answer to question above is that CAT 5E cables are to be installed for Voice, configuration types C8-4-E & C12-6-E do not have the number cable types (CAT 6A or CAT 5E) listed in the Telecommunications Outlet Schedule on Sheet 00-TG700. What are the number of cable types for these configurations, or any other that are blank or listed as (varies)? |
| IMEG: No new Category 5e cabling will be installed for Voice. All new cabling will be Category 6A for data ports. Existing to remain voice ports will be re-installed in new cover plate if location is to include replacement of data cabling. |
| 28 |
| Manufacturer Acceptability |
Please confirm whether Honeywell security platforms (including Access Control, Video Management, enterprise head end software, or integrated security solutions) are acceptable as alternates or equals to the specified base building systems, either as primary systems or through integration.
Awen: Security scope for EHRM must be compatible with existing base building system. Base building access controls and video surveillance system recently upgraded. VA security to advise on current installed system.
| 29 |
| Alternate or Additive Scope |
Will the bid include any additive alternates, voluntary alternates, or allowances related to security, access control, video, or infrastructure upgrades that are not shown in the current drawings and specifications?
Awen: See sheet 00-TY001 for security allowances to carry into bid, to be provided as credit back to VA if unused. This is included to cover unforeseen conditions and scope of the existing system.
| 30 |
| Future Phases or Deferred Scope |
Are there any future phases, deferred security upgrades, or planned expansions anticipated that may be awarded under this same contract, task order, or a related package, even if not included in the current bid set?
Awen: VA to advise.
| 31 |
| Enterprise / Head End System Upgrades |
Are any enterprise level security upgrades planned or under consideration (e.g., command center functionality, enterprise access control management, monitoring, analytics, cybersecurity, or system consolidation) that would be separate from base building device standards?
Awen: VA to advise.
| 32 |
| Access Control System Expansion |
While drawings indicate existing ACRE access control panels are to remain, please confirm whether any of the following are included or anticipated:
| • | Panel expansions or replacements |
| • | Software or licensing upgrades |
| • | Server or head end refreshes |
| • | Capacity increases to support new devices |
| Awen: Reuse of existing access control panels is required for new PACs devices where possible. Submit shop drawings showing existing capacity and required expansion based on current availability to AE for review. Software licensing to be provided for all new cameras and devices where required. No upgrades to base building access controls or security system are anticipated as part of EHRM project. |
| 33 |
| Video System Scope & Flexibility |
For new cameras and SSTV devices:
| • | Are these strictly required to be add ons to the existing Avigilon Unity system, or |
| • | Is there any flexibility to propose alternate VMS platforms or enterprise overlays? |
| Awen: Scope of EHRM is limited to new VSS cameras on existing camera system. |
| 34 |
| Integration & Interoperability Responsibility |
Please clarify whether the contractor is responsible for system integration, middleware, or interoperability between existing systems and new devices, and whether alternate integration platforms are acceptable.
Awen: VA to advise.
| 35 |
| Confirmation of Final Scope |
If no additional scope, alternates, integration responsibilities, or future phases are anticipated, please confirm that the current documents represent the final and complete security scope for this project.
Awen: VA to advise.
| 36 |
| What version of Acre access control is running? |
| Awen: VA to advise. |
| 37 |
| What version of Avigilon is running? |
| Awen: VA to advise. |
| 38 |
| Are motion sensors required in the closets? |
| Awen: Yes. |
| 39 |
| Will there be a way to locally arm and disarm the closets? |
| Awen: REX motion sensors to be provided for all new TR doors. Refer to (TY’) security drawings. |
| 40 |
| What is the preferred locking type for the closet doors? I noticed during the walkthrough that electric strikes are being used? |
| Awen: Please clarify which “closet doors” are being referenced. |
| 41 |
| Should the security vendor supply licensing for the newly added cameras and readers? |
| Awen: Yes. |
| 42 |
| There are multiple Duct Bank Details shown on the Drawings. 05-Civil Drawing 00-CS502 has Duct Bank Details that differ from the 16-Telecommunication Drawing 00-TG500 Duct Bank Details. Please confirm what Duct Bank Details we are to use for the installation of the Communication Conduits shown on the Utility, Erosion and Sedimentation Control Drawings 00-CE101 through 00-CS109. |
| Langan: Contractor to use Duct Bank Details on 00-TG500. |
IMEG: Refer to Technology details for conduit installation, spacing, and tracer requirements. Defer to Civil details if discrepancy is present for concrete, depth, and backfill requirements.
| 43 |
| The “Proposed Communications Structure” on Drawings 00-CE101 through 00-CE109 say “Refer to 16-Telecommunication Section for Structure Details”. We cannot find any Communication Structure details on 16 Telecommunication Drawings. However, there are Details on 05 Civil Drawing 00-CS502 – for Telecommunications Manhole and Underground Concrete Pullboxes. The Manholes match the physical dimensions shown on the Site Plans. The details for the Pullboxes do not have any dimensions but refer to the specifications. Please confirm the Underground Manholes and Concrete Pull Box Details that the contractor will need to provide. |
| Langan: MEP to confirm that the proposed manhole detailed is appropriate for the services required. Pull boxes to be according to the 16-Telecommunication Section drawings. Refer to 00-TS101 and 00-TG700. |
| 44 |
| When reviewing the specifications for the Underground Manholes and Pullboxes we found several references to Section 26 05 41 – Underground Electrical Construction however we cannot find Section 26 05 41 in the Specifications. Please provide Section 26 05 41 of the Specifications. |
| IMEG: Specification 26 05 41 will be added. |
| 45 |
| 05-Civil Drawings 00-CE100 through 00-CE109 – Sequence of Construction Note. 5 and Utility Installation Requirements Note 3. State that “Daily Excavation shall be limited to the length of the conduit placement, pug installation and backfilling that can be completed the same day.” Per the details all the Duct Banks will be encased in Concrete. With concrete cure times we will not be able to backfill the trench the same day. Are all concrete encased trenches able to be treated as per Note 6 of the Utility Installation Requirements which allows backfilling to be delayed for six days. |
| Langan: Concrete-encased trenches may be treated as per Note 6 of the Utility Installation Requirements. All requirements of Note 6 are to be followed. All temporary trench spoils to be utilized for backfill must be placed upstream of trench and silt sock placed downstream of stock piles until trench is backfilled and stabilized. |
| 46 |
| Drawing 32-EN100 references disconnecting and reconnecting the fire alarm for the crac units so that they can be replaced. Please confirm that power will need to be disconnected from these units as well and that the circuit referenced on the drawing is the existing circuit to the unit and not a new power feed. |
| IMEG: New (smaller) electrical circuits shall be required to serve the replacement CRAC units. Additional circuit information shall be provided. |
| 47 |
| We would like to formally request a bid extension to allow our vendors adequate time to provide the best possible pricing for a project of this magnitude. |
| Awen: VA to advise. |
| 48 |
| Will the Division 27 Contractor own the Fiber Optic and Copper patch cords and the installation. |
| IMEG: Division 27 furnish fiber and copper patch cords. VA will install. |
| 49 |
| Where the drawings show 48,20,12,16,28,32 and 24 cables at a location what is intent of these cables. Are they terminating in the Ceiling or are they dropping down power poles or columns and feeding Modular furniture. |
| IMEG: All locations that show 12+ data cables are one-for-one data replacements and should reuse the existing pathway infrastructure. Contractor shall field verify existing pathway conditions at each location, as it varies by location. |
| 50 |
| Is the Fire rated Plywood in the Telcom Closets by the Division 27 Contractor or the General Contractor. |
| IMEG: General Contractor |
| 51 |
| Will all the existing Fiber Optic Backbone cable be Demoed after new is up and working. |
| IMEG: Yes. Refer to Phasing Plan on 00-TG000 |
| 52 | |
| Are pre-insulated linesets with 1in insulation and UV coating acceptable to use for the mini-split refrigeration piping? | |
| a. | If so, does the exterior pipe still have to be jacketed because the linesets have a factory UV coating on them? |
| IMEG: Unless the VA approves otherwise, the refrigerant piping shall be provided as specified. Specifications are provided by the VA, edited by the design team, reviewed and approved by VA for issuance. |
| 53 |
| The spec does not mention copper propress for the chilled water piping. Is it acceptable to use copper propress fittings for heating and chilled water pipe less than or equal to 2” in diameter? Or does small bore pipe have to be sweat? |
| IMEG: Unless the VA approves otherwise, the chilled water piping shall be provided as specified. Specifications are provided by the VA, edited by the design team, reviewed and approved by VA for issuance. |
| 54 |
| The spec does not mention grooved fittings for the chilled water piping. Is it acceptable to use grooved fittings on steel pipe for heating and chilled water pipe 2-1/2” and up? Or does the whole system have to be welded? |
| IMEG: Unless the VA approves otherwise, the chilled water piping shall be provided as specified. Specifications are provided by the VA, edited by the design team, reviewed and approved by VA for issuance. |
| 55 |
| The specs call for condensate lines to be sweat copper. During the site visit we observed uninsulated PVC being utilized for the condensate lines in the existing TRs. Is it acceptable to use uninsulated PVC for the condensate drains? |
| IMEG: Unless the VA approves otherwise, the condensate piping shall be provided as specified. Specifications are provided by the VA, edited by the design team, reviewed and approved by VA for issuance. In addition, PVC is not acceptable for use in return air plenums. |
| 56 |
| Is there a basis of design for the CRAC units? |
| IMEG: There is a basis of design manufacturer who provided selections of the equipment used for planning and scheduling. The VA has asked that manufacturers and model numbers be removed from the documents. |
| 57 |
| Is it acceptable to use non-penetrating support stands for the new condensing units that will be located on the roof? |
| IMEG: Unless the VA approves otherwise, supports shall be provided as required in the documents. |
| 58 | |
| There are condensing units that will be demo’d and they are on roof rails. | |
| a. | Are we to demo the existing rails? |
b. Are we to abandon the rails in place and provide a permanent cap?
IMEG: The expectation is that the rails would remain in order to eliminate roofing concerns. Any penetrations of the rails would be sealed.
| 59 | |
| There are existing roof portals that may no longer be utilized due to the relocation of existing TRs | |
| a. | Are we to demo the existing portals? |
| Awen: Please clarify the roof portals being referenced. |
| 60 |
| Can you confirm whether flow fill is required in all areas or only in travel areas where ductwork will be installed? The detail notes indicate “as depicted,” but I am being told there is nothing clearly shown on the plans. |
| Langan: All conduit to be concrete-encased. |
| 61 |
| I noted that 00-CS502 calls out 2000 PSI, while 00-TG500 shows 2500 PSI. However, the trench patch detail on 00-CS501 does not indicate any flow fill. Can you please clarify the intent? Typically, we see flow fill required in travel areas only, with excavated spoils used for backfilling in soil restoration areas. In other words, if it is not under asphalt or travel areas, it typically does not require flow fill. (please clarify) |
| Langan: To be 2500 psi per 00-TG500. All conduit to be concrete-encased. |
| 62 |
| Please provide an abatement report for the tested hazardous materials. |
| Awen: December 12, 2023, Hazardous Materials Report, provided as final bid set. |
| 63 |
| Are there additional ICRA walls required for the project in addition to what is shown on the construction drawings for the TR Rooms? Are ICRA Carts the only requirement for the work to be performed in the corridors? |
| Awen: VA to advise. |
| 64 |
| Please clarify what work will need to be done off hours. |
| Awen: VA to advise. |
| 65 |
| Are there existing sprinkler drawings showing the quantity of new heads required for removal and replacement with upright heads? |
| IMEG: No, plan for 2 heads per TR. |
| 66 |
| Are there soil borings for the site excavation? |
| Awen: no soil borings were completed for site excavation. |
| 67 |
| Please clarify what traffic control will be required for the new sitework. |
| Awen: VA to advise. |
| 68 |
| Please clarify the roofing warranty requirements. Please provide a specification for the roofing. |
| Awen: VA to advise. |
| 69 |
| Please provide a detail for what is required for the new site equipment pads. |
| IMEG: Reference Sheet00-MG500 Detail 03 Mechanical Sheets include Equipment Support detail. |
| 70 |
| Upon reviewing the drawings, specifically the partial electrical riser diagrams, several existing normal and emergency panels are noted for replacement. For example, on page 50-EN401, ENLARGED PLAN – FIRST FLOOR – TR 1A129, Detail C5, Note 1 states: “Replace existing panel with new 54 circuit and 200 MCB panel.” |
Please confirm whether this note applies in all instances. If so, please provide the existing panel information so we can accurately quote these replacements.
IMEG: Note applies in all instances of its use on the construction drawings. The existing electrical panelboard does not have sufficient pole space to accommodate the installation of the new circuit breaker and thusly needs to be replaced. The contractor shall field verify the existing branch circuit breaker ratings/quantities and panel kAIC rating and provide new panelboard to match.
| 71 |
| Please provide additional information on UPS’s A and B. During the site walk, access to this space was restricted. Pictures of the existing units would be greatly appreciated. UPS nameplate information, battery count, etc. |
| IMEG: Both ‘UPS-A’ and ‘UPS-B’ are Powerware 9315, 480V -3ph-3wire Uninterruptible Power System, system # 9315 – 300, model 300 with three battery sections. |
| 72 |
| Site drawings show the installation of new handholes designated as “PW-HH-1” according to the technology equipment schedule. This handhole is a Hubbel/Quazite #PG2424BB24 with an associated top. The depth of these boxes is 24 inches. Telecom ductbank details call out for a maximum top-to-conduit depth of 30”. Handhole details show stubbing into the open bottom of PW-HH-1 Handhole. Given that the underground duct banks are 4” conduit, a standard radius elbow will not allow for an as-designed installation. Given that information, please advise on the following. |
| a. | No specifications were supplied for the installation of the underground duct; it has been assumed that any radius fittings would be rigid steel, and 90s would be sweep radius fittings. Does the VA have a minimum sweep radius in mind when installing underground ducts? |
| b. | Full NEC sweep radius cannot be achieved at handhole stub-up due to depth constraints. Will the VA accept a new maximum depth to the top of the conduit to accommodate a sweep radius into the bottom of the proposed Handhole? For Bidding purposes, can the VA supply a new maximum depth? |
| IMEG: The maximum 30-inch depth to top of conduit applies between handholes and pull boxes. Conduits may be routed deeper in the immediate vicinity of handholes as required to accommodate long-radius sweeps and manufacturer-recommended bend radii. As an alternative, provide a deeper handhole (36” or 48” depth). |
| 73 |
| Mechanical Drawing 32-MN402; General Note #2: calls for the Temperature Control Contractor to |
coordinate the location of all drip pans for the leak detection monitoring in the TR rooms.
a. Please identify how many drip pans are to be installed for each of the TR rooms for each Building.
IMEG: Assume one pan per TR
| 74 |
| Mechanical Drawing 32-MN402; General Note #4: calls for the Temperature Control Contractor to |
coordinate all Rack-Mounted Sensors with the Telecommunications Contractor and is responsible to integrate these into the Facility Controls System. Also, Mechanical Drawing 00-MG700; detail #1: shows a Rack/Cabinet Temperature per Rack.
a. Please identify how many Rack Temperature/Humidity Sensors are to be installed. Does this include any Existing Racks?
b. 00-MG700; detail #1 is the only Control Diagram showing these sensors. Is this only for Building #32 Computer Room BA120; CRAC-1,2,3,4,5, and 6 units or is it a requirement for all Racks? Is this sensor to be by the Temperature Control Contractor or by the Telecommunications Contractor?
c. These notes have been found on the Enlarged Plans for Buildings # 32, 49, 51, 69, 70, 71 only. Are these requirements needed for buildings #52 and 53?
IMEG:
a. Each new rack in the data center shall have three sensors.
b. It is only for Building 32 Computer Room BA120. TR racks do not require it. Sensor is expected to be provided by the controls contractor.
c. Please disregard notes for any buildings or rooms other than Building 32 Computer Room BA120.
| 75 | |
| Upon reviewing the drawings, specifically the partial electrical riser diagrams, several existing normal and emergency panels are noted for replacement. For example, on page 50-EN401, ENLARGED PLAN – FIRST FLOOR – TR 1A129, Detail C5, Note 1 states: “Replace existing panel with new 54 circuit and 200 MCB panel.” | |
| a., | Please confirm whether this note applies in all instances. If so, please provide the existing panel information so we can accurately quote these replacements. |
| IMEG: Note applies in all instances of its use on the construction drawings. The existing electrical panelboard does not have sufficient pole space to accommodate the installation of the new circuit breaker and thusly needs to be replaced. The contractor shall field verify the existing branch circuit breaker ratings/quantities and panel kAIC rating and provide new panelboard to match. |
| 76 |
| Please provide additional information on UPS’s A and B. During the site walk, access to this space was restricted. Pictures of the existing units would be greatly appreciated. UPS nameplate information, battery count, etc. |
| IMEG: Both ‘UPS-A’ and ‘UPS-B’ are Powerware 9315, 480V -3ph-3wire Uninterruptible Power System, system # 9315 – 300, model 300 with three battery sections. |
| 77 |
| Site drawings show the installation of new handholes designated as “PW-HH-1” according to the technology equipment schedule. This handhole is a Hubbel/Quazite #PG2424BB24 with an associated top. The depth of these boxes is 24 inches. Telecom ductbank details call out for a maximum top-to-conduit depth of 30”. Handhole details show stubbing into the open bottom of PW-HH-1 Handhole. Given that the underground duct banks are 4” conduit, a standard radius elbow will not allow for an as-designed installation. Given that information, please advise on the following. |
| a. | No specifications were supplied for the installation of the underground duct; it has been assumed that any radius fittings would be rigid steel, and 90s would be sweep radius fittings. Does the VA have a minimum sweep radius in mind when installing underground ducts? |
| b. | Full NEC sweep radius cannot be achieved at handhole stub-up due to depth constraints. Will the VA accept a new maximum depth to the top of the conduit to accommodate a sweep radius into the bottom of the proposed Handhole? For Bidding purposes, can the VA supply a new maximum depth? |
| IMEG: The maximum 30-inch depth to top of conduit applies between handholes and pull boxes. Conduits may be routed deeper in the immediate vicinity of handholes as required to accommodate long-radius sweeps and manufacturer-recommended bend radii. As an alternative, provide a deeper handhole (36” or 48” depth). |
| 78 |
| What is the current Camera make / model being used? |
| Awen: VA to advise. |
| 79 |
| What Camera make / model is preferred for the upgrade? |
| Awen: VA to advise. |
| 80 |
| Do you require individual licenses for the new cameras? |
| Awen: Yes. |
| 81 |
| Please provide specifications and sizes for in-ground boxes for green space and parking lot. |
| Langan: Refer to 00-TS101. Langan defers to Telecommunications plans regarding structure schedule and in-ground boxes. |
| 82 |
| Please provide building entry details for the 4” site conduits. |
| IMEG: For instances where building conditions do not allow for a weather sealed underground building penetration, transition conduits above ground and route up exterior wall. Terminate conduits in a building mounted pull box. Pull box height to be coordinated with interior conditions to allow for interior cable routing. |
| 83 |
| Please verify that the fiber backbone interior to the buildings does not require conduit as conduit is currently not indicated. Please provide conduit sizes if conduit is required. |
| IMEG: Interior conduit not required. Corrugated innerduct is acceptable for protected interior pathways. |
| 84 |
| Please verify that the grounding backbone interior to the buildings does not require conduit as conduit is currently not indicated. Please provide conduit sizes if conduit is required. |
| IMEG: not required |
| 85 |
| Drawing 32-EN301 – Please verify which feeders are new on the riser. Or all feeders on the riser existing. |
| IMEG: All electrical feeders are existing to remain. Only the disconnecting and reconnecting of the existing feeders is required per sheet note #1. |
| 86 |
| Drawing 32-EN301 - Please verify if the feeds to the new UPS are existing to be disconnected and reconnected or new. |
| IMEG: Correct, existing electrical feeders need only be disconnected and then reconnected to new UPS’s. |
| 87 |
| Please confirm the existing security system manufacturer (PACS). |
| Awen: PACS system has undergone recent upgrades per AE understanding, VA to confirm ACRE system is still campus standard. |
| 88 |
| Please confirm the existing fire alarm system manufacturer. If there is incumbent fire alarm contractor, please provide contact information. |
| IMEG: The existing fire alarm system manufacturer is “Fike.” No information has been given to the EOR regarding an incumbent fire alarm contractor. |
| 89 |
| Lightning Protection specifications were included in the project manual, but no apparent new lightning protection work was indicated on the plans. Please verify if lightning protection scope is needed on this project. |
| IMEG: No lightning protection scope is currently in the project. |
| 90 |
| Please confirm the manhole size needed. The size indicated on 00-CS502 is inadequate for the sixteen conduits needed. |
IMEG to review Detail. Detail may need to be revised.
| 91 |
| After-Hours Work, Notifications, Phasing, and Room Turnover Requirements |
Contract documents reference multiple notification periods for after-hours work, shutdowns, and outages. Please clarify the required notice periods for each activity type and identify the governing requirement. Additionally, the drawings limit construction to three telecom rooms at one time and require completion of each telecom room scope within ten calendar days unless approved by the VA. Please confirm whether the ten-day duration includes abatement, demolition, architectural construction, mechanical and electrical work, security installation, cabling, testing, inspections, punch list activities, and VA OIT cutovers.
Awen: VA to advise.
| 92 |
| Utility Shutdowns, Outages, and Panel Replacement Coordination |
Please define utility outage classifications, required notification periods, allowable outage windows, and sequencing restrictions for electrical, HVAC, telecommunications, fire alarm, fire protection, security, and plumbing systems. Clarify outage requirements associated with panel replacements, new telecom panels, feeder modifications, and any temporary power requirements.
Awen: VA to advise.
| 93 |
| Contractor Staging, Storage, Parking, and Site Logistics |
Please identify approved contractor laydown areas, material storage areas, loading/unloading zones, dumpster locations, temporary office locations, and personnel parking locations. Confirm any restrictions associated with deliveries, working hours, access routes, and elevator use.
Langan: In order to remain under 1 acre to not trigger a NPDES permit, the laydown area must remain at or under 8,600 SF. See below for the recommended area for the laydown area in the parking lot northwest of building #70, located near the entrance to the site.
| 94 |
| Data Center BA120 Scope, WAN Upgrades, and VA OIT Responsibilities |
Provide the complete contractor scope associated with BA120 and WAN infrastructure upgrades, including rack modifications, fiber terminations, cabinet work, interconnectivity, outage sequencing, after-hours requirements, contractor versus VA OIT responsibilities, cutovers, testing, and acceptance criteria.
IMEG: Contractor is responsible or all infrastructure and cabling requirements. VA Migration team will assist with all active equipment requirements. Contractor to work with VA to accommodate all migration activities.
| 95 |
| BAS/DDC Integration, Controls Vendor, and Monitoring Requirements |
Identify the existing BAS/DDC platform, controls manufacturer, service provider, licensing requirements, network ownership, integration responsibilities, monitoring points, alarm requirements, trending requirements, and commissioning responsibilities.
IMEG: VA to confirm current vendor.
| 96 |
| Physical Security Integration, Vendor Coordination, and Access Control Requirements |
Provide existing Acre/Miller system architecture, panel capacities, switch capacities, head-end locations, security vendor requirements, access control integration requirements, and a door-by-door security hardware matrix.
Awen: VA to advise.
| 97 |
| Telecom HVAC Basis of Design and Approved Manufacturers |
Provide basis-of-design manufacturers and models for CRAC units, split systems, and telecom room cooling systems. Identify approved manufacturers, approved equals, and any owner-preferred vendors.
IMEG: There is a basis of design manufacturer who provided selections of the mechanical equipment used for planning and scheduling. The VA has asked that manufacturers and model numbers be removed from the documents.
| 98 |
| Hazmat Reports, Abatement Limits, and Hazmat Drawing Discrepancies |
Provide all referenced hazardous material reports, clarify abatement limits, responsibility for newly discovered materials, and reconcile discrepancies between hazmat drawing references and numbering.
Awen: December 12, 2023, Hazardous Materials Report, provided as final bid set.
| 99 |
| Existing Condensate System Reuse |
Confirm the suitability of existing condensate piping systems identified for reuse and clarify responsibility if existing piping is unsuitable.
IMEG: The condensate piping is expected to be adequate. If concerns are found during construction, they should be brought to the design team for review.
| 100 |
| Temporary Cooling and HVAC Cutover Requirements |
Define temporary cooling requirements, acceptable downtime limits, monitoring requirements, and responsibilities for temporary equipment during HVAC cutovers.
Awen: VA to advise.
| 101 |
| Existing Conditions, Concealed Conditions, and Differing Site Conditions |
Clarify contractual responsibility and available relief for concealed conditions, undocumented utilities, inaccessible pathways, existing equipment conflicts, and conditions differing from design assumptions.
Awen: VA to advise.
| 102 |
| Commissioning Responsibilities and Vendor Participation |
Provide a commissioning responsibility matrix identifying responsibilities of all parties including contractors, vendors, commissioning agent, and VA personnel.
Refer to Specification 01 91 00, Section 3.1, for the roles and responsibilities matrices. These matrices delineate the responsibilities of all parties from the construction phase through project acceptance and are based on Veterans Administration standards as documented in the Technical Information Library.
| 103 |
| Telecom Room Environmental Criteria |
Provide required temperature and humidity setpoints, cooling redundancy requirements, monitoring requirements, alarm thresholds, environmental acceptance criteria, BAS integration requirements, and commissioning requirements.
IMEG: Refer to the control sequences on sheet 00-MG700.
| 104 |
| OFCI / CFCI Responsibility Matrix |
Provide a complete matrix identifying all owner-furnished, owner-installed, contractor-furnished, and contractor-installed equipment.
VA to advise specifically anything that is owner furnished: OFCI.
| 105 |
| Abandon / Decommission Scope Requirements |
Confirm required scope in all abandoned or decommissioned rooms including cable removal, salvage, utility abandonment, system modifications, and finish restoration.
IMEG: All equipment, materials, and infrastructure that is made obsolete from new work shall be removed once cutover is complete. New work is defined on the construction drawings. Existing devices, cabling, and equipment not included within the project's scope shall remain in place and fully operational. Examples of systems to remain include, but are not limited to, existing voice cabling and associated termination hardware, healthcare system head-end equipment, and CATV head-end equipment. Refer to Sheet 00-TG000 – Technology Coversheet for additional phasing requirements and considerations. Refer to Section 27 05 11 for additional demolition requirements. In accordance with Section 3.5.B, remove and dispose of all equipment, materials, and infrastructure made obsolete by the new work.
Awen: All existing finished assemblies to be protected and maintained during construction. All existing finished assemblies affected by the work to be repaired and finished to original condition and, where demolished, repaired and finished to match adjacent assembly.
| 106 |
| Existing Conduit, Pathway, and Backbox Reuse |
Clarify contractor responsibilities if existing conduits, pathways, and backboxes are unsuitable for reuse.
IMEG: All existing conduit and backboxes to be re-used where suitable at maximum 40% fill capacity. Provide a new pathway at locations exceeding 40% fill capacity. At all locations with (3) or more cables that include a ½” conduit, assume new pathway will be required. Assume 20% of outlets represent this condition and provide cost in bid.
Contractor shall provide cost to include surface mount raceway or fished flexible conduit in walls for all locations where existing conditions include cabling fished down wall cavities. Assume 25% of outlets represent this condition and provide cost for new pathway in bid.
For existing rough-in locations with shallow back boxes: provide a surface mount backbox installed over top of existing in-wall backbox to allow for bend radius of new Category 6A cabling.
| 107 |
| Fiber Backbone Routing Requirements |
Provide final A-leg and B-leg routing requirements, conduit quantities, duct bank quantities, spare conduit requirements, handhole requirements, pathway separation requirements, and splice restrictions.
IMEG: Refer to 00-TS101 for A-Leg and B-Leg conduits and routing.
| 108 |
| Horizontal Cabling Variances and Telecommunications Compliance |
Identify all telecom rooms requiring formal variances and clarify contractor responsibilities for cable distance verification and compliance documentation.
IMEG: Contractor shall field mesure the horizontal work area outlet routes from each TR to ensure no route exceeds 295’ total permanent link length. Preferred routing shall utilize corridors, but unique case routing above adjacent occupied spaces may be required to achieve cable distance requirements. Unique conditions may require a more direct route than following corridors. Contractor shall verify all building routes prior to starting work.
| 109 |
| Electrical Capacity Verification and Upgrade Responsibility |
Clarify whether the base bid shall include downstream panel, feeder, transformer, or distribution upgrades if capacity is insufficient.
IMEG: The contractor shall include pricing for upgrading any existing inadequate electrical equipment.
| 110 |
| Duct Bank Concrete Strength and Trench Backfill Requirements |
Clarify required concrete strength, flowable fill requirements, and acceptable backfill materials for all duct bank and trench installations.
Please clarify whether flowable fill / flow fill is required for ALL duct bank trench backfill. The duct bank details on 00-TG500 and 00-CS501 & 00-CS502 show different specs and direction. Please confirm whether flowable fill is required only in paved/travel areas, or whether suitable excavated material compacted per specifications is acceptable in lawn/soil restoration areas.
Concrete PSI – Please confirm whether duct bank encasement concrete is to be 2000 PSI (p. 00-CS502), 2500 PSI (p. 00-TG500, or 4,000 PSI (spec sheets).
Langan: Suitable excavated material compacted per specifications may be utilized in lawn/soil restoration areas. Langan defers to the Telecommunications team for concrete strength of duct bank and where concrete duct bank is necessary.
It is recommended that the entire duct bank is concrete encased.
| 111 |
| Drawing Set, Sheet Numbering, and Contract Document Discrepancies |
Identify the governing drawing set and reconcile discrepancies in sheet counts, drawing references, sheet numbering, and hazmat drawing references.
Campus Orientation - 00-GI101 depicts the campus in a different orientation (Villas are Southwest in Generals. Villas are Northeast in Civils), and Generals has buildings labeled differently than Civil Drawings (example: Bldg 50 & 51).
Langan: Awen to advise on governing drawing set. Civil drawing set has True North pointing up on the sheet. With respect to labeling of buildings, Langan defers to Awen.
Awen: Orientation for True North is shown on the Civil Drawings. 00-GI101 indicates Plan North (not true north) as it is the Campus Map for the facility. Buildings 50 and 51 are noted as Community Living Center aligned with the current campus website.
| 112 |
| Fiber Cable Armor Requirements |
The fiber backbone specifications identify dielectric fiber cable types but do not clearly indicate whether armored fiber is required. Please confirm whether backbone and inter-building fiber cabling shall be armored or non-armored and identify any applicable VA, OIT, or campus standards governing fiber cable construction.
IMEG: Indoor/Outdoor rated armored fiber optic cabling is acceptable. Refer to Division 27 specifications and OIT ISTS manuals for cable construction requirements.
| 113 |
| HVAC Equipment – Please provide manufacturer requirement for Split Systems and CRAC Units. See p. 00-MG600 |
| IMEG: There is a basis of design manufacturer who provided selections of the equipment used for planning and scheduling. The VA has asked that manufacturers and model numbers be removed from the documents. |
| 114 |
| HVAC Controls – Please provide manufacturer and/or vendor requirements, including who is the current manufacture and service provider for commissioning purposes. No specific manufacturer or vendor in the specs or drawings. |
| IMEG: VA to confirm current vendor. |
| 115 |
| Fire Systems – Please provide manufacturer and/or vendor requirements, including who is the current manufacture and service provider for commissioning purposes. No specific manufacturer or vendor in the specs or drawings. |
| IMEG: The existing fire alarm system manufacturer is “Fike.” No information has been given to the EOR regarding a fire alarm service provider. |
| 116 |
| Residential Villas – Bldgs. 63-68 – Please clarify All Scopes of work at these buildings. |
The Civil and General Technology pages indicate site, electrical, & technology scopes at the exteriors of the Villa Buildings. There are no Drawings Sets dedicated to Buildings 63, 64, 65, 66, 67, 68.
IMEG: The scope of work for these buildings is to replace the fiber backbone feeding the buildings. There is no replacement of data outlets inside the buildings.
| 117 |
| Please confirm who is responsible for the cost of the building permit. |
| Awen: VA to advise. |
| 118 |
| Drawing 51-AE601: The floor finish on the Room Finish Schedule shows |
"EPY/SD." SD is not listed in abbreviation key on the same pages.
Please define was SD stands for, and if needed provide a specification.
Additionally, No specification is provided for EPY epoxy. Please provide.
Awen: Finish should be SDT = Static Dissipative Tile.
| 119 |
| Drawing 71-AE601: The Door Schedule shows a door 2C109 at the |
ground floor. This tag is for the second floor, not ground. Per drawings 71-AE100 and 71-AE102, Room 2C109 does not exist on the ground floor and Office 2C209 does not require scope. Please confirm the door 2C109 shown on the door schedule is not required.
Awen: Disregard 2C109 as there is only GA119 at the Ground Level.
| 120 |
| Upon reviewing the drawings, specifically the partial electrical riser |
diagrams, several existing normal and emergency panels are noted for replacement. For example, on page 50-EN401, ENLARGED PLAN – FIRST FLOOR – TR 1A129, Detail C5, Note 1 states: “Replace existing panel with new 54 circuit and 200 MCB panel.”
Please confirm whether this note applies in all instances. If so, please provide the existing panel information so we can accurately quote these replacements.
IMEG: Note applies in all instances of its use on the construction drawings. The existing electrical panelboard does not have sufficient pole space to accommodate the installation of the new circuit breaker and thusly needs to be replaced. The contractor shall field verify the existing branch circuit breaker ratings/quantities and panel kAIC rating and provide new panelboard to match.
| 121 |
| Please provide additional information on UPSs A and B. During the site |
walk, access to this space was restricted. Pictures of the existing units would be greatly appreciated. UPS nameplate information, battery count, etc.
IMEG: Both ‘UPS-A’ and ‘UPS-B’ are Powerware 9315, 480V -3ph-3wire Uninterruptible Power System, system # 9315 – 300, model 300 with three battery sections.
| 122 |
| Site drawings show the installation of new handholes designated as “PWHH- |
1” according to the technology equipment schedule. This handhole is a Hubbel/Quazite #PG2424BB24 with an associated top. The depth of these boxes is 24 inches. Telecom ductbank details call out for a maximum top-to-conduit depth of 30”. Handhole details show stubbing into the open bottom of PW-HH-1 Handhole. Given that the underground duct banks are 4” conduit, a standard radius elbow will not allow for an as designed installation. Given that information, please advise on the following.
1. No specifications were supplied for the installation of the underground duct; it has been assumed that any radius fittings would be rigid steel, and 90s would be sweep radius fittings. Does the VA have a minimum sweep radius in mind when installing underground ducts?
2. Full NEC sweep radius cannot be achieved at handhole stub-up due to depth constraints. Will the VA accept a new maximum depth to the top of the conduit to accommodate a sweep radius into the bottom of the proposed Handhole? For Bidding purposes, can the VA supply a new maximum depth?
IMEG: The maximum 30-inch depth to top of conduit applies between handholes and pull boxes. Conduits may be routed deeper in the immediate vicinity of handholes as required to accommodate long-radius sweeps and manufacturer-recommended bend radii. As an alternative, provide a deeper handhole (36” or 48” depth).
| 123 |
| After reviewing the bid documents there is not a design intent for Fire |
protection or plumbing. Is that correct? A specifications has been provided for fire protection, but not plumbing.
IMEG: There is no plumbing scope. All fire protection requirements are indicated on the M sheets. Refer to 00-MG000 for general scope requirements – see Fire Protection General Notes and TR General Notes. Additionally see General and Sheet Notes throughout individual building M drawings for additional fire protection notations.
| 124 |
| Specification 01000 General Requirements defines normal working hours |
as M-F 7:00 AM to 4:30 PM. It also states that work performed outside of these working hours requires approval. Please define any work is not allowed during the defined normal working hours (ie: loud work, deliveries, shut downs, etc.)
Awen: VA to advise.
| 125 |
| Confirm is full or part time safety manager and quality managers are |
required on this project. Or if this role can be covered by other personnel on site performing dual duties.
Awen: VA to advise.
| 126 |
| Specification 078100 Applied Fireproofing defines the scope as repairs to |
disturbed existing spray-applied fireproofing. Since the extent of this scope is not know, and will not be know until working in the building, we suggest all bidding contractors carry the same allowance. Please advise.
Awen: Agree all bidding contractors should carry the same allowance.
| 127 |
| What is the ceiling material in the corridors where the low voltage |
systems enter the buildings to TDR. Since this scope is not well defined, we suggest all bidding contractors carry the same allowance. Please advise.
Awen: Agree all bidding contractors should carry the same allowance.
| 128 |
| For ICRA partitions and barriers, please confirm the requirements. The |
architectural drawings say that plastic containment is acceptable, but temporary modular wall system must be used only when construction exceeds 48 hours. Page 6 of Specification 010110, states that no plastic will be used in separating construction from the Medical Center. and should only be used as a temporary measure until the modular wall system is installed. Please confirm which is correct.
In addition, please confirm a hard wall is not required for an ICRA barrier, and a temporary modular wall system is acceptable.
Awen: It is understood that plastic is acceptable in certain conditions. Confirm with VA Facility Safety Standards.
| 129 |
| Is there an in-house security, tele data, temperature control contractor? If |
so, please provide the name and contact information for them?
Awen: Refer to sheet TY-001, Miller Information Systems is base building security vendor.
| 130 | |
| The Utility Drawings and Technology Drawings show different sizes and types for the Manholes and Handholes/Pull Boxes. Can the engineer confirm what is required at each location and provide a schedule for the Technology Manholes and Handholes/Pull Boxes with the sizes and specifications for each type? | |
| a. | The Utility Site Plans 00-CE101 through 00-CE109 show a Quantity of (10) - 9’-4” x 6’-4” Manholes, (1) 4’x 4’ Pull box and (9) 2’x 4’ Pull Boxes. |
| b. | Drawing 00-CS502 has Details for the Manholes and the Pull boxes. Note: These details do not include sizes for the Pull Boxes. |