This document is an Amendment to Solicitation (Standard Form 30) for Boiler Inspections and Maintenance Services at the Minneapolis VA Health Care System. The solicitation (RFQ 36C26325Q0474) is a total Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside under NAICS code 238220, with a $19 million size standard. The VA anticipates a single Firm Fixed Price award for boiler maintenance services covering five boilers (four Cleaver Brooks models and one small low-pressure boiler), with a base period from 04/15/2025 to 04/14/2026 and four potential option years.

The amendment addresses vendor questions regarding boiler serial numbers, inspection requirements, and emergency service terms. Key details include an initial visual boiler inspection to identify repair priorities, with potential separate contracts for extensive repairs. Emergency service line items are pre-priced, estimating approximately 10 emergency jobs per performance period. Interested SDVOSB contractors must be registered in SAM and VetCert, submit technical questions by 04/02/2025, and provide quotes by 5:00 PM Central time on 04/04/2025 via email to the contracting specialist Cameron Rick.

View the file

Other files for this federal contract opportunity

Other files attached to J044--Boiler Inspection & Maintenance, newest first.
File Type Posted
36C26325Q0474 0006.pdf PDF
36C26325Q0474 0005.pdf PDF
36C26325Q0474 0004.pdf PDF
36C26325Q0474 0003.pdf PDF
36C26325Q0474 0002.pdf PDF
36C26325Q0474 0002.docx DOCX document
36C26325Q0474 0001.pdf PDF
Site Visit Meeting Location.png PNG image
36C26325Q0474.pdf PDF
Wage Determination - Mpls.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 04-03-2025 36C618 Department of Veterans Affairs Minneapolis VAMC 1 Veterans Dr.

Minneapolis

MN

55417 36C263 Department of Veterans Affairs

NETWORK 23 CONTRACTING OFFICE

316 Robert Street N. STE. 506 St. Paul

MN

55101 To all Offerors/Bidders

36C26325Q0474 02-21-2025

X X X X The purpose of this amendment is to answer vendor questions, see below.

Bid due date remains the same at 5:00pm on 04/04/2025.

Cameron Rick Contracting Officer

1. Are the serial numbers on the boilers available? The serial numbers are all made unique and specific to each building design, they actually look it up in a system before giving proper quotes.

Cleaver Brooks representative states that the serial number and unit number are the same thing, they are as follows:

#1 Cleaver Brooks- Model DL-68-RH 45,000 pounds of steam, 1275 horsepower. WG-3285 #2 Cleaver Brooks- Model DL-68-RH 45,000 pounds of steam, 1275 horsepower. WG-3284 #3 Cleaver Brooks- Model DL-68-RH 45,000 pounds of steam, 1275 horsepower. WG-3286 #4 Cleaver Brooks- Model DL-52-RH 30,000 pounds of steam, 875 horsepower. WG-3287 #5 Small Low Pressure Boiler – Model, Pounds of Steam, and Horsepower to be determined. SN# 64275041

2. Is Item # 1 supposed to say that the testing requirements are to the 8th edition or is the Contractor really expected to correct the entire boiler plant with materials and labor to bring this up to the 8th edition standards?

Inspection / Testing requirements are to the 8th edition (or most current edition at the time of inspection / testing. Contractor will conduct an initial visual inspection of boilers and supporting components upon initiation of the contract. Vendor will provide a list to the contract COR of deficiencies with notes on priority of repair (ex. critical, high, medium, low). Dependent on the scale of required repairs a separate contract may be competed to fix deficiencies dependent on how extensive the repairs are. If any failure to the boiler system occurs during the period of performance in which a backup is not available or a deficiency is noted during the initial visual inspection to be of such an extreme nature it will be considered an emergency and all parts and labor will be billed under that line item, 0009, 1009, 2009, 3009, or 4009 (dependent on option year period of performance if executed). Prior authorization for any emergency repair from the COR must be received prior to any work being performed or repair part ordered.

3. For the annual inspection requirements of the boilers, deaerator, condensate tank, and boiler stack, is this just a visual? There isn't really any description around what is required. Can the expectations be clarified?

Inspection shall be conducted in compliance with the latest rules and regulations found in section J of the SOW.

4. In Section C: Emergency Service, Item 1 says it covers labor and parts and item 3 says that the contractor will provide an estimate for materials. Which is correct?

Contractor shall provide an estimate for materials prior to any work beginning or parts ordered. It is estimated that there will be approximately 10 emergency service jobs required during each period of performance. Funding for this line item is based on historical precedence and has been pre-priced on line items 0009, 1009, 2009, 3009, or 4009. Actual number of services and pricing will be adjusted during the life of the contract based upon actual emergency services rendered.

Boiler Inspections and Maintenance Services for the Minneapolis VA Health Care System.

This is a solicitation conducted using FAR Part 13 (Simplified Acquisition Procedures).

Solicitation number 36C26325Q0474 is issued as a request for quotes (RFQ).

This procurement is a total SDVOSB set-aside.

Prospective offerors must be registered and current in the System for Award Management (SAM) database (https://www.sam.gov) ) and the Veteran Small Business Certification (VetCert) (Veteran Small Business Certification (sba.gov)) as a SDVOSB under the NAICS at time of offer to the Government.

Quotes will only be accepted from responsible contractors. The NAICS code for the solicitation is 238220 with a size standard of $19 million.

A list of the contract line items, quantities, and units of measure are listed within the attached solicitation documentation.

The VA anticipates one Firm Fixed Price award to provide services to the Minneapolis Health Care System, 1 Veterans Dr., Minneapolis, MN 55417 The period of performance is 04/15/2025 to 04/14/2026 with 4 option years if exercised.

Technical questions on this solicitation are due via e-mail only to Cameron Rick, Contracting Specialist, at Cameron.rick@va.gov no later than 5:00pm Central time on 04/02/2025.

Quotes are due to the Contracting Office by 5:00pm Central time on 04/04/2025. Quotes are required to be emailed to cameron.rick@va.gov prior to the solicitation closing date and time. It is the responsibility of the offeror to ensure their quote is received in its entirety by the Contracting Officer before the solicitation closing.