Z2DA--612A4-27-018 | Replace B650 3rd and 2nd Flooring
Solicitation number
36C26127Q00260001
Issued by

About this file

This file contains Questions and Answers (RFI/Q&A document) for a federal construction contract opportunity at the Sacramento VA Medical Center for flooring, painting, and related interior finishes on the second and third floors of Building 650.

The project involves carpet tile replacement (CPT-1: Shaw Respond Tile, 9" x 36"; CPT-2: Patcraft Recover, 18" x 36"), luxury vinyl tile installation (LVT-1 and LVT-2), resilient base replacement (RB-1 at 6 inches and RB-2 at 4 inches), stainless steel corner guard installation, drywall repairs (up to 20% per room), and full-wall interior painting in affected areas. Approximately 18,765 square feet will be replaced on the second floor and 17,930 on the third floor. The project requires work in phases of up to five rooms at a time during off-hours (nights and weekends) unless approved otherwise, with a 240-calendar-day completion requirement from Notice to Proceed. The elevator will be available for material and debris movement with contractor-supplied protective coverings. The VA will remove all IT-related equipment; the contractor is responsible for moving, storing, and reinstalling all other items including furniture, modular workstations, and fixed casework, without disconnecting equipment. A signed notarized bid bond for 20% of project value is required at bid submission. The contract is not tax-exempt and subject to prevailing wage requirements under General Decision CA20260007. The proposal submission deadline was updated to November 20, 2026. This is a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside contract. Key personnel requirements include a Prime Project Manager, Construction Superintendent, Quality Control Manager, and Safety Manager as separate individuals, with evaluation based on a maximum of five relevant projects completed within the last ten years at $2.0 million or greater. Past performance evaluation requires five completed CPARS reports from recent relevant projects. The technical proposal is limited to 35 pages front and back, excluding past performance questionnaires, with standard 8.5" x 11" paper and 11 or 12-point font. The COR will provide project-specific Infection Control Risk Assessment requirements, classified as Level II precautions with specified containment and control measures. Flooring installation must accommodate 72-hour traffic restrictions for resilient materials and 24-hour restrictions for carpet before occupancy.

View the file

Other files

File Type Posted
36C26127Q0026 0005.pdf PDF
Additional RFI clarification 18 Nov 26.pdf PDF
36C26127Q0026 0004.pdf PDF
RFIs 612A4-27-018 B650 3rd and 2nd Flooring 17Nov26.pdf PDF
10 26 00 - WALL AND DOOR PROTECTION.pdf PDF
Attachment 1 - BLDG 650 Mather 2nd and 3rd Floor Carpet Replacement Current Flooring1.pdf PDF
Evaluation Criteria 1 - Key Personnel_ATTACHMENT A.docx DOCX document
36C26127Q0026 0003.pdf PDF
Wage Determination CA20260007 dated 20260903.pdf PDF
Attachment C Price Breakdown 36C26127Q0026_2 B650 3rd and 2nd Flooring.xlsx XLSX spreadsheet
CONTRACTOR CERTIFICATION REGARDING SAFETY AND ENVIRONMENTAL.docx DOCX document
36C26127Q0026 0002.pdf PDF
612A4-27-018 Pre-Bid Sign in Shts.pdf PDF
36C26127Q0026 0001 Replace B650 Flooring.pdf PDF
RFI Form - 36C26127Q0026_2 B650 3rd and 2nd Flooring.docx DOCX document
Exhibit A - BLDG 650 2nd and 3rd Floors Room Flooring Replacement.xlsx XLSX spreadsheet
Attachment 3 - NorCal Paint Standards 2025.pdf PDF
Evaluation Criteria 1 - Key Personnel_ATTACHMENT A.docx DOCX document
Attachment 1 - BLDG 650 Mather 2nd and 3rd Floor Carpet Replacement Current Flooring.pdf PDF
Price Breakdown 36C26127Q0026_2 B650 3rd and 2nd Flooring.xlsx XLSX spreadsheet
PPQ ATTACHMENT B.docx DOCX document
Wage Determination CA20260019 dated 20260903.pdf PDF
Attachment 4 - Stainless Steel Corner Guards_Technical Data_3716_Rev_15.pdf PDF
Attachment 2 - NorCal Flooring Standards 2026.pdf PDF
36C26127Q0026_2.docx DOCX document
Specifications - 612A4-27-018 Replace B650 3rd and 2nd Flooring REV1.pdf PDF
Evaluation Criteria 2- Prior Experience.xlsx XLSX spreadsheet
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Do we need to plan for the Project Manager to be onsite full time, or can the PM be onsite a portion of the time?

The Project Manager may be onsite part of the time; however, the assigned Superintendent shall be onsite at all times.

2. Will the Government revise the Experience Modification Rate (EMR) requirement from “equal to or less than 1.0” to “equal to or less than 1.10”? An EMR of 1.0 represents the industry baseline, and

EMR values for small firms can vary from year to year based on a limited number of claims. A modest tolerance would preserve the Government’s safety objective while broadening competition among qualified SDVOSB offerors.

This will not be changed, it will remain as “equal to or less than 1.0”

3. Can phases of 5 rooms be performed in immediate succession, or is there an anticipated down time between phases that will require additional mobilizations between phases?

It is expected that there will be no anticipated down time between phases of 5 rooms.

4. Are there any items stored in the building that the contractor will not be allowed to move or relocate?

Except for IT items and items containing personal or patient information, the contractor shall relocate all items.

5. Where should personal items and furniture be stored during each phase of construction?

VA will relocate personal items; the contractor shall find a location outside the VA for storing furniture at their own expense. When re-installing furniture, the VA will let the contractor know if a room is getting new furniture. If new furniture is installed, the VA will install.

6. Is a notarized copy of a physical bid bond for 20% of the project value required at time of bid submission, or does the contractor only need to verify bonding capabilities at the time of bid?

Yes, a signed notarized copy of a physical bid bond needs to be submitted at the time of bid.

7. Should the contractor assume painting doors and trim in addition to all walls?

The contractor will not paint any doors and trim in addition to all the walls. Contractor to inspect door frames and touch up if needed to match existing door frame color.

8. Should the stairwells and bathroom walls/ceiling be painted?

No

9. Do stained doors need to be re-stained?

Stained doors do not need to be re-stained; however, all wood doors are to be wiped down, and tape and tacks to be removed.

10. Please confirm that the base price should be for off hours labor.

Refer to Scope of Work (SOW) - 1. General Intention, Section H.

11. Will the owner/client handle any IT equipment disconnect or relocation. i.e. Computer lab equipment?

Yes

12. In the proposal submission instructions, contractor is to provide PPQ’s and/or CPARs. The PPQ form states It is important that the questionnaire be completed and returned by the date proposal is due

(October 19, 2026 at 12:00 PM PT). The contracting agent and/or their representative responsible for construction contract administration must submit complete PPQs via email to kayla.haruguchi@va.gov and daniel.jhun@va.gov before the specified proposal due date.

However, the proposal is due November 12, 2026. Are we still able to submit a proposal since we didn’t get the PPQs returned by October 19, 2026?

Bid due date has been updated to November 20, 2026.

13. In section 5 of the proposal submission format it states the quote must provide the prior experience worksheet, which states submit a maximum of four (4) example projects demonstrating the experience and capability of the Prime Construction Contractor. However, the evaluation criteria for past performance on page 17 of the solicitation states the Offeror shall submit a completed Contractor

Performance Assessment Report System (CPARS) evaluation for at least five (5) recent, relevant projects.

That is correct.

14. Can the super be dual hatted. (QA/QC and CQC) or you need three individual people full-time at the site full-time.

The superintendent can be dual hatted.

15. Is this Tax-exempt job.

According to FAR 52.212-4 (k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties. This is not a tax-exempt job.

16. Can we store material on site.

Refer to SOW - 1. General Intention, Section E.

17. How many rooms can we do at a time.

Refer to SOW - 2. Scope of Work, Section J.

22. Please identify which furniture and equipment the VA will remove before each phase and which items the contractor must move, store, and reinstall. Specifically clarify responsibility for modular workstation disassembly, fixed casework, equipment disconnects/reconnects, and associated IT or electrical coordination. can we use the elevator for moving material and debris?

The VA will remove all IT-related equipment, and the contractor shall remove all other items. The contractor shall be responsible for moving, storing, and reinstalling those items, as well as disassembling and reassembling modular workstations and fixed casework. The contractor shall not disconnect or reconnect any equipment. The contractor may use the elevator to move materials and debris.

23. Please provide the project-specific Infection Control Risk Assessment and required classification for each work area or phase. Identify required barrier construction, negative-air provisions, exhaust locations, monitoring, and any HVAC isolation or restoration requirements.

This will be a Level II Infection Prevention and Control Precaution, see snip below:

mailto:kayla.haruguchi@va.gov

24. Section 09 05 16 requires testing and moisture remediation where results exceed flooring manufacturer limits. Please provide any available existing moisture/pH reports and identify known problem areas. If the remediation extent cannot be established before bidding, please identify a common bidding allowance or quantity for all bidders.

The VA does not require testing and moisture remediation.

25. Please provide available information on existing substrate conditions, including cracks, damaged areas, adhesive buildup, and elevation differences. Identify any required full-area skim coat or self-leveling underlayment, including anticipated areas and thicknesses, or establish a common bidding allowance where conditions are concealed.

There is no available information.

26. Please provide available hazardous materials survey and testing reports for existing flooring, adhesives/mastics, base, and coatings affected by the work. Clarify the contractor’s testing and abatement responsibilities if hazardous materials are identified.

There are no available hazardous materials surveys and testing reports. The contractor will be responsible for abatement if ACM is identified. If ACM is discovered, abatement may be treated as a change under FAR 52.236-2. Abatement shall be compensable only if it results from a material difference in subsurface conditions or latent or unusual unknown site conditions and the contractor satisfies the clause’s notice and documentation requirements.

27. The finish schedule specifies Schluter Vinpro-S at carpet-to-LVT transitions, while Section 09

68 00 describes clamp-down metal edge strips. Please provide transition locations and details identifying the required profiles at carpet/LVT interfaces, retained flooring, doorways, and elevator thresholds. Clarify any required door undercutting or threshold modifications.

Refer to Attachment 1, “BLDG 650 Mather 2nd and 3rd Floor Carpet Replacement Current

Flooring Plan,” and then to Exhibit A, “BLDG 650 2nd and 3rd Floor Room Flooring

Replacement” Excel spreadsheet, to identify which rooms or areas will receive each material. By comparing these two documents, it will provide transition locations (carpet to LVT).

28. Please identify the approved loading/unloading location, material and debris routes, available elevators and operating hours, and designated storage/container areas. Confirm whether conditioned space will be available for the specified flooring acclimation periods and identify any elevator inspection or maintenance costs to include.

The approved loading and unloading location are currently unknown and will need to be coordinated with the COR. Refer to Section E of the Scope of Work for the second part of this question, which explains that no staging areas are available.

The COR will inspect the elevator at the beginning of the project, and the contractor shall return it to its original condition at the end of the project. The contractor shall be responsible for the cost of any replacement parts and associated labor required to repair damage caused during the project.

The contractor shall cover the elevator with specialized fabric elevator covers supplied by the contractor and remove them at the end of the project. The contractor shall also install heavy-duty floor protection, such as Ram Board or rubber tiles, and replace it as needed. The COR will inspect the elevator for damage at the completion of the project.

Only one elevator will be available to the contractor for the duration of the project, and it shall be protected as described above. The contractor shall maintain the elevator in a clean condition at all times.

29. The specification cover identifies the package as “Bridging Documents,” and Section 01 45 00 includes design quality control requirements. Please clarify whether the contractor must provide professional design services, stamped drawings, or a completed finish design, and identify the required design deliverables and approval stages.

Contractors are not required to provide professional design services, stamped drawings, a complete finished design, or identify the required design deliverables and approval stages.

30. Attachment 1 identifies current flooring, while Section 09 06 00 specifies new finishes CPT-1, CPT-2, LVT-1, and LVT-2. Please provide a proposed flooring plan or room-by-room schedule identifying the new finish required in each room and corridor. Clarify how the existing flooring codes, including CPT-3 and CPT-4 on the third floor, correspond to the proposed finishes.

Use Attachment 1, “BLDG 650 Mather 2nd and 3rd Floor Carpet Replacement Current Flooring,” as the floor plan to correlate with Exhibit A, “BLDG 650 2nd and 3rd Floors Room Flooring

Replacement.”

31. The plans identify replacement areas of 18,765 SF on the second floor and 17,930 SF on the third floor, described as net square feet minus restrooms. However, rooms other than restrooms also appear crossed out. Please confirm whether the stated quantities exclude every crossed-out room and provide a room-by-room breakdown of the replacement area by new flooring type. Clarify whether stairways, landings, and elevator cab floors are included.

See the answer to number 30 above. Every room that is crossed out will not be part of this project.

Stairways, landings, and elevator cab floors are not included either.

32. Section 09 06 00 lists CPT-1 as 9 × 36 inches and CPT-2 as 18 × 36 inches, while Section 09 68

00 specifies 12 × 48-inch modular carpet. Please confirm the required size and governing product requirements for each carpet finish.

Section 09 06 00 are the requirements of this project – disregard Section 09 68 00.

33. Section 09 06 00 lists LVT-1 as 6 × 36 inches and LVT-2 as 7.25 × 48 inches, while Section 09

65 19 specifies 9.845 × 39.38-inch LVT, 4.5 mm thick. Please confirm the required dimensions and thickness for each LVT finish and identify which requirements govern.

Section 09 06 00 are the requirements of this project – disregard Section 09 65 19.

34. The finish schedule identifies 6-inch RB-1 and 4-inch RB-2, while Section 09 65 13 specifies 4-inch base, with straight base at carpet and cove base elsewhere. Please identify the required base code, height, and profile for each area and confirm the extent of existing base removal and replacement

Section 09 06 00 are the requirements of this project – disregard Section 09 65 13.

35. The specifications include gypsum board, painting, and a stainless-steel corner guard selection, but the supplied plans do not clearly identify their installation limits. Please confirm whether the work includes full-wall repainting, localized repairs following base removal, new corner guards, or other wall repairs, and provide locations and quantities.

The work includes full-wall repainting, localized repairs following base removal, as needed, and installation of new corner guards, as stated in Section E, “Scope of Work,” of the SOW. Wall repairs shall be performed as needed throughout the project scope.

36. Night and weekend work is required for disruptive activities. Please identify permitted working hours, required phase boundaries, the maximum area available at one time, and required reopening times. Section 09 65 19 requires 72 hours without traffic after resilient flooring installation, while Section 09 68 00 requires 24 hours for carpet. Please confirm that the phasing and occupancy requirements will accommodate these periods

Off-hours are defined as periods outside normal working hours, as stated in Section H, “General

Intention,” of the SOW. The maximum number of rooms or areas available at one time will depend on the contractor’s ability to complete the work during the off-hours period or as stated in the

SOW, 2. Scope of Work, Section J. Areas shall be reopened at least two hours before 7:30 a.m. to allow the COR to inspect them. Phasing and occupancy requirements shall accommodate the 72-hour and 24-hour periods.

37. Will the building remain operational during demolition.

Yes

38. IS there a designated space for storing furniture with in the building, please share the location.

Refer to SOW - 1. General Intention, Section E.

39. Paint all rooms located on the 2nd and 3rd floors": confirm corridors, lobby, restrooms and rooms marked "no change" are included; whether ceilings, doors, HM frames and accent walls are included;

number of colors per room (paint plan "as installation approaches.

Confirmed, only rooms shall be painted. No ceilings, doors, or HM frames. Contractor to inspect

HM frames and touch up if needed to match existing HM frame color.

40. Provide quantity, height and locations of existing plastic corner guards to be replaced; confirm SS guard size/gauge/height per Attachment 4 and Engineering Suite mock-up.

Refer to Attachment 1, “BLDG 650 Mather 2nd and 3rd Floor Carpet Replacement Current

Flooring,” for the number and locations of corner guards, which are marked with green dots.

Refer to Specification Section 09 06 00, paragraph 5, for corner guard information.

41. Confirm whether contractor or VA moves furniture, systems furniture and IT/medical equipment; who disconnects/reconnects IT and systems-furniture electrical.

Refer to question number 22.

42. Asbestos coverage is required. Provide existing hazardous-materials survey for VCT, mastic and drywall joint compound. If ACM is found, will abatement be a change under 52.236-2?

The VA does not believe that asbestos-containing materials (ACM) are present in the work area.

The contractor shall perform its own due diligence to identify any ACM. If ACM is discovered, abatement may be treated as a change under FAR 52.236-2. Abatement shall be compensable only if it results from a material difference in subsurface conditions or latent or unusual unknown site conditions and the contractor satisfies the clause’s notice and documentation requirements.

43. Confirm allowed off-hours windows (weeknight hours, weekends), elevator use for debris/material, location for dumpster and staging, and contractor parking.

Refer to SOW - 1. General Intention, Section E, F, and H.

44. Please confirm that only one layer of flooring exists.

The VA believes that only one layer of flooring is present; however, if additional layers are discovered, the contractor shall be responsible for removing them at their own cost.

45. Confirm attic-stock quantity required for carpet tile, LVT and base.

The VA is not expecting attic stock construction material other than open boxes of materials.

46. Confirm moisture/alkalinity testing requirements and the remedy if relative humidity (RH) exceeds manufacturer limits.

Refer to specification Section 09 05 16.

47. During the site visit we noticed the flooring layout with different designs. Please advise if that will be required, and if it is, how frequent (How many locations), and provide the layouts.

Once submittals are received with product data, the VA will advise in layouts.

48. Who will be responsible to remove and re-install the existing wall pictures, accessories, etc... so that the contractor can prepare and paint the walls.

The contractor shall be responsible for removing and reinstalling wall pictures, accessories, and similar items as necessary to prepare and paint the walls.

49. Please provide the painting quantities and corner bead/guard quantities.

Refer to Current Flooring Plans (see Attachment 1 - BLDG 650 Mather 2nd and 3rd Floor Carpet

Replacement Current Flooring) and Flooring to be used per room (Exhibit A - BLDG 650 2nd and

3rd Floors Room Flooring Replacement).

50. How many phases will each level be separated in?

Refer to SOW – 2. Scope of Work, Section F for phasing requirements.

51. The Evaluation Criteria 2 form asks for up to four completed projects. All of our relevant experience is as prime contractor on VA projects. Are there any additional requirements or preferences for the projects submitted beyond what is listed on the form? Will the Government contact the listed points of contact for all submitted projects?

There are no additional requirements or preferences for the projects submitted beyond what is listed in this form. The Government may contact the listed points of contacts for all submitted projects.

52. Attachment 1 notes that rooms with a line across will not be replaced and provides net square feet excluding restrooms. Please confirm that the quantities in Exhibit A are the governing quantities for bidding. Are any additional areas such as corridors or lobbies excluded beyond those marked on the plans and listed in Exhibit A? For rooms noted as LVT plus CPT (for example 2B015 and 2B211), please confirm the approximate square-foot split between LVT and carpet or whether the split will be field-directed.

Confirmed: The quantities in Exhibit A are the governing quantities for bidding. No additional areas, such as corridors or lobbies, are included beyond those marked on the plans and listed in

Exhibit A. Room 2B105 and 2B211 are identified as LVT and CPT installations, see Attachment 1 for the division between the two flooring types. Those two rooms in Attachment 1 identify LVT in red letters of Carpet in red letters – designating it to the section that will receive LVT or Carpet.

53. The specifications indicate that disruptive work will be required during nights and weekends and that the Medical Center operates 24 hours a day, 7 days a week. Are there any defined restricted hours or a maximum number of rooms that can be worked at one time? Will the Government provide a preferred phasing sequence, or is the contractor free to propose the phasing plan? Is weekend and night work mandatory for all flooring installation, or only for high-impact areas?

Refer to 1. General Intention, Section H for working hours. The contractor is free to propose the phasing plan, however, refer to 2. Scope of Work, Section F for phasing requirements and J for room requirements. Only for high impact areas is weekend and night work mandatory.

54. Are there specific ICRA containment requirements such as hard barriers, negative air, or HEPA filtration that must be maintained for all flooring work on these floors? Will the COR or Infection

Control provide a project-specific ICRA assessment, or is the contractor solely responsible for developing and implementing the ICRA plan?

Yes, ICRA containment requirements apply to this project. The COR will provide the ICRA requirements, and the contractor shall be responsible for implementing them.

55. Section 09 65 16 is included in the specifications, but Exhibit A and the finish schedule appear to show only LVT and carpet tile. Is any resilient sheet flooring required under this contract? If not, can

Section 09 65 16 be disregarded?

Section 09 65 16, “Resilient Sheet Flooring,” is included in case any resilient sheet flooring requires removal and for the contractor to understand the process of removing it.

56. Has any testing been performed for asbestos-containing materials, lead, or other hazardous substances in the existing flooring, adhesives, or underlayment? If hazardous materials are encountered during demolition, will they be handled by the Government or by the contractor under a change order?

Refer to question number 42.

57. Is painting required on all wall surfaces in every room receiving new flooring, or only on walls that are damaged or adjacent to flooring work? Are ceilings included in the painting scope?

Painting is required on all wall surfaces in every room receiving new flooring. Ceilings are not included in the painting scope.

58. Please confirm whether quantities for transition strips, reducers, and thresholds are to be based on the drawings and Exhibit A, or if the contractor should include an allowance for all doorways and changes in floor height.

Confirmed, contractors shall base quantities based on Attachment 1 and Exhibit A.

59. Are there designated on-site storage areas for flooring materials, or must the contractor plan for off-site storage and daily delivery? Are there any restrictions on elevator use or loading dock access during nights and weekends?

Refer to question number 28 - The approved loading and unloading location are currently unknown and will need to be coordinated with the COR. Correct: the contractor must plan for offsite storage and daily deliver. Refer to question number 28 for elevator use. Loading dock access will be available, but with restrictions which are to schedule deliveries at least 72 hours in advance.

Also, any loading dock use is subject to the COR’s approval.

60. What is the expected timeframe for Government review of submittals after Notice to Proceed? Are there any long-lead items (specific LVT or carpet products) that the Government anticipates may affect the schedule?

For submittal reviews, refer to Specification Section 01 00 00. In previous flooring projects, LVT lead times have ranged from 6 to 8 weeks, and carpet lead times have ranged from 3 to 4 weeks;

however, lead times depend on market conditions.

61. Please confirm the required warranty periods for the LVT, carpet tile, and resilient base. Are manufacturer warranties required to be in the Government’s name, and are there any extended warranty requirements beyond the standard manufacturer warranties?

For warranty requirements, refer to the provided specifications, including the Construction

Warranty clause, FAR 52.246-21, “Warranty of Construction.” The project specifications also require manufacturers’ warranties.

62. Amendment 0001 defines a relevant project as one completed within the previous five (5) calendar years. Due to the significant disruption and delays caused by the COVID-19 pandemic across the construction industry, particularly on VA medical center projects, please consider extending the recency period to seven (7) or eight (8) years. This would allow offerors to submit their most relevant projects of similar size, scope, and complexity that were completed just outside the current five-year window but remain highly applicable to this flooring replacement effort.

It will remain as within the previous five calendar years.

63. Amendment 0001 defines a relevant project for size as any project over $2,000,000. The solicitation magnitude for this project is $1,000,000 to $2,000,000. Using a $2M threshold would exclude projects that are the same size as the work being bid. Please consider revising the size definition for relevant projects to $1,000,000 or greater so that projects of similar magnitude to this solicitation can be considered relevant.

It will remain as $2M.

64. Amendment 0001 requires a Technical Literature/Information volume (key personnel, prior experience, schedule narrative, Attachment A, and Evaluation Criteria 2). Please clarify any page limits, font size, margins, spacing, or other formatting requirements for the technical volume, including the project schedule summary/narrative.

The Technical Literature/Information Volume shall not exceed the page limits stated herein. If the page limits are exceeded, the pages in excess of the limit will not be read or considered. Page limits for entire Technical Quote shall not exceed thirty-five (35) pages front and back. The CPARS/Past Performance questionnaires do not count as part of the 35 pages.

Page Limits Shall Include: All appendices, charts, graphs, diagrams, tables, photographs, drawings, etc. except as noted in the instructions. Text lines will be single-spaced.

Written quotes shall be prepared on standard 8.5 x 11-inch paper (charts may be landscaped but must be on 8.5 x 11-inch paper) and shall be in a legible font size (11 or 12 point). All pages of each proposal shall be appropriately numbered and identified with the RFP number. For ease of reference, consecutive page numbering with tabs is required. ** The schedule sheet may be larger for legibility.

Email Copy: Provide one (1) email copy of the complete quote.

65. Amendment 0001 requires the Offeror to submit a completed CPARS evaluation for at least five (5) recent, relevant projects. The original solicitation required four (4) projects. Please consider reducing the required number of CPARS to three (3) or four (4). Reducing the quantity would allow us to provide our strongest and most relevant CPARS for evaluation.

This will remain as five recent, relevant projects.

66. Drawing reference: VA102B, VA103B, VA104B, VA105B, VA106B, VA107B, VA108B, and VA109B

- Where is the finish schedule legend indicating which LVT option goes in each building, room, or area. Need call out for flooring and base called out for each area.

Refer to Flooring to be used per room (Exhibit A - BLDG 650 2nd and 3rd Floors Room Flooring

Replacement).

67. Reference Instructions to Offerors, Item 5 – Format and Content of Offeror Response to Quote on RFQ

Page 14: This indicates the Technical Literature/Information part of the proposal must include a “project schedule summary/narrative with a breakdown of major activities”. However, Evaluation Factors do not mention anything about a schedule. Please confirm a schedule/narrative is not required to be submitted with proposals.

Refer to RFI 64.

68. Reference “Prospective Contractors’ Responsibility” (RFQ Page 14). Please clarify which part of the proposal these items should be included with, including Representations and Certifications found throughout the RFQ.

There is no solicitation requirement for submitting a project schedule summary/narrative. This has been removed from section 5 of the Instructions to Offerors. These are the evaluation factors:

Key Personnel

Prior Experience

Past Performance

Price

You are required to submit solicitation submission requirements outlined in the evaluation criteria.

69. Under Evaluation Criteria 1 (Key Personnel) on RFQ Page 16 it states the Offeror shall complete the attached ‘Criteria 1-Key Personnel’ spreadsheet (Attachment A) for each of the proposed Project

Manager and Superintendent. However, Attachment A indicates a separate sheet should be submitted for the Project Manager, QC, Safety, and Site Superintendent. Please confirm the Evaluation Criteria prevails, requiring only the proposed Project Manager and Superintendent.

The offeror must submit the information shown in Attachment (A) for their Key Personnel.

Prime Project Manager, Construction Superintendent, Quality Control and Safety

Manager. Submission of information on each of the key personnel’s experience is limited to a maximum of five (5) projects. If the Offeror submits more than five (5) projects for each key personnel, the Government will evaluate the first five (5) and disregard any other project information after the first five (5). In addition, the quote shall also clearly indicate the number of years of experience for the key personnel in each of their respective positions. In order to properly evaluate the quotes, the quote shall clearly indicate the number of years of experience, and shall NOT show combined experience, such as, Project Manager/Superintendent for three years. The proposed key personnel shall be employees of the Offeror’s firm. If the proposed key personnel are not an employee of the Offeror’s firm at the time of proposal submission, the

Offeror shall obtain a letter of intent to be employed by the Offeror, signed by the key personnel and the Offeror, and shall submit it with the quote. Submissions for each individual key personnel shall be limited to five (5) single-sided pages, 8.5” x 11”, 1” margin left/right/top/bottom, and 10-point font or larger.

In addition, the offeror shall submit the information shown in Attachment (A) for the Quality

Control Manager of Prime Contractor. Submission of information to demonstrate experience for the Quality Control Manager of the Prime Contractor will be limited to five (5) projects as outlined above. Please note: As stated in the Specification titled (01 45 00 Quality Control), the individual/individuals submitted as potential QC Managers are required to be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of 3 years construction experience on projects of similar size, scope and complexity.

(b) Basis of Evaluation: The above listed key positions are listed and will be rated in descending order of importance. The Offeror's key personnel shall be evaluated based upon experience of work construction, demonstrated by a maximum of two (2) flooring replacement projects or similar for each person. Each project shall have a dollar value of approximately

$2.0M or more, completed within the last ten (10) years. Each person shall have a minimum of two years of construction experience in their respective positions and five years in their respective fields. Key personnel with demonstrated experience in the specific flooring or similar site improvement disciplines outlined in this paragraph may be rated more favorably. Likewise, key personnel with 5 or more years in their respective positions and 10 or more years in their respective fields may be rated more favorably.

70. Evaluation Criteria 1 (Key Personnel) on RFQ Page 16, under Basis for Evaluation it states the Offeror’s key personnel shall be evaluated based upon experience in relevant projects with flooring and carpet replacement, demonstrated by a maximum of three (3) projects for each person. However, Attachment A indicates offerors should provide a maximum of five projects. Please advise.

See RFI 69.

71. Section 01 45 00 para 3.4/B states, “The CQC System Manager is required to be a graduate engineer / architect to determine qualifications based on project complexity at construction review.” Please confirm the CQC System Manager is not required to be an engineer or architect, which would be overkill and drive costs up for this flooring replacement project.

Yes that is correct.

72. Instructions to Offerors, Item 5 requires completed Attachment A - Evaluation Factor 1 - Key Personnel.

Evaluation Criteria 1 requires the prescribed spreadsheet for the proposed PM and Superintendent and states information submitted outside that form will not be considered. The RFQ attachment list names

Evaluation Criteria 1 - Key Personnel_ATTACHMENT A.

The Prospective Contractors Responsibility provision separately requires the Responsibility - Contractor

Certification Regarding Safety and Environmental form. The Key Personnel spreadsheet is included in the solicitation package; the Safety and Environmental certification form was not identified among the solicitation documents. The supplied Evaluation Criteria 2 - Prior Experience workbook and price breakdown are separate forms and do not replace these requirements.

Please clarify:

1. Please confirm that the solicitation file "Evaluation Criteria 1 - Key Personnel_ATTACHMENT A" is the required "Attachment A - Evaluation Factor 1 - Key Personnel" form, and that the price breakdown referenced in the RFQ as "Attachment C - Pricing Breakdown" is the file titled "Attachment A - Price

Breakdown."

2. Provide the Responsibility - Contractor Certification Regarding Safety and Environmental form, or identify its exact filename and location.

3. Confirm the forms and supporting documentation required with the quote, including the safety/environmental certification and EMR/violation documentation referenced in the RFQ.

4. If the prescribed forms are unavailable, confirm an acceptable alternate submission format and that information provided in that format will be evaluated. Please issue any clarification or replacement forms to all offerors before the quote deadline.

Attachments have been updated.

73. The RFQ includes General Decision CA20260019 dated September 3, 2026, Modification 6. Page 1 identifies Construction Types: Residential and describes residential construction projects as single-family homes and apartments up to and including four stories. Sacramento County is included in the listed counties.

Applicable General Decision CA20260007

The SOW describes flooring replacement, drywall repairs, painting, and related work on the second and third floors of Building 650 at the Sacramento VA Medical Center, an active hospital. The supplied residential designation therefore requires clarification for this hospital renovation. The RFQ incorporates

FAR 52.222-6 (Construction Wage Rate Requirements), 52.222-8 (Payrolls and Basic Records), and

52.222-13 (Compliance with Construction Wage Rate Requirements and Related Regulations).

1. Confirm whether CA20260019, dated September 3, 2026, Modification 6, is the intended wage determination for this hospital renovation despite its residential construction designation.

2. If a different determination applies, issue the correct wage determination by solicitation amendment, identifying the general decision number, construction type, applicable county, modification number, and publication date.

3. Confirm the wage determination and revision offerors must use as the common basis for labor and fringe-benefit pricing, including any applicable scheduled increases, and provide sufficient time to incorporate any correction before quotes are due.

See RFI 72

74. The pricing form groups Project Manager/QC and Superintendent/Safety. However, Section 01 35 26, 1.7.C requires an SSHO separate from the Superintendent and QC Manager, with duties only as SSHO;

1.7.D requires on-site coverage during construction operations.

All three roles will be a separate individual.

Section 01 45 00, 3.4.A requires on-site CQC presence throughout the work. Paragraph 3.4.B states the

CQC System Manager is a GC employee, always on site during construction, and also performs

Superintendent duties. It references a graduate engineer/architect qualification and requires an equally qualified alternate. Section 01 35 26, 1.8.A separately establishes SSHO training/experience requirements. These provisions do not align with the pricing form's role groupings.

CQC System Manager will be a separate individual.

1. Given the limited complexity of this scope (interior flooring, base, corner guard and paint replacement on two floors, with no structural, MEP or exterior work), please confirm the Government will accept the following combined roles, consistent with the Price Breakdown groupings:

a. The Superintendent also serving as SSHO, with an equally qualified alternate per Section 01 35 26, 1.7.D; and

b. The Project Manager also serving as CQC System Manager per Section 01 45 00, 3.4.B.

2. If combined roles are not acceptable, please confirm a dedicated SSHO is required only during active construction shifts, and confirm the CQC System Manager qualifications (graduate engineer/architect, or experienced construction professional).

All three roles will be a separate individual.

75. Exhibit A assigns new flooring by room. Rooms 2B015 (614 SF) and 2B211 (471 SF) receive LVT-1 +

CPT-2 and refer to Attachment 1 for finish locations. Attachment 1 is titled Current Flooring and uses existing finish marks; Exhibit A notes that new CPT-1/CPT-2 marks differ from existing marks.

Dimensioned new finish boundaries and installation directions are not clearly established.

Refer to Exhibit A for flooring installation in Rooms 2B105 and 2B211. Attachment 1 also identifies which sections will get LVT or carpet in those two rooms.

Section 09 06 00, 2.1.B-C identifies LVT-1/LVT-2, CPT-1/CPT-2, and RTR-1 (Schluter Vinpro-S, brushed anodized aluminum). Section 09 68 00 requires carpet layout shop drawings, edge molding, and pattern/pile direction coordination, but does not resolve the mixed-finish boundaries.

Disregard mixed-finish boundaries.

1. Provide coordinated, dimensioned new flooring plans identifying the exact areas receiving CPT-1, CPT-2, LVT-1, and LVT-2. Confirm whether VCT-1/VCT-2 identify existing flooring only or any new

VCT is required.

Refer to Exhibit A. The “New Mark” column identifies the material each room will receive.

2. For Rooms 2B015 and 2B211, identify the finish type and area of each portion and dimension all carpet/LVT boundaries.

Attachment 1 identifies areas labeled “LVT” and “Carpet.” These labels indicate which sections will receive LVT or carpet, respectively.

3. Confirm installation directions, patterns, offsets, borders, and accent layouts for each flooring type.

Refer to the project specifications provided for installation directions.

4. Identify transition locations/profiles at carpet-to-LVT interfaces, doorways, and connections to existing flooring. Confirm where RTR-1 applies and provide details for differing finish elevations.

Refer to the project specifications for instructions on handling transitions where different floor finishes meet.

5. Exhibit A and Attachment 1 are solicitation attachments of equal precedence under FAR 52.212-4(r), Order of Precedence. Please confirm Exhibit A governs room finish assignments, and whether the

Contractor must propose layouts for VA approval or follow VA-issued layouts.

Confirmed: Exhibit A governs room finish assignments.

76. The SOW requires repairs to up to 20% of the drywall surface area in each room before painting. Section

09 29 00, 3.5.A specifies Level 4 for finished areas open to public view; 3.6.A-D addresses repair of damaged and defective surfaces. Section 09 91 00 requires painting disturbed, damaged, repaired, or patched surfaces.

1. Is the 20% quantity basis calculated from wall surfaces only, or the combined wall and gypsum ceiling surfaces in each room?

Correct, combined wall surfaces in each room only.

2. Confirm Level 4 per Section 09 29 00, 3.5.A is required for repaired surfaces, including staff-only rooms, or identify any locations requiring a different finish level.

Confirmed: Level 4 is required for repaired surfaces only.

3. If required repairs in a room exceed the 20% quantity basis, please confirm the excess will be directed by the Contracting Officer and compensated by modification under FAR 52.243-4, Changes, with quantities measured and agreed with the COR before the work is performed.

The 20% repair quantity is neither a guaranteed quantity nor an entitlement for each room. The contractor shall field-verify the actual repair requirements for each room and account for the fact that some rooms may require less than 20% repair, while others may require more.

If the required repairs in an individual room exceed the 20% quantity basis, the contractor shall use the unused portion of the 20% allowance from other areas for that room.

4. The SOW requires painting all rooms on the 2nd and 3rd floors, with a VA paint plan to be provided as the installation date approaches. Please confirm the painting scope to be quoted (walls only, or also ceilings, doors and frames), and whether rooms not receiving new flooring are included.

Painting is limited to walls in rooms receiving new flooring. Rooms not receiving new flooring are excluded from the painting scope.

77. Flooring, adhesive, and base removal, drywall repairs, and paint preparation may disturb existing materials. No project-specific asbestos/lead surveys or quantified abatement scope were identified in the supplied documents.

Section 02 41 00, 3.1.B refers hazardous-material removal to Hazardous Materials specifications.

Section 09 91 00, Regulatory Requirements, A.2.d references Section 02 83 33.13 for lead-paint removal; that section was not identified in the supplied package. Sections 01 74 19, 3.1.C and 09 05 16, 3.2.A.2 address compliant waste handling and flooring/adhesive removal without clearly allocating investigation, abatement, monitoring, or clearance responsibilities.

1. Provide available asbestos and lead surveys, sampling results, and location plans for existing flooring, underlying layers, adhesives/mastics, wall base/adhesives, and painted surfaces affected by the work.

2. Identify responsibility for additional sampling/testing, abatement, waste characterization/disposal, air monitoring, and final clearance, including work by the VA or its separate contractor under FAR 52.236-8, Other Contracts.

3. If abatement is included, provide applicable specifications, locations, quantities, and procedures, including referenced Section 02 83 33.13.

4. For hazardous materials not identified in the solicitation, please confirm they will be treated as a differing site condition under FAR 52.236-2, Differing Site Conditions, with notification to the

Contracting Officer, suspension of affected work, and adjustment of contract price and time by modification under FAR 52.243-4, Changes.

78. The SOW requires compliance with the ICRA permit class and zipper-door dust barriers. Section 01 35

26, 1.12.B assigns the ICRA assessment to VA personnel. Class III/IV provisions require HEPA-equipped negative-air units and continuous digital pressure monitoring with recording/alarm at 0.01 inch water gauge negative pressure.

Paragraph 1.12.C.2.a allows airtight floor-to-ceiling plastic barriers where dust control is the only hazard and the COR approves; other provisions address drywall barriers, sealed penetrations, and Class IV anterooms. Paragraph 1.14.D requires smoke-tight construction partitions and rated partitions where applicable. Paragraph 1.12.H.1 addresses exhaust reentry into the facility but does not identify an approved exhaust route.

1. As the ICRA is performed by VA personnel per Section 01 35 26, 1.12.B, please provide the anticipated ICRA classification and project-specific containment requirements for corridor flooring removal, substrate preparation, drywall repairs, and painting. Provide the applicable ICRA assessment/permit for pricing.

2. Are sealed fire-retardant plastic barriers with zipper doors acceptable for corridor work, or are rigid smoke-tight/rated barriers and self-closing rated doors required? Identify locations, heights, and any anteroom requirements.

3. Confirm required negative-air equipment, pressure criteria, continuous monitoring/recording/alarms, and whether operation must continue between shifts.

4. Identify approved dedicated exhaust routes and discharge locations. Confirm whether exterior exhaust is required or filtered recirculation is permitted, including required HVAC isolation and responsibility for related modifications.

Refer to question number 23.

78. The SOW requires after-hours work unless approved otherwise and completion/inspection of assigned rooms before additional rooms are released. Section 01 00 00, 1.4.A and 1.7.J requires protected work areas and coordinated phasing, but does not establish a next-business-day turnover requirement.

Section 09 65 19, 3.4.B prohibits traffic on resilient material for at least 72 hours after installation.

Section 09 68 00, 3.2.A requires isolation of the installation area; 3.2.D requires continued ventilation for at least three days; and 3.2.E prohibits traffic and furniture/equipment movement for 24 hours after carpet installation.

1. May assigned rooms remain closed across multiple shifts for demolition, testing, substrate repairs, flooring installation, painting, and curing, or must each room be returned to service before the next business day?

Assigned rooms may be worked on concurrently; however, the number of rooms that may be worked on at one time will be limited. For example, up to five rooms may be worked on simultaneously if the work is performed and approved during normal business hours, as stated in Section J, “Scope of

Work,” of the SOW.

2. If multi-shift closures are permitted, confirm the maximum continuous closure period and whether containment may remain in place between shifts.

There will be only one work shift, and barriers, controls, or containment may remain in place between workdays.

3. If next-business-day turnover is required, please reconcile that requirement with the specified 72-hour resilient flooring and 24-hour carpet traffic restrictions and identify any approved revised restrictions or installation systems, or confirm the Government will issue an amendment revising those restrictions.

The Government understands those restrictions and will comply with the 72-hour resilient-flooring and 24-hour carpet-traffic restrictions.

79. The SOW requires phasing coordination with the COR and prohibits blocking doorways. Section 01 00

00, 1.7.H.2 requires unobstructed access to operational areas; 1.7.J requires coordinated successive phases. Section 01 35 26, 1.14.B and F-G requires emergency access and unobstructed egress; 1.14.D addresses temporary construction partitions.

Section 09 65 19, 3.4.B prohibits traffic for at least 72 hours after resilient flooring installation.

Paragraph 3.4.D describes protection for construction traffic but does not establish temporary patient/staff walking surfaces or authorize early reopening. The supplied documents do not identify corridor closure durations or a sectional access plan.

1. Confirm allowable corridor closure durations and approved closure windows, including whether closures may extend between shifts for substrate preparation, installation, and curing.

When working in corridors, the contractor shall focus on completing the corridor unless an alternate route is available. Closures may remain in place between shifts and workdays as needed for substrate preparation, installation, and curing.

2. Confirm minimum clear access widths and required routes for patients, staff, wheelchairs, stretchers, emergency response, and egress. Identify any approved alternate routes.

Minimum clear access widths shall be at least 36 inches. The COR and contractor shall identify potential alternate routes, subject to the COR’s approval.

3. May corridors be completed in sections or half-width phases while maintaining an approved access route? Identify any required sequence or maximum work-area length.

Yes, work coordination will happen according to the project’s needs.

4. Will temporary walking surfaces, ramps, or temporary flooring be required between shifts? If so, define locations, performance requirements, and installation/removal frequency, and reconcile access with the specified 72-hour traffic restriction, so that all offerors quote a common basis.

Temporary walking surfaces, ramps, or temporary flooring will not be required to be removed between workdays as long as properly secured to the floor and always kept clean.

80. The SOW requires replacement of existing plastic corner guards, matching the wall mockup outside the

Building 650 Engineering Suite for installation and lengths, plus up to 10 additional guards at VA request.

Section 09 06 00, 2.1.E identifies Inpro Type 304 stainless steel, 18-gauge, 3-1/2-inch, No. 4 satin finish, meeting NSF Standard 51, or approved equivalent. Attachment 4 lists multiple sizes, gauges, heights, and screw-on/cement-on options without selecting project-specific heights or mounting. A standalone

Section 10 26 00 was not identified in the supplied package.

1. Provide the existing guard count and replacement location schedule, including any rooms not receiving new flooring.

Refer to Attachment 1, “BLDG 650 Mather 2nd and 3rd Floor Carpet Replacement Current

Flooring,” which identifies the corner guards to be replaced with green dots. In addition to the corner guards identified in the plans, the contractor shall account for the installation of up to 10 additional corner guards.

2. Provide required heights/lengths, top/bottom elevations, and Engineering Suite mockup details.

Confirm termination above wall base or at the floor and any custom angles/dimensions.

The corner guard located at the Engineering Suite mockup is approximately 90 inches high and extends from above the installed resilient base to the ceiling grid. The resilient bases to be installed are RB-1 (6 inches) and RB-2 (4 inches).

3. Confirm mounting: adhesive/cement-on, exposed screws, or a combination. Identify required backing, fasteners, and substrate preparation.

All mounting will be with adhesive/cement-on. COR will provide Specification Section 10 26 00 as an amendment.

4. Identify locations, heights, and mounting for the additional 10 guards. Confirm whether the additional

10 guards are to be included in the quoted price, or ordered by modification if directed by the

Contracting Officer.

The mounting requirements for the 10 additional corner guards shall be the same as those specified in

Item 3 above. The contractor shall include the cost of the 10 additional corner guards in its quotation since they will have to provide them to the VA COR at the end of the project no matter if they were not installed.

5. Confirm Type 304 stainless steel, 18-gauge, 3-1/2-inch wings, No. 4 satin finish, meeting NSF

Standard 51 governs over Attachment 4 alternatives. Provide Section 10 26 00 if applicable.

Refer to specification Section 09 06 00 for details. COR will provide Section 10 26 00 which is applicable.

81. Section 09 68 00, 2.1.A.2.b specifies 12-inch x…