36C26126R0009 Solicitation.pdf
PDF 773 KB Posted
- Attached to
- Z1DA-- Renovate OR for Hybrid Installation
- Solicitation number
- 36C26126R0009
About this file
This document is a Request for Proposal (RFP) for a construction project to renovate operating rooms (OR) at the VA Northern California Healthcare System in Mather, California. The project involves renovating four existing operating rooms and expanding to include a fifth hybrid OR, with a total project area of approximately 12,500 square feet. The solicitation is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) with an estimated project value between $10 million and $20 million.
Key details include a 500-day performance period, a site visit scheduled for December 11, 2025, and proposals due on January 15, 2026. The project requires specific brand-name or equal items, including Fortress stainless steel wall systems, SLD Technology Modular Ceiling Systems, Johnson Controls programming and controls, Secutron fire alarm system, HID PIV card readers, and a Swiss Log pneumatic tube system. The evaluation will use a best-value tradeoff approach, with technical/management factors being most important, followed by past performance, and then price. Contractors must submit both technical and price proposals, and demonstrate experience managing temporary trailers and operating in a 24-hour surgical environment.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES NO
a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
1 72
36C26126R0009
X
12-03-2025
612-26-2-3166-0003
612A4-25-004
36C261
Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Sierra Nevada Health Care System 975 Kirman Avenue Reno NV 89502-2597
Department of Veterans Affairs Network Contracting Office 21 VA Sierra Nevada Healthcare System 975 Kirman Avenue Reno NV 89502
Charee Harris 775-788-5511
Project No.: 612A4-25-004 Project Title: Renovate Operating Room (OR) for Hybrid Installation Project Location: 10535 Hospital Way, Mather CA 95655
Description: The VA Northern California Healthcare System has a requirement to renovate the operating rooms for a hybrid installtion in accordance with the statement of work, specifications and drawings.
NAICS: 236220 - Commercial and Institutional Building Construction Size Standard: $45 Million
This acquisition is set-aside 100% for certified/verifiable Service-Disabled Veteran Owned Small Business Concerns
(SDVOSB)
Acquisition method is competitively negotiated best value tradeoff selection process in accordance with FAR 15.103-2.
A price proposal and a technical proposal are both required. Please reference evaluation and submittal criteria.
Although not mandatory, all interested parties are strongly encouraged to attend the pre-proposal conference and site visit.
Bid bonds, payment bonds, and performance bonds shall be required under this solicitation and any resulting contract.
The estimated magnitude of this construction project is between $10,000,00.00 and $20,000,000.00. This information is provided in accordance with VAAR 836-204.
An organized site visit is scheduled for December 11, 2025, at 10:00 AM Pacific Time VA Northern California Healthcare System, 10535 Hospital Way, Flag poles Front of Building 650, Mather California 95655
10 500
X X 52.211-10
X 10
1 1000 PST
01-15-2025
X
14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY
PHONE: FAX:
28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code)
(Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
(Type or print)
(4 copies unless otherwise specified)
(Type or print) (Type or print)
(Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C261
Department of Veterans Affairs Network Contracting Office 21 Southern Nevada Healthcare System 6900 N. Pecos Road, Building 6 North Las Vegas NV 89086
Financial Services Center P.O. Box 149971
Austin TX 78714-9971
Charee K. Harris Contracting Officer NCO 21
Table of Contents
PART I - THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,
ALTERATION, OR REPAIR)– BACK
Temporary OR Trailers:
Support Areas Beyond the Trailers:
Commissioning and Certification:
Phased Construction Management:
Support Areas Beyond the ORs:
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.209-5 CERTIFICATION REGARDING RESPONSIBILITY MATTERS (AUG
2020)
2.2 52.216-1 TYPE OF CONTRACT (APR 1984)
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE
OF THE WORK (MAY 2014)
2.4 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION
MATERIALS UNDER TRADE AGREEMENTS (MAY 2014)
2.5 52.228-1 BID GUARANTEE (SEP 1996)
2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE)
(FEB 2021)
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB
1998)
2.10 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR VERIFIED
SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (NOV 2022)
2.11 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND
VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)
2.12 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE
RESOLUTION (OCT 2018)
2.13 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
2.14 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY
ACCESSIBILITY NOTICE (FEB 2023)
2.15 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES
INCORPORATED BY REFERENCE (JAN 2008)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
3.2 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—
CERTIFICATION (NOV 2021)
GENERAL CONDITIONS
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND
CERTIFICATIONS (DEC 2014)
4.2 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING
RESPONSIBILITY MATTERS (OCT 2018)
4.3 52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022)
4.4 52.219-27 NOTICE OF SET-ASIDE FOR, OR SOLE-SOURCE AWARD TO,
SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS (SDVOSB) CONCERNS
ELIGIBLE UNDER THE SDVOSB PROGRAM (FEB 2024)
4.5 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION
(JAN 2025)
4.6 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)
4.7 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL
LABOR RELATIONS ACT (DEC 2010)
4.8 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
4.9 52.223-20 AEROSOLS (MAY 2024)
4.10 52.223-21 FOAMS (MAY 2024)
4.11 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV
2018)
4.12 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR
2019)
4.13 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)
4.14 VAAR 852.237-75 KEY PERSONNEL (OCT 2019)
4.15 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) .. 46
4.16 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT
(SEP 2019)
4.17 MANDATORY WRITTEN DISCLOSURES
4.18 IT CONTRACT SECURITY
4.19 SUPPLEMENTAL INSURANCE REQUIREMENTS
4.20 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION
(APR 2019)
4.21 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)
4.22 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT
ADMINISTRATION (OCT 2020)
4.23 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)
4.24 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)
4.25 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR
PERSONNEL (MAY 2020)
4.26 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)
4.27 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—
CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)
(DEVIATION)
4.28 VAAR 852.222-71 COMPLIANCE WITH EXECUTIVE ORDER 13899
(DEVIATION)(APR 2025)
4.29 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)
4.30 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION
CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)
PROJECT TITLE: 612A4-25-004 Renovate OR Area for Hybrid Installation
PROJECT LOCATION: Renovation and Expansion of Surgical Facilities at Building 700, VA Northern California Health Care System
1. SCOPE OF WORK:
This project involves the comprehensive renovation, expansion, and modernization of the existing surgical operation room (OR) area located on the second floor of Building 700, totaling approximately 12,500 square feet. The scope includes architectural, structural, mechanical, plumbing, electrical, and low-voltage systems to create a state-of-the-art surgical environment aligned with current VHA Design Guides and standards. The period of performance shall be 500 calendar days.
Project Objectives:
• Renovate and upgrade the existing four ORs to meet contemporary clinical and safety standards.
• Expand the surgical suite to include a 5th OR specifically configured as a Hybrid OR suite to support advanced surgical procedures.
• Optimize workflow and operational efficiency through strategic layout design.
• Ensure minimal disruption to ongoing VA operations via phased construction and temporary facilities.
• Address existing condition deficiencies, with a focus on critical systems such as plumbing, mechanical, electrical, and low-voltage infrastructure.
Additional Requirements:
Temporary OR Trailers:
The VA will supply three (3) temporary OR trailers to serve as interim surgical facilities during the renovation process.
These trailers must be set up, constructed, certified, and commissioned on-site prior to the commencement of renovation activities on the second-floor OR areas.
The contractor shall coordinate installation, setup, testing, and certification of these trailers, ensuring they meet all applicable safety, building, and clinical standards.
Support Areas Beyond the Trailers:
The scope extends to the support infrastructure necessary for the effective utilization of the trailers, including:
• Temporary utility connections and distributions.
• Pathways for patient transfer and personnel movement.
• Ancillary support spaces for staff and clinical functions related to the trailers.
• Installation and connection of utilities (HVAC, electrical, plumbing, medical gas, communications)
• Testing and certification to ensure compliance with all applicable safety, building, and clinical standards.
• Integration of trailers into the overall operational workflow, including access routes and support systems.
The trailers shall be fully operational and ready for use during the first phase of construction, supporting ongoing surgical procedures and maintaining clinical capacity.
Commissioning and Certification:
The contractor shall work with third-certified inspectors and relevant authorities to ensure all temporary trailers are properly certified and commissioned prior to their use. This includes verifying all systems—HVAC, electrical, plumbing, medical gas, safety, and communications—are fully functional and compliant.
Phased Construction Management:
The work shall be executed in phases, with the temporary trailers serving as interim surgical facilities to ensure continuous operational capacity.
The contractor shall develop and implement a detailed phased construction plan that minimizes operational disruptions and meets VA scheduling requirements.
Support Areas Beyond the ORs:
The scope includes renovation and upgrade of all adjacent support and auxiliary areas integral to surgical operations, such as:
• Mechanical and electrical rooms support the surgical suite.
• Utility connections and distributions.
• Installation and connection of utilities (HVAC, electrical, plumbing, medical gas, communications).
This project will consist of the following Brand Name or Equal Items:
1) Fortress stainless steel wall systems. A fully integrated Fortress stainless steel wall system, five (5) in total with one (1) each per operating room (OR), is required to meet the Government’s minimum needs for patient safety and quality of services required in ORs.
Five (5) Fortress stainless steel wall systems are to be configured and installed within the OR suites and fully integrated within the building infrastructure.
2) This procurement is for the installation of brand name SLD Technology Modular Ceiling Systems within five (5) operating rooms for the VANCHS. A fully integrated modular ceiling system, five (5) total with one (1) each per operating room (OR), is required to meet the Government’s minimum needs for patient safety and quality of services required in ORs.
3) Programming and Controls - Johnson Controls. Description: Johnson controls programming and controls system for the project. This installation will include programming in the building to monitor equipment and utilities systems from our utility plant; Testing and commissioning the system at startup to ensure programming was successful.
4) Fire Alarm System Secutron- Secutron brand name fire alarm, system programming, alarms, and devices that will operate within the Mather Metasys system.
5) PIV Card Reader System- HID PIV class readers - HID card readers that will operate with this brand name interface, installed in Northern California Health Care System (NCHSC) for compatibility with existing CCure9000 software.
6) Pneumatic Tube Swiss Log - Existing tube station will need to be relocated to new permanent location inside the Pharmacy. Associated tubing will need to be routed above ceiling to drop to the new location.
///////////////////////////////////////////////////End Statement of Work////////////////////////////////////////////////////////
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO
BIDDERS/OFFERORS
1. INTRODUCTION:
a. These instructions prescribe the format of Offers. Offers are defined as consisting of both Prime Contractor’s Price Proposal and Prime Contractor’s Technical Proposal.
These instructions describe the approach for the development and presentation of the required information and documentation. These instructions are designed to ensure the submission of necessary information and documentation to provide for the comprehensive evaluation of offers.
b. Offerors are cautioned to carefully review this solicitation prior to commencing preparation. For offers to receive full consideration for award, offerors shall ensure that the information and documentation furnished in support of the price proposal and the technical proposal are current, factual, complete, and accurate.
c. Offerors are strictly advised to comply with all instructions within this solicitation to ensure submission of a complete Prime Contractor Offer. Failure to furnish a complete offer with the instructions of this solicitation by the required time and date may result in the Offeror’s proposal being determined ineligible.
d. The Government intends to award without discussions, unless discussions are in the best interest of the Government.
2. CONTRACT TYPE:
a. The contract awarded will be a firm fixed price (FFP) contract.
b. This solicitation is a total SDVOSB set-aside. The offeror MUST have an active Unique
Entity Identification (UEI) number and be current in System for Award Management (SAM). SDVOSB firms must be Certified Veteran Eligibility (CVE) verified prior to the submission of proposals.
3. SUBMISSION INSTRUCTIONS:
a. Each offeror shall also provide one (1) emailed copy of the technical proposal and one
(1) emailed copy of the price proposal, to arrive on or before the due date/time to charee.harris@va.gov.
The subject line of the email must cite RFP: 36C26126R0009. In no circumstances shall file size exceed 10MB. Multiple emails are acceptable.
b. Faxed proposals are not permitted under any circumstances.
c. Please ensure you allow time for email transmission.
d. Offerors MUST mark the subject line of the email as 36C26126R0009 Renovate OR for
Hybrid Installation Technical Proposal and 36C26126R0009 Renovate OR for Hybrid Installation Price Proposal.
e. Offer Due date is January 15, 2026, at 10:00 A.M. Pacific Time.
4. QUESTIONS CONCERNING THIS RFP:
All Requests for Information (RFIs) regarding this RFP shall be submitted in writing and received no later than Tuesday, January 6, 2025, 2026, at 10:00 AM Pacific Time to allow replies to reach all prospective offerors in a timely manner. All RFIs shall be sent via email to Charee Harris at charee.harris@va.gov.
mailto:charee.harris@va.gov
5. PRE-PROPOSAL SITE VISIT:
Offerors are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of performing these services. In no event shall failure to inspect the site constitute grounds for a claim after contract award. See block 10 of SF1442 for site visit details.
6. PROPOSAL FORMAT:
a. All commitments made to the proposal may become a part of the resultant contract. The data submitted with each proposal shall be complete and concise, but not overly elaborate. Reliance on promotional brochures is discouraged.
b. The Technical Volume shall not exceed the page limits stated herein. If the page limits are exceeded, the pages in excess of the limit will not be read or considered. Page limits for entire Technical Proposal shall not exceed thirty-five (35) pages front and back. The CPARS/Past Performance questionnaires do not count as part of the 35 pages.
c. Page Limits Shall Include: All appendices, charts, graphs, diagrams, tables, photographs, drawings, etc. except as noted in the instructions. Text lines will be single-spaced.
d. Written proposals shall be prepared on standard 8.5 x 11-inch paper (charts may be landscaped but must be on 8.5 x 11-inch paper) and shall be in a legible font size (11 or 12 point). All pages of each proposal shall be appropriately numbered and identified with the RFP number. For ease of reference, consecutive page numbering with tabs is required. ** The schedule sheet may be larger for legibility.
e. Email Copy: Provide one (1) email copy of the complete proposal (Volumes 1 and 2) as specified above.
f. Indexing: Each volume will contain a “Table of Contents” for that volume. The “Table of Contents” will identify major elements of technical and price proposals. Tab indexing will be used to identify Sections as appropriate. Table of Contents and Tab indexes do not count toward page limitation.
g. Offerors may, at the discretion of the Government, be asked to provide information for clarification purposes regarding their proposals in accordance with FAR 15.202.
Requests for such clarification information do not constitute negotiations as outlined in FAR 15.204. When a competitive range is established, the government may enter into negotiations.
h. The offeror shall be held responsible for the validity of all information supplied in their proposal, including information provided by potential subcontractors. Should subsequent investigation disclose that the fact and conditions were not as stated, the proposal may be rejected and receive no further consideration.
i. If revised proposals are requested, the number of revised copies to be submitted shall be the same as those of initial proposals unless stated otherwise.
7. PROPOSAL VOLUME CONTENTS:
TECHNICAL VOLUME (BINDER - 1): Include the following information on the cover:
Company Name Renovate OR for Hybrid Installation
RFP: 36C26126R0009
Volume 1 – Technical Proposal
BINDER INDEX:
Tab 1: Technical Management Approach Tab 2: Key Personnel Experience, as specified ...
Tab 3: Schedule/Phasing Approach, as specified ...
Tab 4: Corporate Project Experience, as specified Tab 5: Relevant Past Performance, as specified ...
a. The Technical volume shall include necessary information regarding the offeror’s ability to performance requirements outlined in the solicitation. Failure to provide a Technical Proposal in accordance with the solicitation instructions shall render an offeror’s proposal incomplete and ineligible for award.
b. Similar scope and complexity, when referred to in the evaluation factors, is defined as projects that consist primarily with Modular Swing spaces, HVAC, Flooring (same type) and trailer swing space components, modernization, repair, and maintenance.
c. Similar magnitude (size), when referred to in the evaluation factors, is defined as projects that were valued between $10,000,000 and $20,000,000.
d. The project personnel included in the offer shall be the personnel that are assigned to the project for the entire project. In the event a substitution must be made during the course of the project, the contractor shall submit to the contracting officer a request that includes a resume of the proposed substitution that indicates the person meets all of the qualifications in the evaluation factor included in this solicitation.
e. This project requires four positions to be assigned: Project Manager, Superintendent, Safety Officer, and Quality Control Officer. The Superintendent must be full-time and dedicated only to this project. The Superintendent must perform full-time in this role and no other role. The Superintendent must not perform other duties or responsibilities, i.e., safety officer, quality control officer, job site or home office project manager during the project duration.
f. The letter of intent for project personnel shall contain the following information:
i. Current Employees - Letter that is signed by both the employee and contractor lists the solicitation the contractor is proposing on and their proposed roll on the project.
ii. Potential Employees - Contractor must provide a letter of intent signed by both the Contractor and potential employee that lists the following:
1. Specific solicitation/project being offered on
2. The position the proposed employee will be taking
3. Statement that the proposed employee has NO known conflicts that would prevent him or her from completing this project if awarded and that this person possesses the skills necessary to perform the required tasks as assigned.
**Letters of Commitment/Intent are only required for those personnel being hired specifically for the project and are not current employees. A letter is not required for current employees.
g. If proposed as a joint venture, a copy of the executed joint venture agreement shall be included in the proposal.
PRICE VOLUME (BINDER – 2): Include the following information on the cover:
Company Name Renovate OR for Hybrid Installation
RFP: 36C26126R0009
Volume 2 – Price
BINDER INDEX
Tab 1: Standard Form 1442 (fully completed and signed); and acknowledgment of all amendments by either entering data in block 19 of the SF1442 or, completing blocks 15 a, b and c of the Amendment(s) (SF30’s) and returning with offer.
Tab 2: Cost Break-Out Sheet (fully completed) for each project 612A4-25-004 Tab 3: SF24 Bid Bond with Raised Seals, and Power of Attorney (original bid bond, fully completed/signed as required) Tab 4: Safety & Environmental Record Documentation Tab 5: Experience Modification Rate (EMR) Documentation Tab 6: Representations and Certifications as applicable along with a completed
852.219-75.
*Note: Offerors are responsible for insuring and verifying their offer and all required documents are received at the address designated in block 8 of the SF1442 Solicitation (and further specified directly below) by the date and time specified in block 13A of the SF 1442 Solicitation (subject to amendment).
PROSPECTIVE CONTRACTORS’ RESPONSIBILITY: Purchases shall be made from, and contracts shall be awarded to, responsible prospective contactors only. The presumed winning offer must be determined as “Responsible” by the Contracting Officer in accordance with FAR Part 9, Contractor Qualifications. To aid in making this determination, offerors shall provide:
1. Safety & Environmental Record information as specified below
2. Experience Modification Rate (EMR) information as specified below
3. Completed Representations and Certifications; FAR 52.209-5, and 52.209-7. (See Section K of RFP as appropriate).
This information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines below or submit this information may result in a determination of non-Responsibility and make the offer ineligible for award. The Contracting Officer will obtain additional information as needed and specified in FAR 9.105-1 to make the Determination of Responsibility, to include, but not limited to the Federal Awardee Performance and Integrity Information System (FAPIIS), Excluded Parties List System (EPLS) and Past Performance Information Retrieval System (PPIRS).
PER VHA DIRECTIVE 7715 (06 April 2017: SAFETY & ENVIRONMENTAL RECORD AND EXPERIENCE MODIFICATION RATE (EMR): To be eligible for consideration and award, the contractor shall have no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years and have an EMR of equal to or less than 1.0.
All offers shall submit the following information pertaining to their past Safety & Environmental Record and EMR with their proposal.
1. SAFETY & ENVIRONMENTAL RECORD: A self-certification on company letterhead that the Offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.
2. EMR: All offerors shall submit information regarding their current EMR. This information shall be obtained from the Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If an offeror’s EMR is above 1.0, Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the EMR, and the anticipated date the EMR may be reduced to 1.0 or below.
ADDITIONAL SOLICITATION INFORMATION: See Provision 52.236-27 for specific information regarding the project pre-proposal site visit. This pre-proposal site visit will be the only opportunity for potential offerors to visit the site. All potential contractors, subcontractors, and suppliers are strongly encouraged to attend this pre-proposal site visit.
REQUEST FOR INFORMATION (RFI): To obtain clarifications and/or additional information concerning the contract requirements, submit a written RFI utilizing the RFI Form included in this RFP, and send it via email to charee.harris@va.gov. See RFI Form for specifics.
RFIs will be responded to as necessary in amendment format and will be posted on FBO (now called Contract Opportunities). Deadline for submission or RFIs for this RFP is January 6, 2025, at 10:00 AM Pacific Time. No questions will be answered after this date/time unless determined to be in the best interest of the Government as determined by the Contracting Officer.
Telephone request for information will not be accepted or returned.
SYSTEM FOR AWARD MANAGEMENT (SAM): Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at https://sam.gov/SAM/ and enter all mandatory information into the system. Award cannot be made until the contractor has been registered. Offerors are encouraged to ensure that they are registered in SAM prior to submitting their offer. (See FAR 4.1102)
ADDITIONAL VET CERTIFICATION INFORMATION:
(a) Eligibility of SDVOSBs continues to be governed by the Small Business Administration regulations, 13 CFR subparts 125.8 through 125.13, as well as the FAR, except where expressly directed otherwise by the VAAR, and 38 CFR verification regulations for SDVOSBs.
(b) At the time of submission of offer, the offeror must represent to the contracting officer that it is a—
(1) SDVOSB concern
(2) Small business concern under the North American Industry Classification System (NAICS) code assigned to the acquisition; and
(3) Verified for eligibility in the Small Business Dynamic Search.
(c) A joint venture may be considered an SDVOSB or VOSB concern if
(1) At least one member of the joint venture is an SDVOSB or VOSB concern and makes the representations in paragraph (b) of this section.
(2) Each other concern is small under the size standard corresponding to the NAICS code assigned to the procurement.
(3) The joint venture meets the requirements of paragraph 7 of the size standard explanation of affiliates in FAR 19.101; and
(4) The joint venture meets the requirements of 13 CFR 125.15(b), modified to include Veteran-owned small businesses where this CFR section refers to SDVOSB concerns.
Any SDVOSB or VOSB concern (nonmanufacturer) must meet the requirements in FAR 19.102(f) to receive a benefit under this program.
mailto:charee.harris@va.gov https://sam.gov/SAM/
JOINT VENTURES: See 13 C.F.R. § 121.103(h)
(h) Affiliation based on joint ventures. A joint venture is an association of individuals and/or concerns with interests in any degree or proportion consorting to engage in and carry out no more than three specific or limited-purpose business ventures for joint profit over a two-year period, for which purpose they combine their efforts, property, money, skill, or knowledge, but not on a continuing or permanent basis for conducting business generally.
This means that a specific joint venture entity generally may not be awarded more than three contracts over a two-year period, starting from the date of the award of the first contract, without the partners to the joint venture being deemed affiliated for all purposes. Once a joint venture receives one contract, SBA will determine compliance with the three awards in two years rule for future awards as of the date of initial offer including price.
As such, an individual joint venture may be awarded more than three contracts without SBA finding general affiliation between the joint venture partners where the joint venture had received two or fewer contracts as of the date it submitted one or more additional offers which thereafter result in one or more additional contract awards. The same two (or more) entities may create additional joint ventures, and each new joint venture entity may be awarded up to three contracts in accordance with this section. At some point, however, such a longstanding inter-relationship or contractual dependence between the same joint venture partners will lead to the finding of general affiliation between and among them.
For purposes of this provision and in order to facilitate tracking of the number of contract awards made to a joint venture, a joint venture must be in writing and must do business under its own name, and it may (but need not) be in the form of a separate legal entity, and if it is a separate legal entity it may (but need not) be populated (i.e., have its own separate employees). SBA may also determine that the relationship between a prime contractor and its subcontractor is a joint venture, and that affiliation between the two exists, pursuant to paragraph (h)(4) of this section.
**If there is a Joint Venture, we will allow the extra pages for this information it shall be referenced as an attachment
NOTICE TO PROCEED (NTP): A notice to proceed (NTP) shall be issued after award of a fully executed contract. The NTP date and time are “to be determined” after award to a successful offeror. Primary factor in determination to issue NTP shall be the Prime Contractor submission of, and the Government review and approval of both Payment and Performance Bonds, both of which are enforceable legal documents.
SECURITY REQUIREMENTS (GENERAL):
1. All personnel employed by the contractor in the performance of work, issued under this contract, or any representative of the contract shall abide by all security instructions and directives of the Department of Veterans Affairs. Employees are responsible for safeguarding all government property provided for contractor use.
2. At the close for each work period, government facilities, equipment and materials shall be secured, lights, and all doors and window secured.
3. The contractor and, as applicable, subcontractor shall not employ persons for work on this contract if such employee is identified as a potential threat to the health, safety, security, general well-being or operational mission of the station/campus and its population, nor shall the contractor or subcontractor employ persons under this contract who have an outstanding criminal warrant as identified during background checks.
4. Contractors shall ensure their employees and those of their subcontracts have the proper credentials allowing them to work in the United States. Employees and subcontractors later found to be undocumented, or illegal aliens will be remanded to the proper authorities.
5. Contractor Badge Policies: All requests for contractor ID badges will be submitted through the station Police/Security office.
6. Vehicle registration, proof of insurance and a valid driver’s license must be presented for all vehicles while operating on the station/campus. All vehicles entering the station/campus are subject to search. Any refusal or non-consent by an employee will result in termination of their access and immediate confiscation of their ID badge.
2.1 52.209-5 CERTIFICATION REGARDING RESPONSIBILITY MATTERS
(AUG 2020)
(a)(1) The Offeror certifies, to the best of its knowledge and belief, that—
(i) The Offeror and/or any of its principles
(A) Are [ ] are not [ ] presently debarred, suspended, proposed for debarment, or declared ineligible for the award of contracts by any Federal agency.
(B) Have [ ] have not [ ], within a three-year period preceding this offer, been convicted of or had a civil judgment rendered against them for: commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State, or local) contract or subcontract; violation of Federal or State antitrust statutes relating to the submission of offers; or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, tax evasion, violating Federal criminal tax laws, or receiving stolen property (if offeror checks "have," the offeror shall also see 52.209-7, if included in this solicitation);
(C) Are [ ] are not [ ] presently indicted for, or otherwise criminally or civilly charged by a governmental entity with, commission of any of the offenses enumerated in subdivision (a)(1)(i)(B) of this provision; and
(D) Have [ ], have not [ ], within a three-year period preceding this offer, been notified of any delinquent Federal taxes in an amount that exceeds the threshold at 9.104–5(a)(2) for which the liability remains unsatisfied.
(1) Federal taxes are considered delinquent if both of the following criteria apply:
(i) The tax liability is finally determined. The liability is finally determined if it has been assessed. A liability is not finally determined if there is a pending administrative or judicial challenge. In the case of a judicial challenge to the liability, the liability is not finally determined until all judicial appeal rights have been exhausted.
(ii) The taxpayer is delinquent in making payment. A taxpayer is delinquent if the taxpayer has failed to pay the tax liability when full payment was due and required. A taxpayer is not delinquent in cases where enforced collection action is precluded.
(2) Examples.
(i) The taxpayer has received a statutory notice of deficiency, under I.R.C. Sec. 6212, which entitles the taxpayer to seek Tax Court review of a proposed tax deficiency. This is not a delinquent tax because it is not a final tax liability. Should the taxpayer seek Tax Court review, this will not be a final tax liability until the taxpayer has exercised all judicial appeal rights.
(ii) The IRS has filed a notice of Federal tax lien with respect to an assessed tax liability, and the taxpayer has been issued a notice under I.R.C. Sec. 6320 entitling the taxpayer to request a hearing with the IRS Office of Appeals contesting the lien filing, and to further appeal to the Tax Court if the IRS determines to sustain the lien filing. In the course of the hearing, the taxpayer is entitled to contest the underlying tax liability because the taxpayer has had no prior opportunity to contest the liability. This is not a delinquent tax because it is not a final tax liability. Should the taxpayer seek tax court review, this will not be a final tax liability until the taxpayer has exercised all judicial appeal rights.
(iii) The taxpayer has entered into an installment agreement pursuant to I.R.C. Sec.
6159. The taxpayer is making timely payments and is in full compliance with the agreement terms. The taxpayer is not delinquent because the taxpayer is not currently required to make full payment.
(iv) The taxpayer has filed for bankruptcy protection. The taxpayer is not delinquent because enforced collection action is stayed under 11 U.S.C. 362 (the Bankruptcy Code).
(ii) The Offeror has [ ] has not [ ], within a 3-year period preceding this offer, had one or more contracts terminated for default by any Federal agency.
(2) Principal, for the purposes of this certification, means an officer, director, owner, partner, or person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a division or business segment; and similar positions).
THIS CERTIFICATION CONCERNS A MATTER WITHIN THE JURISDICTION OF AN
AGENCY OF THE UNITED STATES AND THE MAKING OF A FALSE, FICTITIOUS, OR
FRAUDULENT CERTIFICATION MAY RENDER THE MAKER SUBJECT TO PROSECUTION
UNDER SECTION 1001, TITLE 18, UNITED STATES CODE.
(b) The Offeror shall provide immediate written notice to the Contracting Officer if, at any time prior to contract award, the Offeror learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances.
(c) A certification that any of the items in paragraph (a) of this provision exists will not necessarily result in withholding of an award under this solicitation. However, the certification will be considered in connection with a determination of the Offeror's responsibility. Failure of the Offeror to furnish a certificate or provide such additional information as requested by the Contracting Officer may render the Offeror non-responsible.
(d) Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render, in good faith, the certification required by paragraph (a) of this provision. The knowledge and information of an Offeror is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.
(e) The certification in paragraph (a) of this provision is a material representation of fact upon which reliance was placed when making award. If it is later determined that the Offeror knowingly rendered an erroneous certification, in addition to other remedies available to the Government, the Contracting Officer may terminate the contract resulting from this solicitation for default.
(End of Provision)
2.2 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price Requirements contract resulting from this solicitation.
(End of Provision)
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—
SECONDARY SITE OF THE WORK (MAY 2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.4 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—
CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "designated country construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials Under Trade Agreements" (Federal Acquisition Regulation (FAR) clause 52.225-11).
(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material, other than designated country construction material, that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material, and the offeror shall be required to furnish such domestic or designated country construction material. An offer based on use of foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.5 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 100 percent of the bid price or 20,000,000.00, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID
GUARANTEE) (FEB 2021)
(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and
(2) Standard Form 28, Affidavit of Individual Surety.
(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.
(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.
(End of Provision)
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Charee Harris
Hand-Carried Address:
N/A email only
Mailing Address:
Network Contracting Office 21 Email: charee.harris@va.gov
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB
1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for—
December 11, 2025, at 10:00 A.M. Pacific Time
(c) Participants will meet at—
Flag poles Bulding 650, 10535 Hospital Way, Mather CA 95655
(End of Provision)
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE
(FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer.