RFI 33 - Cryoblation.pdf
PDF 683 KB Posted
- Attached to
- 36C26125R0084 - Radiology Patient Safety
- Solicitation number
- 36C26125R0084
About this file
This document is a detailed implementation plan for the procurement of a Visual-ICE MRI Cryoablation System for VA Palo Alto, created by Boston Scientific on September 13, 2022. The system uses extreme cold to destroy tissue through a process based on the Joule-Thomson effect, with custom cabling designed for the specific facility. The pre-installation requires five key steps: a group meeting to understand layout, purchase order receipt, on-site meeting to finalize location, facility sign-off on measurements, and facility build-out of a filter plate.
The system will be delivered in three containers and installed by a Boston Scientific Field Engineer, with the entire process taking approximately 20 weeks after facility site plan sign-off. Specific facility requirements include an accessible electrical outlet, a 6 x 8-inch penetration panel space, and provisions for junction boxes and cable conduits. The system requires both Argon and Helium high-pressure gases for operation, with precise purity and technical specifications detailed in the document. The installation involves pre- and post-scanning with a phantom, and the facility must have a physicist or technician present during the process. Boston Scientific emphasizes the importance of placing the purchase order before January 1, 2023, to lock in the current pricing.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
©2022 Boston Scientific Corporation or its affiliates. All rights reserved.
VISUAL-ICE MRI CRYOABLATION SYSTEM
Created for VA Palo Alto September 13, 2022
OVERVIEW
1. Project Background and Description
Procurement of the Visual-ICE MRI Cryoablation System
• Cryoablation is a process that uses extreme cold to destroy or damage tissue
• Treatment delivered by the Cryoablation System and Needles are based on the Joule-Thomson effect in which compressed gases change temperature when the gas expands to a lower pressure
• The Cryoablation Systems controls the gas delivered from cylinders of compressed gas and circulated through closed tip cryoablation needles creating the freezing and thawing
• Each Visual-ICE MRI Cryoablation System cabling is custom designed to your specific facility
• Pre-install is outlined in steps below and must be completed prior to build of the custom system
• Post install- testing and training will be carried out
2. Pre-Installation Scope
There are 5 main steps that need to occur prior to shipping and installation of the Visual-ICE MRI Cryoablation System to make sure the suite is ready to accept the Visual-ICE Cryoablation System.
Group meeting to understand floor plan and layout
Purchase order is received for capital acquisition
On-site meeting to finalize location for junction boxes and measure for cable lengths (see appendix A)
Facility signs off on document containing measurements and floor plan
Facility build-out of blank plate (filter plate)
3. Facility Build Out Requirements
Accessible outlet in control room within 6 feet of the suggested console location during cases
• ELECTRICAL SPECIFICATIONS
• Input Voltage: 100 to 240 VAC, single phase
• Input Frequency: 50-60Hz
• VA Rating: 450 VA
• IP Rating: IP10
• Fuse Rating: T 5.0A
VHAPALGargM Text Box
ATTACHMENT D
Penetration (Filter) Plate hole to be cut, threaded, and installed by customer facility/contractor – (if drywall cavity is required, i.e. - not able to utilize existing MRI penetration panel for pass through, a filter plate frame (wall frame that will accept Visual-ICE system filter plate to be mounted with threaded mounting holes matching filter plate penetration to accept filter plate, blank plate and template is provided during site visit
• Footprint of plate: 8 in x 6 in
• Note: about 12” of clearance is needed from the front of the Penetration Panel to allow space for gas, electrical and fiber optics connections and 2-3 in at top and sides for clearance and connections
2 1/2in-3in holes in wall for junction box cable conduit runs at each junction box location above or below junction box
• Will be determined at site visit
Tank storage location mounts if applicable, (some sites have tanks brought in on carts for cases and do not keep them in control room)
• Based on feedback from the pre-call gas will be brought in on carts at this facility
If Visual-ICE MRI cabling to Visual-ICE MRI from junction box will remain in place, facility should install cable hooks (this method ensures cable connections at junction box remain fastened. Same can hold true for MRI suite if applicable.
• Based on feedback on the pre-call this system will be stored when not in use
4. Delivery of System
The system will ship in 3 containers and will ship via freight company
1 crate- Mobile Connection Panel
1 crate- Console
1 box- with cabling, junction boxes, penetration panel with connections
5. Installation
Installation is performed by a Boston Scientific Field Engineer that has been trained and has experience in installing into a MR Suite. Installation and testing will take approximately 4-6 hours.
Facilities individuals on site during installation:
Physicist or Technician to perform a pre-scan using phantom once all hospital facility/contractor pre-work has been completed (a post scan will be required after installation of Visual-ICE MRI system to verify no artifact present)
Facilities representative, in case of questions
During installation, a tank of Helium and Argon gas should also be present for testing (see gas requirements below)
6. Gas Requirements
Gas is required during testing at time install and for all procedures.
Both Argon and Helium gas is required with the use of the Visual-ICE MRI Cryoablation System
7. High-Level Timeline/Schedule
Timeline for a custom-built Visual-ICE MRI system is 20 weeks. This timeline starts following facility sign-off site plan.
NEXT STEPS
Next steps to proceed with this project:
Activity Responsible Party Date
Boston Scientific to receive PO VA Palo Alto
Site visit by Boston Scientific Field Engineer
BSC to coordinate with Facility
Site Visit- the following individuals should be present from the facility during site visit:
MR Tech
All parties
Boston Scientific will provide blank plate
Physician
Physicist
Facilities during this visit
Sign-off of site plan created by Boston Scientific
VA Palo Alto
Start custom cable build and system build
Up to 20 weeks
Boston Scientific
VA Palo Alto to complete build out and placement of blank plate
VA Palo Alto
Facility and Boston Scientific check-in
2 weeks prior to shipping
Both parties
Shipping of Visual-ICE MRI Cryoablation System
Boston Scientific
Schedule and complete installation
Installation can be performed after hours if needed to avoid scheduling conflicts during the day
Both parties
Appendix A
Garg, Mohit
From: Reilly, Jennifer <Jennifer.Reilly@bsci.com>
Sent: Thursday, September 22, 2022 9:01 AM
To: Garg, Mohit; Kerkvliet, Julie
Subject: [EXTERNAL] Re: MRI Overview and Specifications
Hello Mohit, I hope this finds you well. Just wanted to let you know we had a conference call on Tuesday confirming the cryoablation system price increase in 2023. If we get the PO in before January 1, 2023 we can lock in your price. Like
Julie mentioned, just because we have a PO# doesn’t mean we need to install right away. We just want to ensure you get the best price.
Thank you, Jen
Jen Reilly
Interventional Oncology Consultant
(559) 801-5652 jennifer.reilly@bsci.com
From: Garg, Mohit <Mohit.Garg@va.gov>
Sent: Wednesday, September 14, 2022 10:52:54 AM
To: Kerkvliet, Julie <Julie.Kerkvliet@bsci.com>
Cc: Reilly, Jennifer <Jennifer.Reilly@bsci.com>
Subject: {External} RE: MRI Overview and Specifications
Thank you very much for the clear and concise scope of work document!
From: Kerkvliet, Julie <Julie.Kerkvliet@bsci.com>
Sent: Wednesday, September 14, 2022 4:56 AM
To: Garg, Mohit <Mohit.Garg@va.gov>
Cc: Reilly, Jennifer <Jennifer.Reilly@bsci.com>
Subject: [EXTERNAL] RE: MRI Overview and Specifications
Thank you for your well wishes, it will be a long road, but all will be good.
Please see the attached scope and please let me know if you have questions.
I did ask another facility the time and costs it took to do the build out of the panel at there site and they responded the following, “…once we knew where we wanted the plate to be placed and verified nothing was in the wall it took labor about 2 hours to complete. I do not have exact costs for this plate construction as we had other work being performed at the same time.” I can keep digging if you need costs estimates.
All the best, Julie
VHAPALGargM Highlight If we get the PO in before January 1, 2023 we can lock in your price.
MRI Components and Specifications
For planning purposes: The facility will need a 6in x 8in space available in the penetration panel.
Mobile Connection Panel (MCP)
• MR compatible- sits next to the scanner
• This is what the MR compatible needles will connect to in order to perform the treatment
• From the back of the MCP will be a Harness (3 connected cables) this will connect to the Junction Box in the room
• No electrical plug in is required
Harness
This is MR compatible and this is a connection for gas, electrical and fiber optics to flow
• from the MCP in the MR room to the Junction Box and
• from the Console in the Control Room to the Control Room Junction Box
Junction Box
There are 2 Junction Boxes one that sits on a wall mounted in the MR Room and one that is in the Control Room
• Location of these will be decided during BSC site visit- these will be strategically placed
• Junction Boxes will be installed by a BSC Technical Service Rep during full install of the system
• Extending from the Junction Boxes out the front will be the opposite end of the Harness Connection
• From the top or bottom of the box another set of cables will be attached- this will flow thru a 3in hole and connect to the penetration panel.
o The 3in hole will be drilled on site during install
Penetration Panel
This is the main connection for all connections. This space will need to be identified in current panel or a new panel will need to be created. This panel work is all done by the facility.
• Upon receipt of a PO a blank panel will be provided to prep the space for install
• During install from a BSC Technical Services Rep he will remove the blank panel and install the working
Penetration Panel
• Panel space needed- 6in tall x 8in wide
• Physicist and team will run measurement testing both pre and post install
Console
Is not MR compatible- sits in the Control Room
• Requires a basic electrical connection
• Input Voltage: 100 to 240 VAC, single phase
• Input Frequency: 50-60Hz
• VA Rating: 450 VA
• IP Rating: IP10
• Fuse Rating: T 5.0A
• The front of the Console will connect to the Harness
• The back of the Console will connect to Argon and Helium gas lines which will then run to tanks (see below for specifications)
Gas
Argon and Helium High Pressured Gas is required to run the needles
• Gas will be needed for every case and depending on treatment multiple tanks will be required
Best, Jen Reilly
Interventional Oncology Consultant
C: (559) 801-5652
E: jennifer.reilly@bsci.com
Boston Scientific https://www.bostonscientific.com/en-US/Home.html