This document is a Request for Information (RFI) form for the VA Northern California Health Care System (VANCHCS) McClellan Building 98 Power Upgrade project. The RFI specifically addresses a question about tree removal at the project site, with the VA project manager confirming that the tree located at the proposed site of the new MSB/ATS must be removed along with its roots due to interference with the planned underground ductbank and new conduit pathway. The RFI is tracked as RFI 004, dated 7/30/2025, and is associated with solicitation number 36C26125R0071, with an amendment number of 0002. The document was signed by the VA Project Engineer/Manager Fensua Vang and references additional details about site utilities in the project documentation.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C26125 R0071 I 36C261-25-AP-3702 I NRM 612A4-24-004 I McClellan Bldg 98 Power Upgrade
RFI FORM
Contractor Name:
Address:
Phone:
Email:
Please note: If submitting multiple RFls, please utilize one form for each RFI.
Send to:
Contracting Officer, Jose.Hernandez1@va.gov and Contract Specialist, Nicole.Renfrew@va.gov
RFI
(REQUEST FOR INFORMATION)
RFQ#: 36C26125R0071 CONTRACTOR RFI #: I
PROJECT NAME: DATE REQUESTED:
VANCHCS McClel lan
Bldg 98 Power Upgrade
ACQUISITION NO.:
N/A
REFERENCE:
DRAWING: SPECIFICATION SECTION:
DESCRIPTION OF PROBLEM OR INFORMATION BEING REQUESTED
Please be spectfic as possible:
1. Are there any plans to demolish the tree located on the new proposed location of the new
MSB/ATS due to the pathway of new conduits?
VA PROJECT MANAGER'S RESPONSE
VA TRACKING# FOR ALL RFls: AMENDMENT #:
VA PROJECT ENGINEER/MANAGER: DATE:
07/30/2025
0002RFI 004 36C26125R0071 Power Upgrade
7/30/2025
Yes, the tree that is located on the new proposed location of the MSB/ATS must be removed along with it's roots as it interferes with the location of the proposed underground ductbank. It will also interfere with the pathway of the new conduits.
The stated information in 36C26125R0071.docx on page 9 under "3. Site Utilities".
| 2025-07-30T11:29:32-0700 | |
| FENSUA VANG |