This document is an Amendment of Solicitation/Modification of Contract for VA Project 640-23-104, which involves correcting mental health deficiencies in Building 520 at the VA Palo Alto Health Care System in California. The amendment responds to multiple Requests for Information (RFIs) from potential bidders, providing clarifications on various technical and procedural aspects of the project.
Key details include a project scope involving flooring replacement, shower repairs, sally port modifications, and patient bedroom upgrades across four wards (A, B, C, D). The project will be completed in 4 phases, with each ward serving as a swing space during renovation. The solicitation requires a comprehensive construction solution including replacing nurse call systems, CCTV cameras, doors, toilets, and other fixtures. The proposal is due on June 24, 2025, at 3:00 PM PDT, with a total project duration of 840 days. The estimated project value is between $2-5 million, with a NAICS code of 236220 for Commercial and Institutional Building Construction. Contractors must be registered in SAM and verified as a Service-Disabled Veteran Owned Small Business (SDVOSB) through Network Contracting Office 21.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26125R0042 0003.docx | DOCX document | |
| 640-23-104_100_Submission_DRAWINGS_R1 Full set.pdf | ||
| 36C26125R0042 0001.pdf | ||
| WAGE DETERMINATION CA-HI-NV 5-18-24 for this USE CA20240018.pdf | ||
| Exhibit2_640-23-104_B520_PSU_SPECS.pdf | ||
| Supplemental Price Breakdown by Division Sheet.docx | DOCX document | |
| Exhibit1_640-23-104_B520_PSU_DRAWINGS.pdf | ||
| REQUEST FOR INFORMATION FORM 1.docx | DOCX document | |
| Exhibit3_640-23-104_B520_PSU_Cutsheets.pdf | ||
| 36C26125R0042_1.docx | DOCX document | |
| DRAFT_640-23-104_B520_PSU_SPECS.pdf | ||
| DRAFT Correct B520 SOW.pdf | ||
| 36C26125R0042_2.docx | DOCX document | |
| DRAFT 640-23-104_B520_PSU_DRAWINGS.pdf | ||
| DRAFT_640-23-104_B520_PSU_Cutsheets.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODECODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
0002 06-17-2025 640-25-4-5285-0009 640-23-104
Department of Veterans Affairs Network Contracting Office 21 (NCO 21) VA Pacific Islands Health Care System 711 Kapiolani Blvd Suite 200 Honolulu HI 96813
Department of Veterans Affairs Network Contracting Office 21 (NCO 21) VA Pacific Islands Health Care System 711 Kapiolani Blvd Suite 200 Honolulu HI 96813
To all Offerors/Bidders
36C26125R0042
X
X X
This amendment is to respond to the RFI questions.
The proposal due date remains the same at June 24, 2025 at 3:00PM PDT.
All other terms and conditions remain unchanged and in full force.
Charee Harris Contracting Officer
A.1 PRICE/COST SCHEDULE
PROPOSAL SCHEDULE
PROPOSAL ITEM #1 - GENERAL CONSTRUCTION: Complete Project 640-23-104 to repair Mental Health Deficiencies in Building 520 at the VA Palo Alto Health Care System, California.
Project Scope: Provide all labor, materials, tools, equipment, transportation, supervision, temporary power, startup, training, project documentation, and warranty necessary to accomplish the following TASKS:
1.1. Flooring Replacement: A-111 OFFICE, A-115 CONFERENCE ROOM, A-
117 ENCLOSED DAYROOM, A-120 OFFICE, A-121 BEDROOM, A-122
BEDROOM, A- 123 BEDROOM, A-125 BEDROOM, A-127 BEDROOM, A-
132 BEDROOM, A-133 BEDROOM, A-134 BEDROOM, A-135 BEDROOM,
A-136 BEDROOM, A137 BEDROOM, A143 BEDROOM, A145
OBSERVATION, A-150 NURSES STATION, A- 152 CONFERENCE, A-181
OFFICE, A-182 OFFICE, A-183 OFFICE, A-184 OFFICE, A-185 OFFICE, A-
186 OFFICE, A-187 OFFICE, A-189 OFFICE.
1.2. Shower Repair: BATHROOM A-143A, BATHROOM A-132A.
A. Remove floor tiles, concrete Slab, and shower drain. cast new concrete slab with proper slope to drain, reinstall shower drain at proper elevation and re-tile floor to match existing.
1.3. Sally Ports: B-C01, C-C01, D-C01
A. Replace existing Hollow Metal door to ward with new 4’-0” hollow metal door with 4” x 25” laminated glass door lite, Provide concealed closer, continuous hinges and ligature resistant lever. (90 min rated) Replace existing Wood door to Lobby with new 4’-0” hollow metal door with 4” x 25” laminated glass door lite, Provide concealed closer, continuous hinges and ligature resistant lever. (not rated)
B. Provide an Airphone intercom in lobby outside of each wards Sally port.
This device will ring the ward nursing station at the existing Airphone control panel and provide an intercom and camera for the nursing station staff.
C. Provide an Airphone intercom in lobby outside of each wards Sally port.
This device will ring the ward nursing station at the existing Airphone control panel and provide an intercom and camera for the nursing station staff.
1.4. Patient Bedrooms: B-121, B-122, B-123, B-125, B-126, B-127, B-132, B-133, B- 134, B-135, B-136, B-137, B-145, C-121, C-122, C-123, C-125, C-126, C-127, C-
132, C-133, C-134, C-135, C-136, C-137, C-145, D-121, D-122, D-123, D-125, D-
126, D-127, D-132, D-133, D-134, D-135, D-136, D-137, D-145.
A. Replace existing single pull cord Nurse-call stations with dual cordless push button plates secured with security screws one floor height and one wall height.
B. Wall mounted light fixtures to be removed, wall patched and painted to match adjacent.
C. Replace existing Patient toilets with anti-flood, shatter-proof, ligature resistant, stainless-steel toilets. One room per wing will receive a Bariatric rated toilet.
D. Replacement fixtures shall be compatible with existing utility rough in behind walls and in floor.
E. Remove existing paper towel Dispensers.
F. Remove and replace existing soap dispensers (2)
*** PROPOSAL ITEM 1 ---------------- $_____________________
1.5. Deductive Alternate, Ensuite Bathrooms: C-121A, C-122A, C-123A, C-125A, C- 126A, C-127A, C-132A, C-133A, C-134A, C-135A, C-136A, C- 137A, C-145A, D-121A, D-122A, D-123A, D-125A, D-126A, D-127A, D- 132A, D-133A, D-134A, D- 135A, D-136A, D-137A, D-145A.
*** PROPOSAL ITEM 2 ---------------- $_____________________
NOTE: A single award will be made on BID #1, but in the event the bid exceeds the funds available, a single award will be made on BID #2. In the event the bid exceeds the funds available for BID #2, a single award will be made on BID #3. In the event the bid exceeds the funds available for BID #3, a single award will be made on BID #4.
Offeror’s must submit a bid for all items to be considered for award. Failure to provide a price for all Bid Items will result in a rejection of the offer.
FOR OFFICIAL USE ONLY
REQUEST FOR INFORMATION (RFI) FORM
36C26125R0042 Construction Correct Mental Health Deficiencies
RFI #1 – Please advise location for Contractor temfacil and laydown yard.
o Response: LAYDOWN YARD CURRENTLY IN USE FOR HVAC WILL BE
MAINTAINED
RFI #2 – IF bidder has existing project on site, can Contractor use their current Temfacil/Laydown yard for this project which is close to bldg 520? And transfer to the new bldg 520 project laydown yard after completion of previous project?
o Response: YES, LAY DOWN AREA CURRENTLY IN USE WILL BE
MAINTAINED FOR THIS PROJECT
RFI #3 – Can VA recommend phasing requirements they expect for the scopes of work?
(EX: demolition on some areas needs to be after work hours or weekends-depending on existing staff occupancy of the space). It is expected that the scope will produce noise, vibration, utility impact and dust during performance of work. Please advise if VA can provide a list of rooms that will require to be performed during off-hours or phasing sequence for this project.
o Response: THE PROJECT PHASING AS OUTLINED IN THE NARRATIVE AND
SOW DOCUMENTS IS AS FOLLOWS:
o Each of the 4 wards, A B, C and D, constitute a 13 patient bedroom unit with associated support spaces.
o Each of the 4 Wards constitutes a complete functioning stand-alone unit and each is a near identical reflection of one another. As such the in-patient portion of the project will be completed in 4 phases. Each ward will be empty and fully available to the contractors to perform all work during normal business hours o • Ward D is currently unoccupied and will be renovated as Phase 1. Upon completion of Phase 1 ward D will serve as the swing space and patients and staff will be moved from Ward C.
o • Ward C will be renovated in Phase 2. Upon completion of Phase 2, Patients and Staff will be moved from Ward B.
o • Ward B will be renovated in Phase 3. Upon completion of Phase 3 VA staff can determine which of the 3 completed wards will be left unoccupied.
o • Ward A will be renovated in Phase 4. THE FLOORING REPLACEMENT IN
THE ADMIN OFFICE OF WARD A WILL NEED TO BE PERFORMED AFTER
HOURS. OR ON WEEEKENDS
o • A detailed phasing plan and schedule will be developed by the GC to include 30 DAY patient transition times between Phases.
RFI #4 – The Project require removal of existing specialty items (exit signs, FE cabinets, Mirrors, Towel dispensers, soap dispensers, pressure monitors, even doors and frames, PC workstations, etc.)- are all these items to be disposed of by contractor or turned over to VA? Please advise or provide list of items for demolition that VA wishes to be disposed of or keep.
o Response: PER GENERAL NOTE #6, EXISTING ITEMS SCHEDULEDED TO
BE REMOVED AND REPLACED SHOULD BE RETURNED TO THE VA.
EXCEPT FOR PLUMBING FIXTURES, LAUNDRY MACHINES AND TOILET
ACCESSORIES TO BE DISPOSED OF BY CONTRACTOR.
RFI #5 – Site Walk photos show some ceiling bubbles that seems to look like there was a leak above or a sign of water leak. Please confirm if this needs to be repaired and if a possible leak above floor needs to be repaired as well.
o Response: NOT IN THE SCOPE OF WORK FOR THIS PROJECT
RFI #6 – The RFP (par 2.2) noted that 3 of the 4 wards are occupied with the 4th ward as swing space. Does this mean that VA will relocate existing patients to the 4th ward to clear the space before renovation can begin? - does this mean that the area for renovation will be fully empty for contractors?
o Response: YES, see phasing description in question #3
RFI #7 – Are hazardous materials expected in this project? (Molds, Asbestos, Lead paints, etc.) IF yes, please provide hazmat survey if available.
o Response: No hazardous materials are expected
RFI #8 – For Bathroom floor repairs, the RFP noted ‘Remove Floor Tiles, Concrete Slab’..- Is the VA pertaining to the tile mortar/grout on the floor or the full structural concrete slab?
o Response: Structural concrete cutting will be required to remove/replace the floor drains in bathrooms A-132A & A-143A.
RFI #9 – What is the existing Nurse Call System in Bldg 520? (Jeron, Rauland, etc.)?
o Response: The existing system is a Simplex/Grinell Executone Zettler Series.
RFI #10 – Is PACS/Card Readers required in the project? What is the existing access control in the facility?
o Response: NO NEW CARD READERS ARE REQUIRED. EXISTING SYSTEM
TO REMAIN, WITH COVERS ADDED PER SPECIFICATIONS
RFI #11 – Plans noted removal of existing CCTV cameras. Please advise if VA will keep the old cameras or for become property of contractor.
o Response: PER GENERAL NOTE #6, EXISTING ITEMS SCHEDULEDED TO
BE REMOVED AND REPLACED SHOULD BE RETURNED TO THE VA.
RFI #12 – The RFP noted the new ‘CCTV system will be compatible with campus 520 cctv (AVIGILION) system and components shall comply with the latest VA police and safety guidelines.’ – Can bidder get the latest VA police safety guidelines for the cctv requirement?
o Response: Bidder can download the latest Physical Security Design Resiliency Manual (PSDRM) and VA directive 0730 requirements FROM THE VA WEB
SITE
RFI #13 – To assure compatibility of cctv system, does VA prefer the same brand to existing (AVIGILION) maybe an updated model or can bidder propose an approved equal?
o Response: Avigilon is the brand being installed in a concurrent campus wide security update project. Therefore, Avigilon is the basis of design and only approved brand for this project.
RFI #14 – Please confirm if the Superintendent can ‘dual hat’ as SSHO and /or QC for the Project.
o Response: SHALL BE SEPARATE INDIVIDUALS IN EACH ROLE
RFI #15 – Please confirm if project scheduler is not required to be submitted for pre-con submittals.
o Response: NOT REQUIRED FOR PRE-CON
RFI #16 – The specs require ‘Buildingblock’ for project management software platform-please confirm if contractor can use Procore instead.
o Response: ProCore is acceptable to the A/E.
RFI #17 – Please confirm if 21 days is enough for the facility to transfer patients to the newly renovated ward before work begins in the next phase? Is the 21 day duration included in the 840 total project duration per RFP?
o Response: YES, VA PATIENT TRANSFER TIME IS INCLUDED IN THE 840
DAY DURATION. WORK WILL BEGIN IN A VACATED WARD. ALLOW 30
CALENDAR DAYS FOR PATIENT MOVES PRIOR TO PHASES 2 - 4.
RFI #18 – Please advise number of shutdowns expected for this project. 21 days for minor and 45 days for major utility shutdowns- are these included in the 840 days project duration?
o Response: SHUTDOWNS ARE A PART OF GC MEANS AND METHODS. AS
THERE IS NO HVAC, FS OR MAJOR ELECTRICAL WORK IN SCOPE NO
SHUTDOWNS ARE ANTICIPATED.
RFI #19 - The RFP listed Electrical systems, HVAC and Fire Suppression for utility shutdowns. The project scope does not include HVAC and FS work. Please confirm.
o Response: There is no HVAC or FS work included in the project scope.
RFI #20 – RFP require Class IV Infection Control- this will require to exhaust work areas outside of the building. Please confirm facility allows removal of existing windows for this requirement.
o Response: THE EXISTING WARDS HAVE MULTIPLE EXTERIOR DOORS TO
SECURED COURTYARDS THAT SHOULD PROVIDE ADEQUATE
LOCATIONS FOR VENTILATION WITHOUT REMOVING WINDOWS.
RFI #21 – Is contractor allowed to use MC cable for electrical work?
o Response: REFER TO DIVISION 27 FOR NURSE CALL AND SECURITY
CAMERA CABLING. ALL OTHER NEW ELECTRICAL DEVICE RE-USE
EXISTING CABLING.
RFI #22 – Site Walk photos show possible mold remediation on some of the baseboards- Is there a possibility of mold remediation on this project?
o Response: NOT IN THE SCOPE OF THIS PROJECT
RFI #23 – Will VA consider replacing the existing Nurse call to Rauland Responder 5? - Note most VA Hospitals are going this route.
o Response: YES, SUBMIT AS PROPOSED EQUAL PER THE SOLICITATION
PROCESS.
RFI #24 - Nurse Call Specs in TIL Section 27 52 23, Drawings and SOW: Please CONFIRM that Jeron is the standard being deployed throughout the facility and is required? If so, will the Government please issue an amendment with the J&A.
o Response: BASIS OF DESIGN IS WESTCOM, ANY OTHER MFG. THAT ARE
EQUAL MAY BE SUBMITTED AS A PROPOSED EQUAL PER THE
SOLICITATION. THE BUILDING IS STAND-ALONE.
RFI #25 - Nurse Call Specs in TIL Section 27 52 23: Please CONFIRM the nurse call spares must be provided and compatible with the existing spare parts kit at the facility?
o Response: REFER TO RFI #24, PROVIDE SPARE PARTS AS SPECIFIED IN
SECTION 27 52 23
RFI #26 - Nurse Call Specs in TIL Section 27 52 23, Drawings and SOW: Please CONFIRM that dual cordless pushbutton plates for the bathrooms must be flush mount tamper proof anti-ligature stainless steel nurse call devices to meet the VA behavioral/mental health inpatient care standard?
o Response: CONFIRMED
RFI #27 - Nurse Call Specs in TIL Section 27 52 23, Drawings and SOW: Please DEFINE what is considered NURSE CALL? The reason for the question is the term “nurse alert” and “nurse help” are used in the drawings while the term "nurse call staff assist" is used in the RFQ PSU Specs Section 27-52-23 which is the nurse call life safety section. Furthermore, the RFQ cut sheets show Cornell brand "nurse call staff assist" devices.
o Response: “Nurse call” or “nurse aleart” stations are the existing “pull cord stations” located in bedrooms and attached bathrooms.
o Response: “Nurse Help” stations are the existing “push buttons” located only in shared spaces. The RFQ cut sheets for Cornell brand “nurse call staff assist is the same thing as “nurse help”
RFI #28 - Nurse Call Specs in TIL Section 27 52 23, Drawings and SOW: Because Cornell, Executone and WestCom are all listed in the RFQ bid specs (in the cut sheets, TIL specs and drawings), will the government ISSUE an amendment clarification that Jeron nurse call is the brand required?
o Response: Jeron nurse call is not required. Products called out are for reference only. A working ligature resistant notification station system is required.
RFI #29 - Construction Drawings, Cut Sheets and SOW: What wall MATERIAL is being used in the bathrooms and can a spec cut sheet be provided?
o Response: The existing bathroom walls are a solid surface material. NO CUT
SHEET AVAILABLE
RFI #30 - Nurse Call Specs in 1442, TIL Section 27 52 23, Drawings and SOW: Please CONFIRM that the nurse call must be B.A.A. compliant?
o Response: YES
RFI #31 - Nurse Call Specs in TIL Section 27 52 23, Drawings and SOW: How will the Government CONFIRM what brand of nurse call was bid by each GC and if it meets the TIL specs?
o Response: West-Com is the basis of design per General Note 1. Nurse Call Single Line Diagram. Other brands may be submitted as “or equivalent” per the solicitation process.
RFI #32 - Nurse Call Specs in TIL Section 27 52 23 and SOW: Please CLEARIFY what is meant by "to form an integrated nurse call system"? This infers that the new nurse call system being installed must be integrated into the old nurse call in other areas of building 520 that are NOT a part of this project. The purpose of clarifying statement is UL, Life Safety and FDA 510K Medical Device certifications don't allow for interfacing/intermingling different brands of nurse call life safety systems because it would create a standard of care life safety issue by attempting to integrate/intermingle different nurse call systems.
o Response: Each of the three (3) wards stand alone. Provide a complete working system that meets the requirements of the specifications.
RFI #33 - Nurse Call Specs in TIL Section 27 52 23: Please CONFIRM that the nurse call must include self-service repair training so that the PAD electronics shop can repair the nurse call without engaging a 3rd party?
o Response: NOT REQUIRED IN SPECIFICATIONS
RFI #34 - Nurse Call Specs in TIL Section 27 52 23: Please CONFIRM that the nurse call must provide plug-n-play device replacement capability meaning that ZERO programming is required to replace a nurse call end point device?
o Response: NOT REQUIRED IN SPECIFICATIONS
RFI #36 - Nurse Call Specs in TIL: Please confirm that the nurse call life safety system must be FDA 510K registered?
o Response: NOT REQUIRED IN SPECIFICATIONS
RFI #37 – Nure Call Specs in TIL Section 27 52 23, Drawings and SOW: Please CONFIRM that Jeron is the standard being deployed throughout the facility and is required? If so, will the Government please issue an amendment with the J&A.
o Response: SEE RFI #24
RFI #38 – Nurse Call Specs in TIL Section 27 52 23: Please CONFIRM the nurse call spares must be provided and compatible with the existing spare parts kit at the facility?
o Response: SEE RFI #25
RFI #39 – Nurse Call Specs in TIL Section 27 52 23, Drawings and SOW: Please CONFIRM that dual cordless pushbutton plates for the bathrooms must be flush mount tamper proof anti-ligature stainless steel nurse call devices to meet the VA behavioral/mental health inpatient care standard?
o Response: SEE RFI #26
RFI #40 – Nurse Call Specs in TIL Section 27 52 23, Drawings and SOW: Please DEFINE what is considered NURSE CALL? The reason for the question is the term “nurse alert” and “nurse help” are used in the drawings while the term "nurse call staff assist" is used in the RFQ PSU Specs Section 27-52-23 which is the nurse call life safety section. Furthermore, the RFQ cut sheets show Cornell brand "nurse call staff assist" devices.
o Response: SEE RFI #27
RFI #41 – Nurse Call Specs in TIL Section 27 52 23, Drawings and SOW: Because Cornell, Executone and WestCom are all listed in the RFQ bid specs (in the cut sheets, TIL specs and drawings), will the government ISSUE an amendment clarification that Jeron nurse call is the brand required?
o Response: NO SEE RFI #28
RFI #42 – Construction Drawings, Cut Sheets and SOW: What wall MATERIAL is being used in the bathrooms and can a spec cut sheet be provided?
o Response: THE EXISTING RESTROOMS USE A SOLID SURFACE WALL
CLADDING. NO CUT SHEET AVAILABLE
RFI #43 – Nurse Call Specs in 1442, TIL Section 27 52 23, Drawings and SOW:
Please CONFIRM that the nurse call must be B.A.A. compliant?
o Response: SEE RFI #30
RFI #44 – Nurse Call Specs in TIL Section 27 52 23, Drawings and SOW: How will the Government CONFIRM what brand of nurse call was bid by each GC and if it meets the TIL specs?
o Response: SEE RFI #31
RFI #45 – Nurse Call Specs in TIL Section 27 52 23 and SOW: Please CLEARIFY what is meant by "to form an integrated nurse call system"? This infers that the new nurse call system being installed must be integrated into the old nurse call in other areas of building 520 that are NOT a part of this project. The purpose of clarifying statement is UL, Life Safety and FDA 510K Medical Device certifications don't allow for interfacing/intermingling different brands of nurse call life safety systems because it would create a standard of care life safety issue by attempting to integrate/intermingle different nurse call systems.
o Response: EACH WARD IS A STAND-ALONE SYSTEM, NO INTEGRATION
WITH OTHER AREAS OF THE BUILDING OR CAMPUS.
RFI #46 – Nurse Call Specs in TIL Section 27 52 23: Please CONFIRM that the nurse call must include self-service repair training so that the PAD electronics shop can repair the nurse call without engaging a 3rd party?
o Response: SEE RFI #33
RFI #47 – Nurse Call Specs in TIL Section 27 52 23: Please CONFIRM that the nurse call must provide plug-n-play device replacement capability meaning that ZERO programming is required to replace a nurse call end point device?
o Response: SEE RFI #34
RFI #48 – Nurse Call Specs in TIL: Please confirm that the nurse call life safety system must be FDA 510K registered?
o Response: SEE RFI #36
RFI #49 – There appears to be a typo in the first paragraph of the A.3 PRICE/COST Schedule on Page 7 of the Solicitation. Proposal Item #1 describes a different project than Project 640-23-104, Correct Mental Health Deficiencies in Building 520. Will a revised A.3 PRICE COST Schedule be issued?
o Response: Revised A.3 Price Cost Schedule is attached to this amendment
RFI #50 – Page 25 of 55, section 4.39 Qualifications, A.: “The contractor shall be bonded and licensed in the state of California.” For other VA projects where the performance of work is within a federal facility (VA hospital) the contractor is not required to be licensed in the state of performance. Will contractor license from another state another state satisfy this qualification?
o Response: VA will accept contractors that are licensed in other States, (inside the U.S.)
| A.1 PRICE/COST SCHEDULE |
| PROPOSAL SCHEDULE |
| 1.1. | Flooring Replacement: A-111 OFFICE, A-115 CONFERENCE ROOM, A-117 ENCLOSED DAYROOM, A-120 OFFICE, A-121 BEDROOM, A-122 BEDROOM, A- 123 BEDROOM, A-125 BEDROOM, A-127 BEDROOM, A-132 BEDROOM, A-133 BEDROOM, A-134 BEDROOM, A-135 BEDROOM, A-136 BEDROOM, A137 BEDROOM, A143 BEDROOM, A145 OBSERVATION, A-150 NURSES STATION, A- 152 CONFERENCE, A-181 OFFICE, A-182 OFFICE, A-183 OFFICE, A-184 OFFICE, A-185 OFFICE, A-186 OFFICE, A-187 OFFICE, A-189 OFFICE. |
| 1.2. | Shower Repair: BATHROOM A-143A, BATHROOM A-132A. |
| 1.3. | Sally Ports: B-C01, C-C01, D-C01 |
| 1.4. | Patient Bedrooms: B-121, B-122, B-123, B-125, B-126, B-127, B-132, B-133, B- |
| 1.5. | Deductive Alternate, Ensuite Bathrooms: C-121A, C-122A, C-123A, C-125A, C- 126A, C-127A, C-132A, C-133A, C-134A, C-135A, C-136A, C-137A, C-145A, D-121A, D-122A, D-123A, D-125A, D-126A, D-127A, D-132A, D-133A, D-134A, D- |
| REQUEST FOR INFORMATION (RFI) FORM |
File details come from the government source that posted it. Updated .