36C25922R0051_Solicitation.docx

DOCX document 258 KB Posted

Attached to
554-21-121 Replace Heat Pumps in CBS with Fan Coils
Solicitation number
36C25922R0051
Issued by

About this file

This document is a solicitation notice requesting proposals to replace heat pumps in a clinic building at the Rocky Mountain Regional Veterans Affairs Medical Center.

The solicitation seeks proposals to replace existing heat pumps serving electrical and elevator machine rooms with new fan coil units. The project involves demolishing old equipment, installing new chilled water piping and fan coils, connecting to existing systems, and updating controls integration. Proposals are due by May 6, 2022.

The project is set aside for service-disabled veteran-owned small businesses. Apparent awardees must be verified and listed in the Vendor Information Pages database. The work is to be completed within 120 days of notice to proceed at a cost between $250,000 to $500,000. The contact for proposals is Christina Beeler-Blackburn at the Department of Veterans Affairs Network Contracting Office.

View the file

Other files

File Type Posted
Replace Heat Pumps in CBS with Fan Coils Questions_updated.docx DOCX document
S06- 36C25922R0051 Amend 0002.docx DOCX document
Replace Heat Pumps in CBS with Fan Coils Questions.docx DOCX document
S04- Site Visit Attendance 220408.pdf PDF
S04- Site Visit Meeting Doc.docx DOCX document
S06- 36C25922R0051 Amend 0001.docx DOCX document
Specifications_updated.zip ZIP file
Specifications.zip ZIP file
Past Performance Questionnaire.docx DOCX document
Drawings.pdf PDF
623-18-102 100pct Specifications with Headers stamped.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25922R0051

X 04-06-2022

554-21-121 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 Christina.Beeler-Blackburn@va.gov

Christina Beeler-Blackburn 303-712-5744 The contractor shall furnish all labor, equipment, materials, and supervision to complete the Replace Heat Pumps in CBS with Fan Coils at Rocky Mountain Regional VAMC, located at 1700 N Wheeling, Aurora, CO, 80045.

Important Notice: Apparent successful offerors must apply for and receive verification from the Department of Veterans Affairs Center for Verification and Evaluation (CVE) in accordance with 38 CFR Part 74 and VAAR 819.70 by submission of documentation of Veteran status, ownership, and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the Department of Veteran Affairs CVE at the time of offer submission. Failure to be both VERIFIED by CVE and VISIBLE on VetBiz at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urged to contact the CVE and submit the required documents to obtain CVE verification of their SDVOSB status if they have not already done so.

In accordance with FAR 52.204-7, System for Award Management (SAM), Prospective contractors shall be registered in the SAM database prior to close of solicitation.

Project magnitude: between $250,000 and $500,000. The NAICS code is 236220 - Small Business size standard is $39.5 M.

All questions in relation to this solicitation must be submitted in writing via e-mail to Christina.Beeler-Blackburn@va.gov and received no later than April 14, 2022 at 1:00 P.M. Mountain Time (MT).

A site visit will be held on April 8, 2022 at 9:00 A.M. Mountain Time (MT). Meet in the North Concourse across from the Patriot Brew.

Instructions, Conditions, and Notices to Offerors. All submitted proposals must be received in email by the closing date and time. This solicitation closes May 6, 2022 at 10:30 A.M. MT.

Proposals shall be submitted via e-mail in accordance with Part I/Section B, to be considered for this project.

Proposals received in any other format will result in the offeror's proposal not receiving further consideration.

X X

52.211-10 X

10:30 AM

MDT

05-06-2022 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111

Department of Veterans Affairs Financial Service Center PO Box 149971 Austin TX 78714-9971

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 BID SCHEDULE5
A.4 STATEMENT OF WORK6
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS15
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)22
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)22
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)22
2.4 52.233-2 SERVICE OF PROTEST (SEP 2006)23
2.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)24
2.6 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)25
2.7 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)25
REPRESENTATIONS AND CERTIFICATIONS25
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) (JUL 2020) (DEVIATION)25
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)29
3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)31
3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)33
GENERAL CONDITIONS34
4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)34
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)36
4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (SEP 2021)36
4.4 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (NOV 2021)39
4.5 SUPPLEMENTAL INSURANCE REQUIREMENTS43
4.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)43
4.7 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)46
4.8 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY 2020)46
4.9 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION)46
4.10 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)48
4.11 VAAR 852.219-77 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (SEP 2021) (DEVIATION)49
4.12 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)51
4.13 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)51
4.14 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)51
4.15 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)54
4.16 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)55
4.17 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)56
4.18 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)56
4.19 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)56
4.20 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)58
4.21 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)59
4.22 WAGE DETERMINATION59
4.23 LIST OF ATTACHMENTS64

A.3 BID SCHEDULE

The contractor shall furnish all labor, equipment, materials, and supervision to remodel the Replace Heat Pumps in CBS with Fan Coil Units at the Rocky Mountain Regional VAMC, 1700 Wheeler Ave., Aurora, CO, 80045.

Contractor Name:

DUNS:

CLIN
Description
Qty
Unit of issue

Firm Fixed Price Lump Sum amount

0001 Base Pricing 1 Job $_____________

(SEE SOW FOR DETAILS)

Provide all work as described by attached Plans, specifications, and Wage Determinations for Veterans Administration project:

VA Project: 554-21-121 Replace Heat Pumps in CBS with Fan Coil Units at the RMR VAMC as described in the attached scope of work. Price includes all costs for construction. Cost shall include but not be limited to direct and indirect costs including profit, overhead, general and administration, insurance, labor, bonds, taxes, necessary for 100% completion of the project as indicated in the attached SOW. The construction performance period is 120 days from receipt of notice to proceed.

Grand Total $_________________

A.4 STATEMENT OF WORK

Replace Heat Pumps in CBS with Fan Coil Units Project Number: 554-21-121 Rocky Mountain Regional Veterans Affairs Medical Center (RMRVAMC)

SCOPE OF WORK

OBJECTIVE:

The Department of Veteran’s Affairs has a requirement to install fan coil units (FCUs) to replace existing heat pumps and exhaust fans serving electrical and elevator machine rooms in Building A, Clinic Building South (CBS), of the Rocky Mountain Regional Veteran’s Affairs Medical Center (RMRVAMC). The eleven new cooling-only FCUs will tie into existing chilled water, electrical power, and building automation systems.

STATEMENT OF WORK:

The contract shall include of all the labor, material, and equipment to complete the work described in the project drawings and specifications. The work shall include but is not limited to the following tasks:

· For nine (9) locations with an existing heat pump:

1. Demo existing heat pump.

2. Tie existing condenser water supply and return piping together.

3. Install new FCU in space left from removal of existing heat pump.

4. Connect to existing chilled water, ducting, electrical power, condensate drain, and control wiring to new FCU.

5. Update breaker and disconnect as required to meet code.

6. Update existing BAS with new programming and graphics.

7. Perform testing and balancing of new FCU.

· For Two (2) locations on the second floor with an existing exhaust fan:

1. Install new chilled water piping from riser per drawings.

2. Install new FCU in location indicated on drawings.

3. Install new condensate drain (with condensate pump where necessary) for FCU.

4. Install new electrical service to FCU.

5. Install new control wiring to FCU.

6. Demo existing exhaust fan.

7. Install new ductwork per drawings.

8. Update existing BAS with new programming and graphics.

9. Perform testing and balancing of new FCU.

· Existing heat pumps and exhausts fans shall be replaced with FCU’s per the equipment schedule and specifications.

· Except for the second-floor locations, chilled water supply and return lines have been run close to the heat pumps being replaced. On the second floor, the chilled water lateral must be installed in addition to the runouts.

· Locations on the fourth floor shall be considered ICRA class III. Other locations are ICRA Class II.

· Locations where construction will block access to occupied spaces and main restrooms shall be completed after normal working hours. This applies to at least 50% of the locations and the installation of the lateral on the second floor.

· Temporary cooling with heat rejected to the outside shall be required in the two (2) elevator machine rooms and two (2) large electrical rooms (A1-358, A1-355, A1-353, A1-124, and A1-355) on the first floor while the primary HVAC equipment is offline. The other electrical rooms shall require either ventilation from corridors/return plenum or temporary cooling with heat rejected to corridor/return plenum to maintain room temperature while the primary HVAC equipment is offline. Contractor shall ensure all affected locations maintain room temperatures of less than 85 deg F during the construction.

· New equipment shall be added to the existing Building A BAS utilizing existing controllers where possible. The Building A BAS uses Delta Controls hardware and Setpoint Controls software. Once added, new points shall be integrated with the main campus BAS (JCI/Metasys) utilizing the existing integration server. Metasys Graphics shall be updated for new equipment.

GENERAL

The Dept. of Veterans Affairs (VA) requires strict adherence to the Code of Federal Regulations 29, Part 1926. This includes the requirement that the contractor have a “Competent Person” on the job at all times (must have a 30-hour OSHA card), and that all contractor employees have received a minimum of ten (10) hours of OSHA construction safety training. Documentation of these requirements shall be submitted and approved prior to performing the work.

Contractor must submit a company Site Specific Safety Plan (SSSP) that must be approved by VA Safety prior to work beginning. This plan shall detail fire, construction, and health-related safety measures, in addition to listing Training Records for all employees for the previous year. A company standard or boilerplate safety plan will not be acceptable – plan should contain a detailed hazard analysis for each element of construction to be performed such as an Activity Hazard Analysis (AHA) or Job Hazard Analysis (JHA).

This entire project shall conform to 100% of all VA standards and specifications, OSHA, AIA Construction Guidelines, Joint Commission Environment of Care Standards, and applicable building codes.

The Contractor shall be responsible for the health and safety of their own employees. The VA will inform the Contractor of any hazards such as designated permit confined spaces, electrical hazards, etc. which may affect Contractor employees. The Contractor must take precautions appropriate for the safety of their employees as well as provide equipment necessary for these actions. Contractor employees will notify the VA Representative before entering a designated permit required confined space, so precautions can be taken in advance of the work.

The Contractor shall hold harmless and indemnify the Government against any and all liability, claims, and costs of whatsoever kind and nature for injury to or death of any person or persons and for loss or damage to any property occurring in connection with, in any way incident to, or arising out of the occupancy, use, service, operation or performance of work under the terms of the contract, resulting in whole or in part from the negligence acts or omissions of the Contractor, any subcontractor, or any employee, agent, or representative of the Contractor or subcontractor The Contractor is responsible for protection of existing finishes, and VA property, furnishings, fixtures, and equipment (FF&E), located in the areas where demolition, construction, preventative maintenance, and repair work is being performed, as well as along paths of travel to and from these areas. Both exterior and interior finishes and property must be maintained. The contractor is liable for any damage to VA property during the course of the contract. Any damage to existing finishes must be repaired by the Contractor to equal or greater quality than existing finishes. All tasks accomplished by the Contractor personnel will be performed to preclude damage or disfigurement of government-owned FF&E and architectural or building structures. Contractor will report any damage or disfigurement to these items when caused by the Contractor’s personnel and will perform repairs or replace government-owned equipment, fixtures, furnishings, grounds and architectural or building structures to their previously existing condition.

PROJECT MANAGEMENT:

Based on the above list of work items, the general contractor selected must complete, maintain, and submit the following documentation and managerial requirements:

1. Construction schedule including sequencing and durations.

· The schedule will be provided to the COR ten (10) working days prior to the start of work.

2. Site-Specific Safety Plan (SSSP) with an emphasis on, but not limited to demolition, installation, and safety. The SSSP must:

· Include a detailed description of how the work will be performed and be submitted with sketches, supporting documents, submittals etc.

· Include a Job-Safety-Analysis (JSA) for all tasks associated with Statement of Work (SOW)

· Be approved by VA-Safety prior to commencement of work.

3. Obtain VA identification PIV badges for all employees. Contractor to consider lead-time for badge procurement.

4. Manage job-site access and security.

5. Implement and maintain required ICRA and ILSM measures.

APPLICABLE DOCUMENTS:

Contractor shall be required to field verify current conditions and accuracy of most current documentation, construction drawings and specifications.

CODE & REGULATION COMPLIANCE:

The Contractor shall comply with the public laws and statutes including all changes and amendments of federal, state and local environmental statutes and regulations in effect of date of issuance of this delivery order, including, the applicable portions of the documents cited in the basic contract and below.

1. National Fire Protection Association (NFPA):

2. NFPA 99-2015 Healthcare Facilities Code

3. NFPA 101 – Life Safety Code

4. International Code Council (ICC): IBC: International Building, 2015

5. Building Officials and Code Administrators International (BOCA), 1999

6. International Conference of Building Officials (ICBO): UBC 1997: Uniform Building Code

7. 29 CFR 1910 Occupational Safety and Health Standards

8. 29 CFR 1926 Safety and Health Regulations for Construction

9. Federal Occupational Safety and Health Act (OSHA)

10. Underwriters Laboratories

11. 2018 International Plumbing Code

12. SBCCI Standard Plumbing Code

SUBMITTALS:

Contractor shall submit the following prior to beginning scope of work:

1. Project schedule with sequencing, durations, phasing, and cost loading within 10 working days of Notice to Proceed (NTP), and monthly with invoices.

2. Site Specific Safety Plan (SSSP)

· SSSP to be submitted to VA Safety staff for review within 10 working days after issuance of NTP.

· SSSP to be approved by VA Safety staff prior to start of construction activities. Allow 10 working days for approval.

3. Construction Demolition Removal / Handover Plan.

4. Inspection reports, manufacturer approval certificates, and warranties.

5. Penetration, live work, or hot work permits as necessary.

6. Manufacturer and construction warranties as noted in specifications.

7. Project Schedule including sequencing and durations.

8. SOV – Schedule of Value. The schedule will be provided to COR 10 working days prior to start of the work.

9. Site superintendent OSHA-30, and tradesmen/laborer OSHA-10 certificates. OSHA-30 certified technician shall be onsite anytime work is being performed.

10. Material Submittals – Submit for COR approval

11. Physical and electronic Redline (As-Built) drawings of the completed work.

Contractor shall submit weekly reports showing hours, location, and description of work. Report shall include full name of Contractor’s employees on site and digital photographs before and after work is completed. Reports shall be provided in an agreed upon electronic format such as, but not limited to, pdf or Microsoft Word.

RESOURCES:

The Government will not furnish any resources for the fulfillment of the services required under this contract. The contractor must provide all tools, equipment, materials, transportation, professional expertise, personnel, and supervision for testing, maintenance, and certification services required under this contract. Contractor shall provide parts list with cost.

The Contractor shall secure all materials. The Government assumes no liability for loss of or damage to Contractor-owned property held upon Government premises.

TECHNICIAN/INSPECTOR QUALIFICATIONS:

The Government reserves the right to accept or reject Contractor’s staff for cause. Documented prior the work, Contractor shall provide technicians throughout the contract qualified to perform work on the Electrical and HVAC systems. The Contractor shall notify the Government within 3 business days if it intends to replace a technician. At the time of notification, the Contractor shall submit all required certifications for all personnel working on the contract. In the event new, or replacement, personnel become involved in the contract, the Contractor must submit all required certifications. Additions or changes in personnel require written approval of the Government. The Contractor shall have a back-up technician available in the event the primary technician is unable to perform his/her duties.

The Contractor will ensure their personnel and subcontractor personnel meet the privacy standards as set forth by HIPPA (Health Insurance Portability and Accountability Act of 1996) with respect to personal and confidential information that they may come upon, while contract work is being performed.

PERSONNEL ASSIGNMENTS:

The Contractor shall assign the appropriate quantity and type of personnel to successfully complete all functions specified in this SOW. The Contractor shall maintain throughout the life of this contract, a current list of technicians and their credentials available for inspection by the Government at any time.

Supervision: The Contractor shall specify a Project Manager who will have responsibility for performance of contract services. The Project Manager shall be competent to supervise all aspects of contract and shall be available on-site during performance of contract work. The Contracting Officer shall be notified in writing of the names of the Project Manager and of changes in personnel appointed to fulfill this function or in the absence of the Contractor, act for the Contractor as the Contractor’s Representative.

ACCEPTANCE STANDARDS:

The VA reserves the right to dispute completion of contract scope if contract work is found not in accordance with manufacturer recommendations, is not satisfactorily executed, or if the system is not properly tested and inspected to achieve certification. All work completed by the Contractor must be reviewed and approved by the VA.

SAFETY AND FIRE PREVENTION

a. In the performance of this contract, the contractor shall take such safety precautions as necessary to protect the lives and health of occupants on the site.

b. The Contractor shall immediately correct any fire and safety deficiencies caused by his/her personnel. If the Contractor fails or refused to correct deficiencies promptly, the Contracting Officer may issue an order stopping all or any part of the work and hold the contractor in default of the contract.

c. The Contractor shall comply with applicable Federal, State and local safety and fire regulations and codes which are in effect at the beginning of the contract. The contractor shall keep abreast of and comply with changes in these requirements and codes applicable to the contract. The requirements include but are not limited to, those found in Federal and State Occupational Safety and Health Administration (OSHA) statutes and regulations, such as applicable provisions of Title 29, Code of Federal Regulations (CFR) Parts 1910 and 1926. Contractor is solely responsible for determining the legal requirements that apply to activities, and shall ensure safe and healthful working conditions for its employees

d. The Contractor’s personnel shall follow applicable facility policies concerning fire/disaster programs.

e. All materials and equipment will be removed from the facility or stored properly at the end of the workday and secured during the workday. Under no circumstances will the Contractor allow for any equipment to be left unattended for any length of time.

f. The Contractor shall comply with all applicable Federal, State and local legal requirements regarding workers health and safety.

g. Contractor shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government Property.

h. The Contractor shall perform the work in a manner consistent with the area security and fire safety regulations especially with regard to exits and exit way access. Utility shutdowns shall not compromise security, communication or fire safety for occupants.

i. No flammable liquids shall be stored or used in the medical center.

j. The necessary number and appropriate types of portable fire extinguishers are required per National Fire Protection Agency (NFPA) 10 and NFPA 241. Contractor shall keep certification on site at all times of extinguisher inspections.

k. The Contractor shall receive from the COR a permit for all live work, cutting, welding, soldering, and permit required confined space entry, 24 hours in advance. All permits shall be prominently displayed during all construction. Allow 10 working days for approval.

l. All necessary precautions shall be taken by the contractor to prevent accidental operation of any existing smoke detectors or sprinkler heads.

m. The Contractor shall assume responsibility of environmental protection of all material storage.

n. Precaution shall be exercised at all times for the protection of persons (including employees) and property. These shall include, but not be limited to, the installation of adequate safety guards and protective devices for all equipment and machinery, whether used in the performance of work or permanently installed as part of the work. Contractor shall comply with all applicable laws relating to safety precautions, including the safety regulations of the Division of Industrial Safety, Department of Industrial Regulations of the state.

“VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors

1. Contractor employees who work in or travel to VHA locations must comply with the following:

1. Documentation requirements:

0. If fully vaccinated, shall show proof of vaccination

0. NOTE: Acceptable proof of vaccination includes a signed record of immunization from a health care provider or pharmacy, a copy of the COVID-19 Vaccination Record Card (CDC Form MLS-319813_r, published on September 3, 2020), or a copy of medical records documenting the vaccination

0. If unvaccinated and granted a medical or religious exception, shall show negative COVID-19 test results dated within three calendar days prior to desired entry date. Test must be approved by the Food and Drug Administration (FDA) for emergency use or full approval. This includes tests available by a doctor’s order or an FDA approved over-the-counter test.

0. Documentation cited in this section shall be digitally or physically maintained on each contractor employee while in a VA facility and is subject to inspection prior to entry to VA facilities and after entry for spot inspections by Contracting Officer Representatives (CORs) or other hospital personnel.

0. Documentation will not be collected by the VA; contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.

1. Contractor employees are subject to daily screening for COVID-19 and may be denied entry to VA facilities if they fail to pass screening protocols. As part of the screening process contractors may be asked screening questions found on the following website: COVID-19 Screening Tool. Regularly check the website for updates.

1. Contractor employees who work away from VA locations, but who will have direct patient contact with VA patients shall self-screen utilizing the COVID-19 Screening Tool, in advance each day that they will have direct patient contact and in accordance with their person or persons who coordinate COVID-19 workplace safety efforts at covered contractor workplaces. Contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.

1. Contractor must immediately notify their COR or Contracting Officer if contract performance is jeopardized due to contractor employees being denied entry into VA Facilities.”

ENVIRONMENTAL PROTECTION

a. In order to provide for abatement and control of all environmentally hazardous materials arising from demolition and/or construction activities, the Contractor shall comply with all applicable environmentally hazardous material control and abatement and all applicable provisions of the Corps of Engineers’ Manual EM 385-1-1, “General Safety Requirements” as well as the specific requirements stated elsewhere in the Contract Documents.

b. The Contractor is responsible for daily cleanup of all areas affected by its work. Areas in use or affected shall be returned to condition in which they were turned over or initially found. VA Housekeeping shall not be dispatched for cleaning associated with contractor work.

c. Contractor shall use freight elevators for transmission of materials and personnel. Contractor shall take every precaution in preserving the elevators, including the hoist way and lobby doors, interior finishes, and shall conduct all good practices in observing lifting and motor components tolerances. Any damage incurred to any elevator component due to negligence will be repaired at expense of the contractor, within the workday of incurred damage.

WORK STANDARDS AND ICRA/ILSM

Work site shall be free of debris and returned to original condition upon completion of demolition and construction, preventative maintenance, or repairs.

All work is to be performed in areas used daily by facility clients and staff. Contractor will take suitable measures to control all material and equipment to produce a minimum of interference in facility routine. All work shall be performed in a safe and prudent manner.

Contractor shall so perform all work as to offer the least possible obstruction and inconvenience to staff and the public and shall have under construction no greater amount of work than can be completed promptly and properly with due regard to the rights of staff and the public. Any person the COR may deem incompetent or disorderly shall be promptly removed from the facility and not be allowed to return for the duration of the agreement.

The Contractor shall comply with an Infection Control Risk Assessment (ICRA) which will be developed with the COR and the Infection Control Practitioner. Multiple ICRA’s may be necessary to address specific risks at various stages of the project and must be approved prior to proceeding on each phase.

HAZARDOUS MATERIAL REPORTING

a.The Contractor shall maintain hazardous material inventories and safety data sheets (SDS) for all hazardous materials (as defined in CFR 1910.120, 40 CFR’s 355, 370, & 372) to be stored and used on this Medical Center. Hazardous materials must be inventoried when received and at the project’s completion. The amounts used shall be maintained for the project duration, and for the calendar year (ending 31 December).
b.Hazardous Materials Inventories, Safety Data Sheets and material quantities used shall be submitted to the Contracting Officer for approval.
c.In the event of a spill, Contractor shall immediately notify the Contracting Officer’s Representative as well as the Contracting Officer. The Contractor shall be solely responsible for the expense of any cleanup of such spill, and the cleanup shall be in accordance with the applicable provisions of 40 CFR Part 761.
d.Asbestos Containing Material (ACM) is not present in the workspace. If contractor locates suspected ACM in addition to material noted in report, they shall contact the COR immediately for further direction. If any ACM is disturbed or becomes friable due to contractor actions, the construction site shall be shut down until and contractor shall provide appropriate containment at their own expense. In addition, contractor shall be responsible for all abatement and disposal of affected material at their own expense, only after which the job site shall be reopened for continued work. In the event of an ACM disturbance event, the COR shall be immediately notified and shall provide specifications on asbestos abatement.

HOURS OF WORK:

The hours of work shall take place during the normal business hours of 7:30 AM and 4:00 PM, Monday through Friday, Federal Holidays excluded. Request for weekend, after-hour, and Federal holiday work is permitted with a request in writing submitted beforehand. Allow 10 working days for approval. Off hours are not to billed as overtime. Federal Holidays and any other day declared a federal holiday by the President of the United States are defined below.

New Year’s DayMartin Luther King Jr’s DayPresidents Day
Memorial DayIndependence DayLabor Day
Columbus DayVeterans DayThanksgiving Day
Christmas DayJuneteenth Day

If a holiday falls on Sunday, the following Monday will be observed as the National Holiday. When a holiday falls on a Saturday, the preceding Friday is observed as a National Holiday by the U.S. Government.

If work requires after hours work due to ICRA constraints or inclement weather, then Contractor shall inform FMS fourteen (14) days in advance.

Postponement/Delays: In the event climate or weather conditions become unsuitable for work or may induce an environmental hazard, then the entire work shall be rescheduled to a date and time satisfactory to the Contractor and the COR. Postponement due to inclement weather will not cause assessment of the penalty provision outlined above, nor should there be an additional cost to the Government.

All work shall be scheduled and performed within the date and time approved by the COR, in conjunction with the department occupying the space served by this equipment.

BADGES AND PARKING

If a given contractor’s personnel will be working on-site for less than 5 working days, access to the facility can be attained by contacting the VA police and obtaining temporary access badges. If a contractor will be working on site more than 5 working days, identification badges must be procured prior to beginning project work. All Contractor personnel are required comply with VAAR 852.273-74 (Available online at VA Technical Information Library) which covers the following requirements: background checks, and the wearing of identification (I. D.) badges issued by the VA. Contractor must acquire PIV badge for all staff onsite prior to work beginning. While on VA Facilities grounds, temporary or official I.D. badges shall be worn continuously. Failure of the background check may result in specific personnel being disallowed to work on VA premises and the Contractor will need to provide replacement personnel.

It is the responsibility of the Contractor’s personnel to park in the appropriate designated parking areas. The designated parking area will be specified by COR upon award of contract. While performing under this contract, all vehicles used by the contractor shall be locked and the keys removed when not in use. This is intended to protect the contractor’s property and the safety of the patients at the medical center.

PERIOD OF PERFORMANCE

Government intends to issue NTP immediately after kickoff meeting with Contractor. The period of performance for this contract is one hundred twenty (120) days. The period of performance includes sixty (60) days anticipated to complete initial administrative tasks and receive materials.

** End of Statement of Work**

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

PART I/SECTION A – REQUEST FOR PROPOSAL

I.1A JOINT VENTURES

If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4, http://www.vetbiz.gov/library/jtventure.pdf , an offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETBIZ prior to award.

I.2A SELECTION PROCEDURES

This acquisition will be a competitive acquisition utilizing FAR Part 15 source selection employing tradeoff source selection procedures. By submission of its offer, the offeror accedes to all solicitation requirements, including terms and conditions, representations, and certifications. All such offers shall be treated equally except for their prices and performance records. Failure to meet a requirement may result in an offer being determined non-compliant. It is the intent of the Government to award without discussions; however, the Government will reserve the right to have discussions if such are needed.

I.3A PRE-PROPOSAL SITE VISIT

See SF 1442, Block 10 and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation. Please leave extra time to complete COVID-19 screening process when entering the building. Masks are required to be worn by all employees and contractors while on VA property.

I.4A SELECTION CRITERIA

This acquisition will utilize the tradeoff process in accordance with FAR 15.101-1. This process permits tradeoffs between non-cost factors and cost/price and allows the Government to accept other than the lowest priced proposal or other than the highest rated proposal to achieve a best value contract award based on established evaluation criteria. Inherent in this process is the necessity to make tradeoffs considering the non-cost strengths and weaknesses, risks, and the cost (or price) offered in each proposal.

The source selection process will be conducted utilizing FAR part 15.101-1 Trade-off Process Source Selection Procedures with Special Standards of Responsibility. Offers will be evaluated using the following evaluation factors:

Factor 1 – Past Performance Factor 2 – Price In addition to the general standards of responsibility found at FAR 9.104-1, in accordance with FAR 9.104-2, the special standards of responsibility described below apply to this procurement. Offerors who fail to meet any special standard of responsibility will not be eligible to receive contract award.

Past performance will be evaluated on a basis of significantly more important than, cost or price.

Past Performance Evaluation For Factor 1, based on the evaluation of all recent and relevant past performance for an offeror, an overall performance confidence rating shall be assigned. The performance confidence ratings are defined below:

ASSESSMENT
DESCRIPTION
Substantial Confidence
Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Limited Confidence
Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence
Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
Unknown Confidence (Neutral)
No recent/relevant performance record is available, or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

Note: In the case of an offeror without a record of past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance. Therefore, the offeror shall receive an unknown confidence (neutral) performance confidence rating.

(a) Aspects of Past Performance Evaluation. The past performance evaluation is an assessment based on the offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements. There are two aspects of the past performance evaluation.

(1) The first is to evaluate whether the offeror’s present/past performance is relevant or not relevant to the effort to be acquired. The criteria to establish what is relevant is unique to each source selection.
(2) The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts. The past performance evaluation performed in support of a current source selection does not establish, create, or change the existing record and history of the offeror’s past performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the offeror performed those past contracts. In addition, the Government reserves the right to obtain information for use in the evaluation of past performance from all sources including sources outside of the Government. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/DUNS numbers of Contractors who are part of a partnership or joint venture identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.
(b) Source Selection Evaluation Board (SSEB) members will review past performance information to determine the quality and usefulness as it applies to the performance confidence assessment.

Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system.

Factor 1-Past Performance

(a) Solicitation Submittal Requirements:

Offerors shall provide a maximum of five (5) recent and relevant projects (as defined below) to demonstrate their ability to perform the proposed work identified within the Specifications, drawings and Statement of Work. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted. The Government will evaluate past performance based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THERE IS NOT A PAST PERFORMANCE EVALUATION IN PPIRS or FAPPIIS, then the offeror shall submit Past Performance Questionnaires (PPQ) for each project. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Christina Beeler-Blackburn, Christina.Beeler-Blackburn@va.gov.

Recency – a recent project is defined as being completed within five years of the due date of this solicitation.

Relevant – includes performance of efforts in a project of installing or replacing fan coils that include general construction in an active medical facility that are similar or greater in scope, magnitude, and complexity than the effort described in this solicitation.

Offerors are cautioned to submit enough information in the format specified in the solicitation. Offerors may be asked to clarify certain aspects of their proposal (for example, the relevance of past performance information) or respond to adverse past performance information to which the offeror has not previously had an opportunity to respond. Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system. Communication conducted to resolve minor or clerical errors will not constitute discussions and the contracting officer reserves the right to award a contract without the opportunity for proposal revision.

(b) – Basis of Evaluation:

The contracting officer shall review recent and relevant performance information on each offeror based on past efforts provided by the offeror and may obtain data independently from other government and commercial sources. Past performance regarding predecessor companies, key personnel who have relevant experience, or sub-contractors that will perform major or critical aspects of the requirement will not be considered as highly as past performance information for the principal offeror. Offerors with no past performance history or the offeror’s performance record is so limited that no confidence assessment rating can be reasonably assigned shall receive the rating "Unknown Confidence," meaning the rating is treated neither favorably nor unfavorably.

Initially offers shall be ranked according to price, including any option prices if applicable. The lowest price offer’s past performance shall be evaluated to determine its performance confidence rating.

If the lowest priced evaluated offer is judged to have a Substantial Confidence performance assessment, that offer represents the best value for the government and the evaluation process stops at this point. Award shall be made to that offeror without further consideration of any other offers.

If the lowest price offer does not receive a Substantial Confidence performance confidence rating, the past performance evaluation continues until an offeror’s past performance is judged to have a Substantial Confidence performance rating. The Government reserves the right to award a contract to other than the lowest priced offeror if the lowest priced offeror is judged to have a performance confidence assessment of "Satisfactory Confidence" or lower. In that event, the Source Selection Authority shall make an integrated assessment best value award decision.

Factor 2 – Price:

(a) Solicitation Submittal Requirements:

· Standard Form 1442, Solicitation Offer and Award

· All pages of the SF1442 Continuation Sheet

(b) Basis of Evaluation: The Government will evaluate price based on the total price. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:

· Comparison of proposed prices received in response to the RFP

· Comparison of proposed prices with the IGCE.

· Comparison of proposed prices with available historical information.

Special Standard of Responsibility Solicitation Submittal Requirements:

The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)

1. OSHA or EPA Violation(s):

Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the…