This document contains a pre-proposal meeting agenda and federal contract opportunity notice for replacing heat pumps with fan coils at a Department of Veterans Affairs medical center. The contractor will remove existing heat pumps and install new fan coils at the Rocky Mountain Regional VA Medical Center located in Colorado. Questions are due by April 14th and proposals are due May 6th. The construction value is estimated between $250,000 to $500,000. The contract requires bid guarantees, payment and performance bonds, and compliance with Davis-Bacon prevailing wages. The opportunity is a 100% set-aside for service-disabled veteran-owned small businesses.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Replace Heat Pumps in CBS with Fan Coils Questions_updated.docx | DOCX document | |
| S06- 36C25922R0051 Amend 0002.docx | DOCX document | |
| Replace Heat Pumps in CBS with Fan Coils Questions.docx | DOCX document | |
| S04- Site Visit Attendance 220408.pdf | ||
| S06- 36C25922R0051 Amend 0001.docx | DOCX document | |
| Specifications_updated.zip | ZIP file | |
| Specifications.zip | ZIP file | |
| 36C25922R0051_Solicitation.docx | DOCX document | |
| Past Performance Questionnaire.docx | DOCX document | |
| Drawings.pdf | ||
| 623-18-102 100pct Specifications with Headers stamped.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Proposal Site Visit Meeting 36C25922R0051 Replace Heat Pumps in CBS with Fan Coils at Rocky Mountain Regional VAMC
The contractor is to provide all labor, tools, materials, equipment, and supervision required to complete the construction of the Replace Heat Pumps in CBS with Fan Coils at the RMR VA Medical Center. Work to include removal of Heat Pumps and installing Fan Coils.
Location: RMR VA Medical Center
AGENDA:
· Introduction of Christina Beeler-Blackburn CS, Daniel Davey COR
· The pre-proposal meeting/site walk is not mandatory
· QUESTIONS During site visit MUST BE WRITTEN DOWN
· Address where to send RFQ:
· Electronic submissions to Christina.Beeler-Blackburn@va.gov
· Pertinent Dates:
· Questions due April 14, 2022 no later than 1:00 PM MT prior to closing of RFQ, any questions submitted after this time will not be reviewed or answered! Submit to Christina.Beeler-Blackburn@va.gov
· We’ll get the answers back to you timely
· Proposals due on 5/6/22 at 10:30 AM MT via email
· Prospective offerors are prohibited from attempting to gain information by inquiring with VA employees about project other than through written questions submitted to Contracting Officer.
· Prospective offerors are prohibited from visiting site other than through formal invitation by Contracting Officer.
· Attendees of walk-through are to stay as a group while walking to various locations and are to leave the future project site once the walk-through is concluded.
· All VA campuses are Tobacco Free, including but not limited to, smokeless tobacco and vaping.
· All Federal and local COVID requirements shall be followed for the duration of this project.
· Confirmation of construction range is between $250,000 and $500,000.
· Bid Guarantee & Payment/Performance Bonds: Are required at 20% of bid price or $3,000,000.00 whichever is less.
· Contractor shall begin performance within 10 days after Notice To Proceed (NTP) and complete within 120 days.
· Post Award Compliance:
· Compliance with Davis Bacon Wages and Application wage determination shall be expected of the contractor. The contractor can submit their weekly certified payrolls with their monthly invoice.