This document contains questions and answers regarding a solicitation for renovations to a canteen food court and office suite at a Department of Veterans Affairs medical center. The solicitation seeks to enlarge the deli, deli storage, tray wash area, and kitchen grill storage to centralize the dining area. It will also create a 24-hour dining space and relocate offices. The work includes mechanical, electrical, and finish updates. The total set-aside is for Service-Disabled Veteran Owned Small Businesses. The estimated value is between $1-2 million. Past performance information may include data from subcontractors. Interim CPARS evaluations are acceptable in lieu of past performance questionnaires. Projects more than 25% complete can be used to meet evaluation factors. No more than two past performance examples need be included in submissions.

View the file

Other files

File Type Posted
36C25921R0004 0010.docx DOCX document
RFI 5 Response_AD101.pdf PDF
RFI 5.pdf PDF
36C25921R0004 0009.docx DOCX document
36C25921R0004 0008.docx DOCX document
RFI 4.pdf PDF
36C25921R0004 0007.docx DOCX document
RFI 3.pdf PDF
VVOC17 PL201 plumb changes.pdf PDF
ASBESTOS FLOOR TILE AND MASTIC ABATEMENT.pdf PDF
UPDATED bid docs sheets.pdf PDF
36C25921R0004 0006.docx DOCX document
RFI 2 Canteen Food Court Working 12.14.2020.pdf PDF
36C25921R0004 0005.docx DOCX document
36C25921R0004 0004.docx DOCX document
Pre-Bid Sign-In Sheet Canteen Food Court.pdf PDF
36C25921R0004 0003.docx DOCX document
36C25921R0004R2 Page 1.pdf PDF
16.1035.02_2020.04.27_bid docs_ total.pdf PDF
36C25921R0004 Pg1 Revised.pdf PDF
36C25921R0004 0002.docx DOCX document
36C25921R0004 0001.docx DOCX document
SELF-PERFORMED CALCULATIONS 9-5-2019.docx DOCX document
635-16-104 Approved Construction Drawings.pdf PDF
OKC Canteen Specs Vol 1.pdf PDF
OKC Canteen Specs Vol 2.pdf PDF
S02 Past Performance Questionnaire.docx DOCX document
36C25921R0004_2.docx DOCX document
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Both project site visits are listed for 9 AM on Monday. I assume we will do both consecutively.

Yes

2. While we understand the current solicitation does not allow past performance information from subcontractors, in order to expand competition and allow otherwise qualified SDVOSB offerors to submit, would the VA please consider allowing Offerors to utilize past performance from key subcontractors? This would ensure not only otherwise qualified offerors would be able to submit, but also allow the VA to review and evaluate the subcontractors who will have meaningful involvement in the project. The solicitation DOES NOT restrict submitting past performance by subcontractors. As per the solicitation Past performance regarding predecessor companies, key personnel who have relevant experience, or sub-contractors that will perform major or critical aspects of the requirement will not be considered as highly as past performance information for the principal offeror.

3. Will the VA please allow projects that are in progress (>25% complete) to qualify for Factor 1?

The requirement as stated in the solicitation allows for a better overall view of a contractor’s performance. The requirement stays as posted.

4. Factor 1 does not appear to quantify how many projects should be submitted. We apologize if we’ve overlooked it, but would the VA please consider capping the submitted projects to no more than two submitted projects? This requirement also allows the evaluation board a better overall view of a contractors past performance. The requirements stays as posted.

5. Please confirm what contents should go within the 30 page limit of the technical proposal. Our understanding is only the project write-ups, is that correct? We understand the past performance questionnaires are not part of the 30-page limit, but is the cover letter, or table of contents part of the 30 page limit? Are there any other submission requirements other than the project write-ups? The evaluation factors are past performance and price no other factors will be evaluated other than the Special Standard of Responsibility. It is up to the offeror to determine what they need to submit.

6. Would the VA allow interim CPARS evaluations in lieu of submitting the Past Performance

Questionnaires? CPARS are acceptable as past performance. CPARs will be accepted and evaluated to determine if they are relative in accordance with the criteria as stated in the solicitation.

File details come from the government source that posted it. Updated .