RFI 4.pdf

PDF 44 KB Posted

Attached to
Z2DA--Renovate Canteen Food Court and Office Suite
Solicitation number
36C25921R0004
Issued by

About this file

This document contains a request for information and details of a related federal contract opportunity for renovation work. The request for information pertains to pricing structure and qualifications for a project superintendent under specifications section 01 00 00 1.3. The related federal contract opportunity is a solicitation to renovate the Canteen food court and office suite at a Veterans Affairs medical center to create a more accessible space for disabled and bariatric patients and staff. It involves enlarging food service areas, relocating offices, upgrading building systems, and replacing finishes. The total magnitude is estimated between $1 million and $2 million. The opportunity is a service-disabled veteran-owned small business set aside issued by the Department of Veterans Affairs Veterans Health Administration VISN 19. The full solicitation will be posted after October 21, 2020.

View the file

Other files

File Type Posted
36C25921R0004 0010.docx DOCX document
RFI 5 Response_AD101.pdf PDF
RFI 5.pdf PDF
36C25921R0004 0009.docx DOCX document
36C25921R0004 0008.docx DOCX document
36C25921R0004 0007.docx DOCX document
RFI 3.pdf PDF
VVOC17 PL201 plumb changes.pdf PDF
ASBESTOS FLOOR TILE AND MASTIC ABATEMENT.pdf PDF
UPDATED bid docs sheets.pdf PDF
36C25921R0004 0006.docx DOCX document
RFI 2 Canteen Food Court Working 12.14.2020.pdf PDF
36C25921R0004 0005.docx DOCX document
36C25921R0004 0004.docx DOCX document
Pre-Bid Sign-In Sheet Canteen Food Court.pdf PDF
36C25921R0004 0003.docx DOCX document
36C25921R0004R2 Page 1.pdf PDF
16.1035.02_2020.04.27_bid docs_ total.pdf PDF
36C25921R0004 Pg1 Revised.pdf PDF
36C25921R0004 0002.docx DOCX document
RFIs 1.pdf PDF
36C25921R0004 0001.docx DOCX document
SELF-PERFORMED CALCULATIONS 9-5-2019.docx DOCX document
635-16-104 Approved Construction Drawings.pdf PDF
OKC Canteen Specs Vol 1.pdf PDF
OKC Canteen Specs Vol 2.pdf PDF
S02 Past Performance Questionnaire.docx DOCX document
36C25921R0004_2.docx DOCX document
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI #4

1. In the specs page 17 section 01 00 00 1.3 statement of bid – it shows three different item breakouts:

Item I General Construction, Item II Electrical Work and Item III Mechanical Work. Then in the same section it shows alternate No. 1 and alternate No. 2, but the SF1442 only states to provide one price.

How many prices should be submitted and what are they?

One price in block 17 for all the work there are no adds or deducts. You do not need to breakout pricing for Item I General Construction, Item II Electrical Work and Item III Mechanical Work.

2. Can the superintendent act as the SSHO or does the SSHO need to be a separate qualified individual?

Yes based on the assumption the Project Superintendent meets all qualifications for both listed in specifications