RFI 2 Canteen Food Court Working 12.14.2020.pdf

PDF 482 KB Posted

Attached to
Z2DA--Renovate Canteen Food Court and Office Suite
Solicitation number
36C25921R0004
Issued by

About this file

This document contains a request for information (RFI) and questions and answers related to a solicitation to renovate the food court and offices at a Veterans Affairs medical center. The renovation aims to centralize the dining area, enlarge food storage and preparation spaces, relocate offices, update mechanical and electrical systems, and install new finishes. The total estimated value is between $1-2 million. The opportunity is a total service-disabled veteran-owned small business set-aside to be issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19. The RFI addresses clarifying questions on phasing plans, specifications, equipment, and finishes.

View the file

Other files

File Type Posted
36C25921R0004 0010.docx DOCX document
RFI 5 Response_AD101.pdf PDF
RFI 5.pdf PDF
36C25921R0004 0009.docx DOCX document
36C25921R0004 0008.docx DOCX document
RFI 4.pdf PDF
36C25921R0004 0007.docx DOCX document
RFI 3.pdf PDF
VVOC17 PL201 plumb changes.pdf PDF
ASBESTOS FLOOR TILE AND MASTIC ABATEMENT.pdf PDF
UPDATED bid docs sheets.pdf PDF
36C25921R0004 0006.docx DOCX document
36C25921R0004 0005.docx DOCX document
36C25921R0004 0004.docx DOCX document
Pre-Bid Sign-In Sheet Canteen Food Court.pdf PDF
36C25921R0004 0003.docx DOCX document
36C25921R0004R2 Page 1.pdf PDF
16.1035.02_2020.04.27_bid docs_ total.pdf PDF
36C25921R0004 Pg1 Revised.pdf PDF
36C25921R0004 0002.docx DOCX document
RFIs 1.pdf PDF
36C25921R0004 0001.docx DOCX document
SELF-PERFORMED CALCULATIONS 9-5-2019.docx DOCX document
635-16-104 Approved Construction Drawings.pdf PDF
OKC Canteen Specs Vol 1.pdf PDF
OKC Canteen Specs Vol 2.pdf PDF
S02 Past Performance Questionnaire.docx DOCX document
36C25921R0004_2.docx DOCX document
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI #2

1. Should bidders include the costs associated with Submittal Exchange in Proposal There is no need to price this as part of the contract. This will be covered otherwise.

2. Please provide area that will be provided for contractor storage. If onsite storage is not available, should bidders include the costs associated with offsite storage?

On site storage will not be available.

3. Please provide location for contractor field office. If onsite location is unavailable, should bidders include the costs associated with offsite field office? No on-site office will be available except the job site itself.

4. Plan set issued online is missing all electrical, mechanical & fire protection drawings. Please provide.

Drawings have been provided by A/E

5. Does the project site contain existing asbestos flooring mastic? Demolition Plan Note 19 on Sheet AD101 calls for asbestos to be mitigated per specification section 02.82.13-19. This spec section is not in the current issue spec book.

See attached spec section

6. Infection Control Plan Note 3 on GI105 calls for temporary walls to be installed per detail 2/GI100. This plan sheet is not on the index. This is also the case with notes 1 & 2

All references to Temporary Control and Smoke Barrier should reference details 2, 3, and 4 on sheet GI103. All information required is contained in those details.

7. Section 11 40 21 does not list acceptable manufacturers for the new food service equipment.

Please provide acceptable manufacturers.

According to Equipment Floor Plan AQ101 – Equipment Schedule all equipment is either existing to be relocated or listed as Government Supplied / Contractor Installed. Coordination with the Food Services and their equipment supplier will be required during construction.

8. Drawings GI103-GI107 Infection Control General Note C states the project shall be completed in three (3) phases. However, the referenced sheets also include the following Phasing Schedule diagram [of 5+ phases]:

General Note Letter C: Should read as follows:

PHASING OF THE PROJECT IS CRITICAL TO THE SUCCESS OF THIS PROJECT.

THE INTENT IS TO COMPLETE ALL CONSTRUCTION WHILE THE CANTEEN

REMAINS FUNCTIONAL FOR THE DURATION OF THE CONSTRUCTION PERIOD.

THE PROJECT AS SHOWN IS INTENDED TO BE COMPLETED IN FIVE (5) PHASES.

FINAL PHASING OF THE PROJECT MUST BE COMPLETELY COORDINATED

BETWEEN THE CONTRACTOR AND THE COR ON SITE.

a. The phasing requirements are not clear. Please advise accordingly.

b. Looking at the above Phasing Schedule diagram, is Phase 4 to be performed during nights and weekends only? If yes, the areas shown on Drawing GI106 state, “This area of floor tile to be abated during allowed 7-day shut down as Phase 4.” This would be contradictory. Please advise accordingly.

As stated the abatement of the area of phase 4 is to be accomplished during a 7 day shut down of the area. And then the area of phase 4 to be reopened so the canteen may function. The remainder of the work (mostly flooring ceiling, and finish work) to be accomplished either during the 7 day shut down, or nights and weekends.

c. Spec 00 01 15 identifies Drawing GI100 Phasing Plan/Infection Control Plan;

however, this drawing was not provided and not listed on the drawing Sheet List. Please provide the referenced drawing. If GI100 is not available, please provide drawing that shows the overall phasing plan. All phases shown on one

(1) drawing sheet would aid in understanding the phasing requirements.

Infection Control and phasing are accomplished with sheets GI103-GI107 the referenced to GI100 is incorrect and should reference GI103-GI107 only.

Due to overlapping square footage for infection control and phasing placing al phases on a single plan is overlapped and confusing, this is the reason for the separate plans to show independent individual phases.

9. Drawings GI103-GI107 Infection Control General Note A states, “Refer to list of required infection control precautions outlined by class in Spec 01 01 10 and additional information.” This spec section was not provided and not listed on the Spec Table of Contents (TOC). Please provide referenced spec section.

Note should read as follows:

Refer to list of required infection control precautions outlined by class in Specification Section 01 35 26 and additional information.”

10. Drawings GI103-GI107 Infection Control General Note E states, “…Contractor shall provide drawing to COR and Patient Safety/Infection Control Representative once ICRA protocols and plan is approved.” Does the referenced drawing need to be stamped by a

PE?

The ICRA plan is to be submitted to the COR for review with the safety office prior to any work commencing. No PE stamp is required.

11. Drawings GI103-GI107 Phasing General Note D states, “Refer to Specification 01 00 00 for information on work duration for each phase and area of work.” We are not locating this information in the referenced spec. Please advise accordingly.

More information regarding the requirements for phasing of the project are in Specification section 01 00 00 General Requirements. Specifically see page 01 00 00-08 Phasing.

12. Drawing AD101 Demolition General Note J states to coordinate demolition work with vendor drawings. Please provide referenced vendor drawings.

According to Equipment Floor Plan AQ101 – Equipment Schedule all equipment is either existing to be relocated or listed as Government Supplied / Contractor Installed.

Coordination with the Food Services and their equipment supplier (vendor) will be required during construction.

13. Drawing AD101 Demolition Plan Note 10 identifies relocation of existing tray wash machine.

a. We are not locating this identifier on the Drawing AD101. Please advise accordingly.

Existing Dishwashing machine is located in Tray Wash GB104K1 located just north of GB104b.

b. Please provide product data, installation information, power requirements, etc., for the referenced equipment. If this information is not available, please provide manufacturer and model information.

Contractor to field verify all existing conditions for equipment in field.

14. Drawing AD101 Demolition Plan Note 11 states, “Existing bag in the box lead lines located in this area. New location of bag in the box soda lines requires complete removal of all existing lines and rerouting.”

a. We are not locating this identifier on the Drawing AD101. Please advise accordingly.

Existing Bag in Box soda supply is located in Storage Room GB104f11

b. Do the lead lines require hazardous material abatement/removal? Please advise accordingly. If lines require hazardous material abatement/removal, please provide applicable abatement spec/information.

Existing Lead (supply) lines are food grade polymer lines see attached photo of existing lines penetrating rated floor slab no abatement is required.

c. Who is providing the new soda lines?

Contractor is to supply new lines between supply and serving locations.

15. Drawing AD101 Demolition Plan Note 17 states, “Existing wall to remain, patch and repair surface for new construction.” We are not locating this identifier on Drawing AD101. Please advise accordingly.

Note 17 can be found in the Northeast corner of the canteen project. Located in Tray Wash GBB104k1 and Storage GB104K south of Stair 3. It is in Phase 5 as indicated on Sheet GI107 and is also indicated by Plan note #2 on sheet AS101.

16. Drawing AD101 Demolition Plan Note 19 references spec section 02 82 13 19 Asbestos Floor Tile and Mastic Abatement. This spec section was not provided and not listed on the Spec TOC. Please provide referenced spec section.

See attached specification section 02 82 13.19 for information requested.

17. Drawing AS101 Architectural General Note U refers to Drawing AS501 for accessories to be provided at the hand lavatories. We are not locating accessories at the hand lavatories on Drawing AS501. Please advise accordingly, to include applicable spec section(s).

Accessories to be supplied at the hand lavatories are to be Government supplied Contractor installed. These may include but are not limited to soap dispenser, paper toweled dispenser, and hand sanitizer. Final coordination with food services equipment supplier and the facility management is required during construction.

18. Drawings AS111, AS502, and AQ101 appear to be missing detail/sheet numbers at some of the sections. Please advise accordingly. A few examples are shown below:

See attached drawings updated 05.17.2020 for information requested.

19. Drawing AS002 Detail 1 identifies crash rails and refers to the finish schedule. We are not locating any crash rail requirements on the finish schedule. Please advise accordingly. If required, please also provide applicable spec section.

Crash rail detail is shown as a patch and repair only out in the main corridor outside of the existing canteen. See note number #3 on sheet AS101. Where door is infilled existing crash rail handrail in the existing hall must be repaired and made continuous where door is infilled.

20. Drawing AF101 Finish Schedule lists WP-1 Wall Protection. WP-1 is not identified on Drawing AF101’s floor plan. Where is this material to be installed? Please advise accordingly.

An updated finish plan AF101 Dated 11/30/2020

21. Drawing AF101 Finish Schedule list WP-2 Wall Protection. What is the height requirement for this material? Please advise accordingly.

See details 5 and 8/AS501 for this information.

22. Drawing AF101 Room Finish Schedule does not identify wall finish for Room GB104N. Please advise accordingly.

Room is to be supplied with WP-2.

23. Spec 10 26 00 Wall and Door Protection Paragraph 3.3 identifies door and door frame protection. We do not location this requirement on the drawings. Is this applicable to all doors and door frames inside the project area? Please advise accordingly.

24. Drawing AQ101 Equipment Schedule identifies several GFCI items. However, per Drawings AS501 and AS502, it appears the some of the finishes (i.e., countertops, cabinet fronts) are required to be update by the Contractor. Please confirm this is correct for the stations identified to receive new finishes.

Existing serving stations to be resurfaced, including laminate and counter top are to be resurfaced by the Contractor. The following is a list of items to be resurfaced by the contractor.

2 - Serving Station 3 – Serving Station 6 – Serving Station 7 – Serving Station

10 – Serving Station 30 – Serving Station

25. Drawing AQ101 Equipment Schedule:

a. Type Mark 8 shows to be GFCI; however, it also shows to be furnished by the

Contractor. Please clarify.

Item #8 will be Government supplied contractor installed.

b. Type Mark 32 shows to be CFCI; however, it also shows to be existing. Please clarify.

These are existing lockers to be relocated by the contractor.

26. Drawings AS501, AS502, and AF101 show different finishes on the walls and/or need clarity. Please advise accordingly. A few examples are shown below:

Sheet AF101 wall finishes are to control the project. Bid Accordingly. Clarification will be issued by Addendum.

27. Drawings AD101 and AD102 identify the Canteen Dining Room as GB104h and the Canteen (station area) as GB104. Drawing AF101 identifies the Canteen Dining Area as GB104 and the Canteen (station area) does not have a room number. Please advise accordingly. Please provide revised AF101 Room Finish Schedule for these rooms.

Canteen (Station Area) – identified as GB104 on Demo Plans shall be considered Canteen (Station Area) GB119 for finished project. Finishes are to be as follows. (And as shown on drawing 2/AF101 Finish Wall Treatment Plan.

GB119 Canteen (Station Area) Floor – PLT-2 Base – PLT-4

Walls – PLT-1

28. Who is storing the GFCI equipment?

The COR will store the materials.

29. Who is providing the television monitors?

Monitors to be provided by contractor. Coordination with onsite existing system required by contractor prior to bid.

30. Spec 10 14 00 identifies a signage requirement. Please furnish a Signage Schedule.

Signage is to meet the existing onsite standard. A signage plan will be issued by Addendum.

31. Spec 01 00 00 General Requirements Paragraph 1.3 identifies a Statement of Bid Item(s). Does the Govt have a form (Bid/Pricing Schedule) the Contractor needs to complete?

No pricing to be entered block 17 make sure you read the verbiage in 17 also.

32. The phasing plan makes reference of Phase 2A, however no area ‘2A’ is shown. Please define phase ‘2A’.

All references to Phase 2A are to be disregarded.

33. What is the style of Armstrong ceiling tile for ‘AP-1’?

AP-1 Canteen Seating Area Armstrong Optima Lay-in White or Equal

34. What is the style of Armstrong ceiling tile for ‘AP-2’?

AP-2 Back of House Scrubbable Ceiling is Armstrong Cerama Guard White or Equal.