This document contains an amendment to a solicitation for a Guest Wifi and Wayfinding project at the Salt Lake City Veterans Affairs Medical Center. The key details are as follows:
The amendment extends the deadline for offer submissions to July 28, 2020 at 3:30pm MDT. It also extends the deadline for questions to July 15, 2020 at 3:30pm. The amendment answers various questions from a vendor regarding technical requirements, including details on network infrastructure, fiber runs, wireless access point locations, wayfinding needs, and construction materials. It seeks a Guest Wifi and Wayfinding solution for the entire Salt Lake City VA Medical Center campus, including all buildings and outdoor areas such as parking lots. Full Wifi access is required in patient areas and the parking structure. BLE beacon wayfinding may be used in parking lots but is not needed along roadways.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25920Q0490 0002
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
660-20-3-984-0941
36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village CO 80111
36C259 Department of Veterans Affairs Network Contracting Office
NCO 19
6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 To all Offerors/Bidders
36C25920Q0490 07-13-2020
X x x
7/28/2020, 3:30pm MDT See CONTINUATION Page
660-3600160A1-984-825500-3133 010042198
X The purpose of this amendment is to extend the solicitation until 7/28/2020, 3:30pm MDT.
Extend the submission of the Question until 7/15/2020, 3:30pm.
Answer questions from a vendor.
All other terms and conditions remain the same.
Susan Dela Cruz
VA-VHA-2020-17D99F19
CONTINUATION PAGE
1. Will the “closet (leaf)” switches that connect the APs be connected to a “core (spine)” switch?
a. This will be at the up to the network designer
2. Will there be two “core” switches for redundancy?
a. This would be a best practice, but up to the network designer
3. Will the connections from the closet switches to the core be 10Gbps?
a. This would be the expectation yes
4. Is there fiber connecting these closet locations to the core?
a. Any fiber installed will be home run to either the Main Distribution Frame (MDF) or to the main Intermediate Distribution Frame (IDF) in building 1 Room GB36
5. Is that fiber SMF? Yes
6. Is that fiber MMF? No
7. If the fiber is MMF? What type of fiber is it? OM1 – OM4 generally Single mode only
8. Which buildings require fiber between them?
a. Every building will require fiber. Some SM fiber exists in building, but you should expect to run fiber to every location. This fiber will be 24 strand minimum
9. Is there power to light poles in parking areas where outdoor APs could be located? Are the lights on timers? No power will need to be pulled from the lighting system at any given location
10. Are closets delineated on plans that will have switches are required to uplink all the APs? Can mechanical rooms be utilized?
a. During the walkthrough closets will be designated, mechanical and electrical rooms could be used if needed. This should not however be the case.
11. Can the VA confirm their definition of Wayfinding? Our understanding, and how other VISNs have done it, is to wayfind to hospital departments as opposed to individual rooms.
a. Way finding should be to a given clinic location not a specific room unless a room is being used specifically for check-ins
12. Our understanding is that the main hospital building would have indoor navigation/wayfinding with pathways to find other buildings within the campus. Please confirm.
a. Yes, way finding must also work for other buildings on property that are not directly connect to the main hospital
13. What are the general construction materials used for?
a. Exterior Walls (i.e. CMU, Concrete, Brick, etc.)
b. Interior Walls (i.e. CMU, Wood/Drywall, etc.)
c. Stairwells/Elevator Shafts (i.e. CMU, Concrete, Brick, etc.)
i. Typical building construction
14. What is the anticipated usage density of each building?
a. This is hard to predict; any inpatient areas will have enough density to ensure that continuous and consistent connections for every patient. Waiting rooms and inpatient rooms will require the heaviest density. All non-patient areas will require a much lower density.
b. How many anticipated users per building?
i. This number will vary on a regular basis. We can use the number of rooms as a baseline for the purposes of through put density
15. Are there any areas that are inaccessible, unable to support AP placement, or otherwise not required to support Guest Wifi?
a. This could be addressed on a case by case basis. For the most part everywhere WIFI is needed access should be possible.
16. Mechanical Spaces, Elevator Shafts, Stairwells, Private (Non-Guest Access) Spaces, etc.
a. Will Guest Wifi need to be supported in bathroom areas? Not specifically.
b. There are some mechanical spaces that will require WIFI
17. Request documentation showing existing power/data connection points in outdoor parking spaces. For outdoor spaces, will exterior wall mounted APs be considered?
a. The information requested will take some time to put together. We can view the area during walk-through.
b. External wall mounted AP’s can be used as long as the required coverage is met
18. Can the general locations of the kiosks be identified? Yes. A general description is the two main entrances to building 1 (North end ground floor, South end 1st floor). One in the Tunnel between building 1&8 (final locations to be decided). One at the entrance of building 4 and one at the entrance of building 16.
19. Are there any buildings with inconsistent floor-to-floor heights? For the main building no. There are locations where the roof is much higher. Building 9 and building 6 are two such locations.
a. i.e. auditoriums, split-level buildings, conference areas, etc.
20. It is understood that the coverage in the parking areas will be BLE, without the need for full Wifi Coverage. However, there is a Patient RV Park in one of the parking lots. Will we be wanting full Guest Wifi Access at these locations, or just BLE wayfinding? Full WIFI needs to be available in the parking structure and in all outdoor waiting and break areas
21. Will you be wanting BLE wayfinding accessible from the roadways in addition to the parking lots? Will there be existing conduit for any building to building fiber runs?
a. No BLE required from roadways
b. Conduit exists from building to building the available space in the conduit could be a challange
22. Will there be a requirement for HEPA carts in any areas other than sterile areas? Yes
23. Will there be a requirement for conduit in any areas? This will be as needed on a case by case basis
24. Can the Q&A response date be moved to 7/15/2020 to allow time for questions to be developed after the site visit on the 14th? This will be up to the Contracting Officer to decide.
(End of Page)