This document includes a construction schedule and federal contract opportunity notice for a cleanroom compliance project at the West Los Angeles VA Medical Center. The construction schedule outlines a 18-month period of performance beginning in January 2020, with four phases of construction and commissioning work. Key dates include a January 2020 contract award, May 2021 completion of the final construction phase, and a June 2021 final project closeout. The related federal contract opportunity seeks proposals for upgrade and compliance work at the West Los Angeles VA Medical Center involving all labor, materials and engineering to complete a USP 800 Pharmacy Upgrade project. The total projected value is between $2 million to $5 million, with proposals due in April 2020. The work will be a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses.
36C25820B0011 0001 691-18-109WL B500 USP 800 Final Construction Schedule.pdf
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
B-500 IV CLEAN ROOM COMPLIANCE WITH USP800
CONSTRUCTION SCHEDULE – A/E FINAL SUBMISSION -
100% CD
WEST LOS ANGELES, CALIFORNIA
Prepared FOR:
U.S. Department of Veterans Affairs 11301 Wilshire Boulevard, West Los Angeles, CA - 90073
PREPARED BY:
SC Engineers, Inc.
17075 Via Del Campo | San Diego, CA 92127 P: 858.946.0333 | F: 858.946.0334 | www.scengineers.net
DATE PREPARED:
November 19, 2019 SC Project No. 18801.07
CONSTRUCTION SCHEDULE
Date Updated 11/19/2019 Project Name
Project Location
SC Project No.
VA Delivery Order No.
Period of Performance* 18 Months
PHASE DURATION
(CALENDAR DAYS)*
CONTRACT DATE*
Contract Award 1 Thursday, January 2, 2020
Contractor Mobilization & Admin. Submittals 14 Thursday, January 16, 2020
Construction Submittal Prep & Review 75 Tuesday, March 31, 2020
Equipment Order and Delivery 59 Friday, May 29, 2020
Phase 1 Construction 60 Tuesday, July 28, 2020
Phase‐1 Cx & Certification 14 Tuesday, August 11, 2020
Phase 2 Construction 90 Monday, November 9, 2020
Phase‐2 Cx & Certification 14 Monday, November 23, 2020
Phase 3 Construction 91 Monday, February 22, 2021
Phase‐3 Cx & Certification 14 Monday, March 8, 2021
Phase 4 Construction 60 Friday, May 7, 2021
Phase‐4 Cx & Certification 14 Friday, May 21, 2021
Final Project Closeout 31 Monday, June 21, 2021
HOLIDAYS 2020 2021
New Year's Day Wednesday, January 1 Friday, January 1
MLK Day Monday, January 20 Monday, January 18
Washington's Bday Monday, February 17 Monday, February 15
Memorial Day Monday, May 25 Monday, May 31
Independence Day Friday, July 3 Monday, July 5
Labor Day Monday, September 7 Monday, September 6
Columbus Day Monday, October 12 Monday, October 11
Veterans Day Wednesday, November 11 Thursday, November 11
Thanksgiving Day Thursday, November 26 Thursday, November 25
Christmas Day Friday, December 25 Friday, December 24
691‐18‐109WL B‐500IV Cleanroom Compliance with USP800
36C25818N0553
18801.07
*Calendar Days include Holidays and Weekends but if the last day is a Saturday, Sunday, or legal holiday, the period continues to run until the end of the next day that is not a Saturday, Sunday, or legal holiday.
West Los Angeles Medical Center (Bldg. 500 4th & Ground Fl.)
11301 Wilshire Blvd, West Lost Angeles, CA 90073
ID Task Name Duration Start Finish
1 Contract Award 1 day Thu 1/2/20 Thu 1/2/20
2 Contractor Mobilization & Admin. Submit14 days Fri 1/3/20 Thu 1/16/20
3 Construction Submittal Prep. & Review 75 days Fri 1/17/20 Tue 3/31/20
4 Equipment Order and Delivery 59 days Wed 4/1/20 Fri 5/29/20
5 Phase 1 Construction 60 days Sat 5/30/20 Tue 7/28/20
6 Phase‐1 Cx & Certification 14 days Wed 7/29/20 Tue 8/11/20
7 Phase 2 Construction 90 days Wed 8/12/20 Mon 11/9/20
8 Phase‐2 Cx & Certification 14 days Tue 11/10/20 Mon 11/23/20
9 Phase 3 Construction 91 days Tue 11/24/20 Mon 2/22/21
10 Phase‐3 Cx & Certification 14 days Tue 2/23/21 Mon 3/8/21
11 Phase 4 Construction 60 days Tue 3/9/21 Fri 5/7/21
12 Phase‐4 Cx & Certification 14 days Sat 5/8/21 Fri 5/21/21
13 Final Project Closeout 31 days Sat 5/22/21 Mon 6/21/21
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 2020 2021
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration‐only
Manual Summary Rollup
Manual Summary
Start‐only
Finish‐only
Deadline
Progress
Project: Construction Schedule Date: Tue 11/19/19