36C25819B0020-0005000.docx
DOCX document 27 KB Posted
- Solicitation number
- 36C25819B0020
About this file
36C25819B0020 0005 36C25819B0020 0005.docx
View the file
Other files
Show 40 more
Latest 50 of 59 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A0005
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION
OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADM
INISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and d ate specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 3
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO
MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 05-09-2019 605-20-206 Department of Veterans Affairs NCO22-Gilbert Network Contracting 777 E. Missouri, Suite 300 Phoenix AZ 85014 Department of Veterans Affairs NCO22-Gilbert Network Contracting 777 E. Missouri, Suite 300 Phoenix AZ 85014 To all Offerors/Bidders
36C25819B0020 05-08-2019
X X X
TBD
X one
The Purpose of A0004 is too:
1. Publish RFI's Revisions #26, 37, 39, 41, 42, 53, 57, and 78
2.Publish Stairway and Laydown Pictures.
Justin Hicks Branch Chief RFI # 26 was conflicting with 35, 45 and 77b:
#26- Under the courtyards there are large steel beams above one’s head and smaller beams at the floor, are all beams to be cleaned and repainted? A: Yes Correction- No, only the overhead beams are included #35- Are all beams overhead and at floor level within the space to be cleaned and painted? A: the only beams in the Scope are the overhead beams #45- Are the beams located on the floor in the interstitial areas included in the corrosion control scope? A: No #77B- Are the “beams” only the upper beams that support the courtyard? Or ALL steel? Please see attached photo, we have marked upper support beams in red, and lower (mechanical and conduit line supports in blue). A: Only the upper beams are in the scope of work
RFI # 37 and 41:
#37- Will all existing vegetation be removed prior to starting the planter irrigation and planting activities? A: Yes Correction- Vegetation will be removed from courtyard #3 and #4 prior to commencement of the project but not the Library Patio #41- The Library patio has full vegetation in place. Much of the vegetation is found on the list provided for new vegetation. Will this vegetation be acceptable to leave in place? A: All vegetation will be removed prior to project start. Correction- Vegetation will be removed from courtyard #3 and #4 prior to commencement of the project but not the Library Patio
RFI # 39: The planters have drains located in the bottom under the Styrofoam and rock. Does the VA expect these drains to be replaced? A: Yes Correction- The drain will remain in place and tie in the new 4” drain to existing drain
RFI # 42: The RFP calls for the replacement of the 2” storm drain collection lines with new 4” collection lines. After reviewing the as-built drawings the horizontal main collection line is all 3” and smaller until reaching the Service Bay where it appears to be 6”. Does the VA expect these lines to be replaced in its entirety to the Service Bay? Has the VA performed the engineering to determine if the 6” vertical drain is properly sized for the discharge of all the 4” drain lines? If so, please confirm. A: Replace 2” storm drains lines with 4” lines and proper connections to existing. Correction- Replace 2” & 3” storm drains lines with 4” lines and proper connections to existing
RFI #53: What wall thickness must the new 4-inch drain pipe have? A: Schedule 80 Correction- Should be no hub cast iron
RFI # 57: It is hard to tell how many concrete wall coring’s and steel beam coring’s will be necessary to facilitate the larger pipe. Can anything be provided to clarify that? If coring’s are necessary will any structural engineering or preconstruction inspections or permits be required?
A: Approximately 6 coring’s from drain lines to Service Bays Correction- Approximately 6 coring’s from drain lines to Service Bays. Radar detection will be required to mitigate steel damage in the shear wall
RFI # 78: Please verify if the landscape planter drains are part of this scope of work: A: Yes Correction- The drains are not part of the scope of work. Connect new drain lines to existing planter drains.
See attached document: S02 Patio Stairwell Layout.
See attached document: S02 Patio Laydown area.png.