This is a Past and Present Performance Questionnaire template used by the Department of Veterans Affairs, Network Contracting Office (NCO) 17 to evaluate contractor performance for solicitation 36C25725R0056. The document is source selection sensitive and is sent to points of contact who have direct knowledge of a contractor's past or present performance on federal contracts. Completed questionnaires must be submitted via email to nicholas.smith21@va.gov by the deadline specified in Standard Form (SF) 1442 Block 13A.

The questionnaire evaluates contractor performance across 18 rated criteria using a five-point scale: Exceptional (E), Satisfactory (S), Marginal (M), Unsatisfactory (U), and Neutral (N). The evaluation areas include management and supervision capabilities, regulatory compliance (OSHA, EPA, federal and local laws), quality control, deficiency correction timelines, contract discrepancy resolution, problem identification and initiative, schedule development, responsiveness to changes, record-keeping accuracy, workmanship standards, subcontractor payment timeliness, government communication, cost control and forecasting, billing accuracy, and change order pricing reasonableness. The template also includes questions regarding whether a cure or show cause notice was issued and whether the respondent would award another contract to the contractor. Narrative explanations are required for any Marginal or Unsatisfactory ratings.

View the file

Other files

File Type Posted
Clarifications 2.docx DOCX document
Amendment 0006 36C25726R0053.docx DOCX document
Amendment 0005 36C25726R0053.docx DOCX document
Clarifications 36C25726R0053.docx DOCX document
Component List Pertaining to RFIs.pdf PDF
Amendment 0004 36C25726R0053.docx DOCX document
RFIs with Responses for Solicitation 36C25726R0053.pdf PDF
Amendment 0003 36C25726R0053.docx DOCX document
Amendment 0002 36C25726R0053.docx DOCX document
Amendment 001 36C25726R0053.docx DOCX document
Sign in sheet Solicitation 36C25726R0053.pdf PDF
SPECIFICATIONS.pdf PDF
DRAWINGS-1.pdf PDF
Attachment 4 Itemized Cost Breakdown.xlsx XLSX spreadsheet
DRAWINGS-2.pdf PDF
DRAWINGS-4.pdf PDF
DRAWINGS-3.pdf PDF
DESIGN NARRITIVE.pdf PDF
PCRA ROADS AND ENTRANCES.pdf PDF
GEO-TECHNICAL REPORT.pdf PDF
36C25726R0053_1.docx DOCX document
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAST AND PRESENT PERFORMANCE QUESTIONNAIRE

Note: When completed this document is Source Selection Sensitive IAW FAR 2.101 and FAR 3.104

SUBJECT: Request for Past and Present Performance Evaluation

TO: (to be completed by the Offeror)

You have been identified as a point of contact for a past and/or present performance evaluation of the firm listed on the questionnaire below. This firm is currently being considered for a construction contract with the Department of Veterans Affairs, Network Contracting Office (NCO) 17, Solicitation # 36C25725R0056.

Your prompt attention to this questionnaire will be greatly appreciated. Please submit completed questionnaire via e-mail to nicholas.smith21@va.gov NLT the date and time specified in block 13 A of the Standard Form (SF) 1442. If you have any questions concerning this request, please email me at Nicholas.smith21@va.gov .

Sincerely, Nicholas Smith Contract Officer

PAST AND PRESENT PERFORMANCE QUESTIONNAIRE

A. GENERAL INFORMATION: (to be completed by the Offeror)

Contractor’s Name: LLC Telephone Number:

Contract Number: Tel/Fax Number:

Point of Contact (POC):

POC e-mail address:

Project Title and Brief Description of Work:

Title:

Description of Work

Contract Number: 605-20-427 Dollar Amount:

Final Cost:

Contract Performance Period: Project duration was 365 days initial scope completed in 305 days. Additional controls materials and scope extended the project to present date.

Contractor performed as the Prime Contractor Sub-Contractor

B. RESPONDENT INFORMATION:

Name of Respondent:Title:
Address:Telephone Number:
Fax Number:

Email Address:

C. E-MAIL COMPLETED SURVEY FORM TO: nicholas.smith21@va.gov

D. PERFORMANCE INFORMATION: Choose the appropriate letter on the scale (E, S, M, U, and N) that most accurately describes the contractor’s performance or situation. PLEASE PROVIDE A NARRATIVE EXPLANATION FOR ANY RATINGS OF M or U.

E: Exceptional: Performance meets contractual requirements with many exceeded to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with no more than a few minor problems for which corrective actions taken by the contractor were highly effective.

S: Satisfactory: Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor were satisfactory.

M: Marginal: Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented.

U: Unsatisfactory: Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

N: Neutral: Performance was not observed or not applicable to the current effort being reported against.

CONTRACTOR’S NAME: CONTRACT NUMBER:

Place an “X” in the appropriate rating letter using the definitions matrix above.

The contractor:

1. Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements.

E ___ S _____ M _____ U _____ N _____

2. Provided adequate project supervision.

E ____ S _____ M _____ U _____ N _____

3. Complied with all Federal and locals laws including OSHA, EPA, etc.

E _____ S _____ M _____ U _____ N _____

4. Provided effective inspection procedures which resulted in a quality finished project.

E _____ S _____ M _____ U _____ N _____

5. Corrected deficiencies in timely manner.

E _____ S _____ M _____ U _____ N _____

6. Provided timely resolution of contract discrepancies.

E _____ S _____ M _____ U _____ N _____

7. Identified problems as they occurred/ Suggested alternative approaches to problems.

E ____ S _____ M _____ U _____ N _____

8. Displayed initiative to solve problems.

E _____ S _____ M _____ U _____ N _____

9. Developed realistic progress schedules.

E ____ S _____ M _____ U _____ N _____

10. Was responsive to contract changes.

E _____ S _____ M _____ U _____ N _____

11. Provided accurate, and complete records E _____ S _____ M _____ U _____ N _____

12. Complied with standards of wood workmanship E _____ S _____ M _____ U _____ N _____

13. Paid subcontractors/suppliers in a timely manner.

E _____ S _____ M _____ U _____ N _____

14. Communicated with Government personnel to keep the project on schedule or minimize delays E _____ S _____ M _____ U _____ N _____

15. Was diligent in forecasting and controlling cost.

E _____ S _____ M _____ U _____ N _____

16. Provided timely and accurate billing.

E _____ S _____ M _____ U _____ N _____

17. Submitted reasonable priced change proposals.

E _____ S _____ M _____ U _____ N _____

18. How would you rate the contractor's overall performance?

E _____ S _____ M _____ U _____ N _____

19. Did you ever issued a cure or show cause notice under the referenced contract? If yes, explain outcome in “remarks.”

Yes _____ No _____

20. Would you award another contract to this contractor? If not, explain in “remarks Yes _____ No _____

CONTRACTOR’S NAME: