Clarifications 36C25726R0053.docx
DOCX document 16 KB Posted
- Solicitation number
- 36C25726R0053
About this file
This is a Clarifications document providing offeror guidance on submission requirements and evaluation criteria for solicitation 36C25726R0053, which concerns improvements to roads and entrances at the Olin E. Teague Veterans Medical Center in Temple, Texas.
The clarifications address four key points: (1) offerors are not required to submit CPAR printouts; (2) Past Performance Questionnaires (PPQs) are accepted for projects not yet rated in CPAR, with a template available on SAM.gov; (3) subcontractor past performance will only be evaluated if their work undergoes review due to a teaming event, with the prime contractor responsible for following solicitation instructions on past performance submissions; and (4) a component list and equipment identification document referenced in Amendment 0004 have been uploaded to SAM.gov under the solicitation number for offeror reference.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0006 36C25726R0053.docx | DOCX document | |
| Clarifications 2.docx | DOCX document | |
| Component List Pertaining to RFIs.pdf | ||
| Amendment 0005 36C25726R0053.docx | DOCX document | |
| PAST PERFORMANCE QUESTIONNAIRE TEMPLATE.docx | DOCX document | |
| RFIs with Responses for Solicitation 36C25726R0053.pdf | ||
| Amendment 0004 36C25726R0053.docx | DOCX document | |
| Amendment 0003 36C25726R0053.docx | DOCX document | |
| Amendment 0002 36C25726R0053.docx | DOCX document | |
| Amendment 001 36C25726R0053.docx | DOCX document | |
| SPECIFICATIONS.pdf | ||
| Sign in sheet Solicitation 36C25726R0053.pdf | ||
| DRAWINGS-4.pdf | ||
| DRAWINGS-3.pdf | ||
| DESIGN NARRITIVE.pdf | ||
| Attachment 4 Itemized Cost Breakdown.xlsx | XLSX spreadsheet | |
| DRAWINGS-2.pdf | ||
| PCRA ROADS AND ENTRANCES.pdf | ||
| GEO-TECHNICAL REPORT.pdf | ||
| 36C25726R0053_1.docx | DOCX document | |
| DRAWINGS-1.pdf |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Are offerors to submit CPAR printouts?
Response: No.
2. Will the VA accept PPQs for projects that have not yet been rated within CPARs? If yes, is there a specific format that must be used for the PPQ?
Response: Yes, the PPQ template has been uploaded to www.sam.gov under solicitation 36C25726R0053.
3. On page 18 of the solicitation, paragraph i states “”Offeror” refers to the proposed prime contractor.” Paragraph ii states”…the Offeror’s past performance, as well as that of its major subcontractors”. These statements appear to conflict, please advise. Will subcontractor past performance be evaluated?
Response: The subcontractor’s past performance will only be evaluated if their work is submitted for a review due to a teaming event. The Prime is required to follow the solicitation instructions as it relates to Past Performance submissions.
4. Additionally, the Amendment 0004 RFI references a document that is currently not available to review.
Question 47 - “See the attached list of components that the VA uses.”
Question 64 - “ See comment #48 and the attached document that identifies the equipment.”
Response: Please see the component list which has been uploaded to www.sam.gov under solicitation 36C25726R0053, which pertains to these questions.