36C25726R0032_2.docx
DOCX document 137 KB Posted
- Attached to
- 36C25726R0032_2 674A4-22-254 - CON CTX Consolidate Engineering Bldg. 17 Federal contract opportunity
- Solicitation number
- 36C25726R0032
About this file
This document is a Request for Proposal (RFP) for a construction project at the Doris Miller VA Medical Center in Waco, Texas. The Department of Veterans Affairs Network Contracting Office is seeking a Service-Disabled Veteran-Owned Small Business (SDVOSB) to consolidate and renovate Building 17, transforming the old laundry facility into offices and shops for engineering tradesmen, administrative, and professional staff. The project involves reconfiguring electrical, mechanical, plumbing, IT, and other building systems, with a total project value between $5,000,000 and $10,000,000.
Key details include a 365-calendar day performance period, with proposals due on January 27, 2026, by 10:00 AM CST. A mandatory site visit is scheduled for December 30, 2025, at 1:30 PM CST. The contract requires performance and payment bonds, and the contractor must provide a Superintendent at all times who cannot be subcontracted. The project will comply with VA specifications, infection control requirements, and all applicable city, county, state, and federal regulations. Offerors must be certified SDVOSBs listed in the SBA certification database and will be evaluated on technical acceptability, past performance, and price, with past performance weighted more heavily than price.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25726R0032 0005.docx | DOCX document | |
| 36C25726R0032 0004_Consolidated Engineering Building 17.docx | DOCX document | |
| 36C25726R0032 0003.docx | DOCX document | |
| PN 674A4-22-245_100ptc_VOL 2_23-12-07_EL (1).pdf | ||
| 36C25726R0032 0002.docx | DOCX document | |
| PN 674A4-22-245_100ptc_VOL 2_23-12-07_MH.pdf | ||
| PN 674A4-22-245_100ptc_VOL 2_23-12-07_FA.pdf | ||
| 36C25726R0032 0001.docx | DOCX document | |
| Site visit sign in sheet 25_12_30.pdf | ||
| PN 674A4-22-245_100ptc_VOL 2_23-12-07_PL.pdf | ||
| Attachment 1 Drawings PN 674A4-22-245_100ptc_VOL 1_23-12-07.pdf | ||
| Attachment 4 Itemized Cost Breakdown.xlsx | XLSX spreadsheet | |
| Attachment 3 09-16368 Waco Bldg. 17 Report.pdf | ||
| Attachment 2 Specs PN674A4-22-254_100ptc_SPECS_12-08.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A.1 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)
The Contracting Officer reserves the right to designate an Administrative Contracting Officer (ACO) for the purpose of performing certain tasks/duties in the administration of the contract. Such designation will be in writing through an ACO Letter of Delegation and will identify the responsibilities and limitations of the ACO. A copy of the ACO Letter of Delegation will be furnished to the Contractor.
(End of Clause)
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C25726R0032 X
TBD
TBD
674A4-22-254 36C671 Department Of Veterans Affairs Network Contracting Office 17 5441 Babcock Road Ste. 302 San Antonio
TX
78240 Department of Veterans Affairs Network Contracting Office 17 5441 Babcock Road Ste. 302 San Antonio
TX
78240 Stephanie Ingersoll 210-240-6838
This is a Request for Proposal (RFP) for 674A4-22-254 - Consolidate Engineering Bldg. 17
The contractor shall provide all labor, supervision, materials, and equipment to complete all required project work in accordance with the Statement of Work.
NAICS: 236220 PSC: Z2DA Construction Magnitude: Between $5,000,000 and $10,000,000 IAW VAAR 836.204(f)(2).
This solicitation is 100% Service-Disabled Veteran Owned Small Business SDVOSB set-aside.
Performance and payment bonds are required.
Place of Performance: Doris Miller VA Medical Center, 4800 Memorial Drive, Waco, TX 76711
Site Visit: December 30, 2025, at 1:30 PM CST at Bldg 12 Room BB108, at the Waco VAMC POC Andrew Oliver (254)658–3586 Email: andrew.oliver@va.gov
RFIs Due: 6 January 2026, by 10:00 AM CST, email to stephanie.ingersoll@va.gov Proposals Due: January 27,2026, by 10:00 AM CST, email tostephanie.ingersoll@va.gov
NOTE: Please follow all instructions to offerors on the following pages or your proposal could be deemed nonresponsive.
Awardees will be required to provide a Superintendent at all times work is being performed on the project in accordance with FAR Clause 52.236-6. The Superintendent is considered a key position and SHALL NOT be subcontracted and must work directly for the prime contractor.
X X 52.211-10 X 10:00
CST
01-27-2026 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Department of Veterans Affairs Network Contracting Office 17 5441 Babcock Road Ste. 302 San Antonio
TX
78240 This is accomplished through the Tungsten Network located at:
http://www.fsc.va.gov/einvoice.asp This is mandatory and the sole method for submitting invoices.
(877) 353-9791
(512) 460-5540 Rhonda Richardson Contracting Officer
Table of Contents
| A.1 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 1 | |
| PART I - THE SCHEDULE | 2 | |
| SECTION A - SOLICITATION/CONTRACT FORM | 2 | |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 2 | |
| A.3 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 3 | |
| A.4 PRICE/COST SCHEDULE | 6 | |
| ITEM INFORMATION | 6 | |
| 1. | PROJECT OVERVIEW | 6 |
| 2. | SCOPE OF WORK | 7 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 16 | |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 16 | |
| A.5 INSTRUCTIONS TO OFFERORS | 16 | |
| PROPOSAL PREPARATION INSTRUCTIONS | 16 | |
| EVALUATION FACTORS FOR AWARD | 20 | |
| 2.1 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023) | 25 | |
| 2.2 52.216-1 TYPE OF CONTRACT (DEVIATION) (NOV 2025) | 25 | |
| 2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 26 | |
| 2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 26 | |
| 2.5 52.228-1 BID GUARANTEE (SEP 1996) | 27 | |
| 2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021) | 28 | |
| 2.7 52.233-2 SERVICE OF PROTEST (SEP 2006) | 28 | |
| 2.8 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS REPRESENTATIONS AND CERTIFICATIONS (NOV 2025) (DEVIATION) | 29 | |
| 2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 33 | |
| 2.10 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 33 | |
| 2.11 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 34 | |
| REPRESENTATIONS AND CERTIFICATIONS | 35 | |
| 3.1 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 35 | |
| 3.2 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021) | 36 | |
| GENERAL CONDITIONS | 39 | |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 39 | |
| 4.2 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025) | 39 | |
| 4.3 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022) | 42 | |
| 4.4 52.227-4 PATENT INDEMNITY—CONSTRUCTION CONTRACTS (DEC 2007) ALTERNATE I (DEC 2007) | 47 | |
| 4.5 52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (NOV 2025) (DEVIATION) ALTERNATE I (NOV 2025) | 47 | |
| 4.6 SUPPLEMENTAL INSURANCE REQUIREMENTS | 57 | |
| 4.7 52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (NOV 2025) (DEVIATION) | 57 | |
| 4.8 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 67 | |
| 4.9 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY ACCESSIBILITY NOTICE (FEB 2023) | 68 | |
| 4.10 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 68 | |
| 4.11 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION) | 70 | |
| 4.12 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 73 | |
| 4.13 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 74 | |
| 4.14 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 74 | |
| 4.15 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 76 | |
| 4.16 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION) | 77 | |
| 4.17 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 79 | |
| 4.18 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 80 | |
| 4.19 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2020) | 87 |
A.4 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
The contractor shall provide all supervision, labor, equipment, and materials needed to complete work for Project 674A4-22-254 Consolidated Engineering Bldg. 17 per the provided drawings, specifications, and statement of work.
PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: 5680 – Miscellaneous Construction Materials
| 1.00 |
| EA |
| __________________ |
| __________________ |
Performance and Payment Bonds PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: 5680 - Miscellaneous Construction Materials
| GRAND TOTAL |
| __________________ |
Page 1 of Page 1 of Consolidate Engineering Building 17 Project # 674A4-22-254
STATEMENT OF WORK
1. PROJECT OVERVIEW
1.1 PURPOSE: The Contractor must provide all labor, material, equipment and testing services as required to construct project Consolidate Engineering Building 17 in accordance with all Contract Documents. The project is located in building 17 at the Doris Miller Veterans’ Medical Center located at 4800 Veterans Memorial Drive, Waco, Texas 76711.
This project will reconfigure and renovate the old laundry facility located at the Waco VAMC. The space will be converted into offices and shops for engineering tradesmen, administrative, and professional staff.
The project will include the reconfigurations of the electrical, mechanical, plumbing, IT, and other systems as called for in the Construction Documents.
2. SCOPE OF WORK
2.1 GENERAL: This project will renovate the old laundry building (17) for engineering services. The goal is to reconfigure the building for engineering services. Since this is a 24-hour healthcare facility, some elements of the work shall require after-hour and weekend work.
Work shall include:
The base portion of the project will include all labor, material, equipment and supervision to perform the task described in the construction documents. A site visit is highly encouraged prior to bidding.
Normal hours of operation for VA sites are 8:00AM to 4:00 PM Monday through Friday except for Federal Holidays. If the Contractor desires to work on Saturday, Sunday, holidays, or outside the project site’s normal working hours the contractor must submit a written request for approval to the VA-COR at least five (5) working days prior to the proposed start of such work.
2.2 DESCRIPTION OF WORK
A. Existing Conditions
a. Before disabling any of the following systems, the contractor needs to coordinate with COR at least 10 working days in advance. Contractor shall be responsible for relocating and temporary installing all utilities and controls, including, but not limited to, telephone, data, electrical, med/gas, emergency power, AV alarms, smoke detectors, sprinklers heads, speakers, nurse call, card readers, isolation monitor, phone booster, Wi-Fi boosters, pull stations, etc. It is the contractor’s responsibility to immediately repair any tampered with system at no additional cost to the government.
b. Contractor will coordinate all work with existing work to remain and existing conditions.
c. Contractor shall be responsible for complying with all the construction documents and applicable Department of Veterans Affairs Master Specifications as part of this project.
d. Contractor must also comply with all applicable city, county, state, and federal regulations / codes and applicable OSHA standards project. Construction shall also comply with Infection Control Risk Assessment (ICRA), attached, and IC standards delineated in the specifications.
e. Demolition and renovation shall take place with minimal disruption to adjacent workspaces.
f. Demolition debris shall be recycled to the best ability of the contractor. Reports of weight and deposition of all waste are to accompany the monthly progress payments (C&D Waste Form attached). Form also included in corresponding specification.
g. Any item damage during removal is the contractor’s responsibility to replace with no additional cost to the government.
h. All work shall be in accordance with VA specifications. All costs shall be included in the base bid. All work shall be coordinated with the VA prior to any demolition work being performed.
i. There will be no contractor parking allowed outside of designated areas and the contractor’s limits of construction.
j. All work shall be in accordance with VA specifications. All costs shall be included in the base bid. All work shall be coordinated with the VA prior to any demolition work being performed.
B. Additional Requirements
a. Housekeeping - Accumulation of trash, paper, wood shavings, sawdust, excelsior, boxes and other packing materials will be cleaned up as often as necessary and at the end of each workday.
b. False Alarms – Fire Department response fees for false alarms caused by the contractor will be paid by the contractor. To avoid this, dust covers for smoke detectors and alarms are required to be used while construction work is ongoing. These covers shall be removed at the end of the construction work shift to keep them operational.
c. Fire Watch - Provide fire watch for impairments more than 4 hours in a 24-hour period. Request interruptions in accordance with Article, OPERATIONS AND STORAGE AREAS, and coordinate with COR and facility safety officer. All existing or temporary fire protection systems (fire alarms, sprinklers) located in construction areas shall be tested as coordinated with the medical center. Parameters for the testing and results of any tests performed shall be recorded by the medical center and copies provided to the COR.
d. Smoking is strictly prohibited in all facilities, near flammable liquids, highly combustible materials. Smoking is only authorized in designated smoking areas.
e. Security – Contractors will wear security badge in plain sight above the waist at all times. Contractors found without a badge will be immediately removed from VA property by VA Police.
f. Parking - There will be no contractor parking allowed outside of designated areas and the contractor’s limits of construction.
g. Tuberculosis (TB) – Contractor is responsible for ensuring that if contracted construction worker(s) have been determined to be at risk for transmission of TB based upon the TB pre-construction risk assessment. The contractor must provide written certification, within 24 hours upon request, to the COR that all contract employees assigned to the work site have had a pre-placement tuberculin screening within 90 days prior to assignment to the work site and been found to be free of active TB. Refer to the contract documents for this requirement.
h. Invoicing-Submit the proper documentation and reports to receive payment on this service. See information below:
Payment to be made monthly, in arrears, following satisfactory performance by Contractor’s personnel and upon receipt of a properly prepared invoice. Contractor shall be required to invoice through the Tungsten System at http://www.tungstennetwork.com/us/en/veterans-affairs/. Additional information regarding Tungsten shall be provided upon award. The contract shall have current registration in the System for Award Management (SAM) for this solicitation; URL: www.sam.gov. The invoice MUST be itemized to include the following information. Any information listed below, and not provided on an invoice, will render that invoice incomplete and the invoice will be returned for immediate correction:
| 1. Time period being invoiced for | |
| 2. Description of services performed. | |
| 3. Unit Cost billed. | |
| 4. Extended amount due. | |
| 5. Invoice number, date, and | |
| 6. Contract and obligation numbers. |
i. Government Holidays:
a. The Government hereby provides notice, and the Contractor hereby acknowledges receipt that Government personnel observe the listed days as holidays:
New Year's Day January 1st Martin Luther King's Birthday Third Monday in January Washington’s Birthday Third Monday in February Memorial Day Last Monday in May Juneteenth June 19th Independence Day July 4th
| Labor Day |
| First Monday in September |
| Columbus Day |
| Second Monday in October |
| Veterans Day |
| November 11th |
| Thanksgiving Day |
| Fourth Thursday in November |
| Christmas |
| December 25th |
b. In addition to the days designated as holidays, the Government observes the following days:
1. Any other day designated by Federal Statute
2. Any other day designated by Executive Order
3. Any other day designated by the President’s Proclamation
· It is understood and agreed between the Government and the Contractor that observance of such days by Government personnel shall not otherwise be a reason for an additional period of performance, or entitlement of compensation. In the event the Contractor's personnel work during the holiday, they may be reimbursed by the Contractor, however, no form of holiday or other premium compensation will be reimbursed either as a direct or indirect cost, other than their normal compensation for the time worked.
j. All construction and installation work shall comply with VA specifications for material and workmanship, NEC, NFPA and all applicable city, county, state, and federal regulations and codes and OSHA standards. Refer construction drawings and specs for requirements.
k. All incidental work associated with the installation and construction works in the exterior and interior of the building shall be included in the base bid.
l. Conduct work as to interfere as least as possible with facility operations. All coordination for utilities shutdown shall be coordinated at least 72 hours prior to event with COR. For major utility system shutdowns, coordination shall be done at least 2 weeks in advance.
m. Construction signs and copy of IC permits shall be posted in the project site at all times. All IC and dust control measures shall be implemented at all times. All construction workers shall have a current IC training sticker attached to their badges at all times. If this requirement is not met, workers will be removed from construction site. Refer to construction documents for additional information.
n. All fire and smoke wall penetrations shall be fireproofed according to corresponding wall rating. These shall be through a sleeve and sealed with fire barrier compound to be approved by VA.
2.3 OTHER DELIVERABLES
A. Period of Performance: 365 Calendar days after Notice to Proceed
B. Performance and Payment bonds: Due 10 Calendar days after Notice of Award
C. Proof of Insurance: Due 10 Calendar days after Notice of Award
D. Contractor Quality Control Plan (CQCP): The contractor shall develop a quality control plan and shall furnish to VA for review no later than 30 calendar days after the receipt of notice to proceed. The plan shall identify personnel, procedures, control, instructions, tests, records, and forms to be used. VA will consider an interim plan for the first 45 calendar days of operation. Installation will be allowed to begin only after acceptance of the CQCP or acceptance of an interim plan applicable to the particular feature of the work to be started. Work outside of the features of the work included in an accepted interim plan will not be permitted to begin until acceptance of a CQCP or another interim plan containing the additional features of the work to be started. After acceptance of the CQCP, the Contractor shall notify the Contracting Officer Representative (COR) in writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer. Please see Appendix H for additional details.
E. Safety Plan: Contractor shall develop and implement a Comprehensive safety plan to eliminate injuries occurring relative to providing the design and installation services for this project. Contractor shall furnish to VA for review no later than 15 calendar days after the receipt of notice to proceed. The plan shall also describe how final system installation will meet all applicable requirements of NFPA30 and NFPA30A. Construction/Renovation work will be allowed to begin only after VA’s acceptance of the Safety Plan. Contractor is responsible for providing enough project lead time to allow for VA review of Safety Plan before acceptance. The Department of Labor OSHA requires that all Contractors involved in installation on VA owned or leased property comply with the Incorporation of General Industry Safety and Health Standards applicable to Installation Work and Technical Amendments, Final Rule 29 CFR Parts 1910 and 1926 as published in the Federal Register Volume 58, No. 124, June 30, 1993. In addition, any Contractor that performs construction type work on any VA project as defined by the Scope of the referenced regulation is required to; (1) Provide and maintain his own protective equipment and devices, etc; and (2) Require all sub-contractors used on site to follow these same provisions in the regulation.
F. Submittals CD: As part of the closeout documentation, the contractor shall provide the COR, 3 CDs containing all the approved submittals.
G. Operations and Maintenance Manuals (O&M): The Contractor shall provide three (3) complete sets of O&M manuals including a recommended spare parts list identifying components adequate for competitive supply procurement for operation and maintenance of the system. The O&M Manuals shall include maintenance and inspection for all equipment. A three-ring binder containing all of the O&M and electronic files on CD-ROM shall be provided within the binder.
H. Submittals CD: As part of the closeout documentation, the contractor shall provide the COR, 4 CDs containing all the approved submittals.
I. Operations and Maintenance Training: The Contractor shall provide on-site O&M training for the location which will consist of two (2) formal on-site training sessions during a 30 day period to including but not limited to system operation, corrective and preventive maintenance and inspections.
The contractor shall provide training manuals that include the hands-on exercises, O&M data and troubleshooting guides necessary for personnel to assume full O&M responsibility for the system after completion of the training. The contractor shall provide a written training syllabus for the topics and detailed training content for review and approval by the COR at least 30 days prior to the scheduled training. The contractor will coordinate with the COR the scheduling of any training classes in advance. The COR may require the classes to be provided on non-consecutive days at the convenience of the VA Staff. The Contractor shall video tape this training for official use and forward CD (3 copies) including those training videos.
J. Warranty: Contractor shall provide a minimum three (3) year warranty, unless specified otherwise in the specs, from both the manufacturer and installer including parts and labor to include normal, premium or holidays hours. The Warranty period shall start on the date of Substantial Completion.
2.4 ACCEPTANCE
A. For the purposes of Warranty and payment for the work performed at a location, government “Acceptance” will be provided by the VA upon the completion of all of the following:
a. The Contractor has demonstrated/ verified that the implemented ECMs function as intended at commissioning. All punch list items identified during the commissioning have been resolved.
b. The Contractor has provided O&M manuals.
c. The Contractor has provided Record drawings to include a CD with all as builds CAD files, one full set, one half set and one Mylar full set.
2.5 CONFIDENTIALITY AND NONDISCLOSURE
A. The preliminary and final deliverables and all associated working papers, application source code, and other material deemed relevant by the VA which has been generated by the contractor in the performance of this Order are the exclusive property of the U.S. Government and shall be submitted to the VA-COR at the conclusion of the contract.
B. The Contracting Officer will be the sole authorized official to release verbally or in writing, any data, the draft deliverables, the final deliverables, or any other written or printed materials pertaining to this contract. No information shall be released by the contractor. Any request for information relating to this contract presented to the contractor shall be submitted to the CO for response.
C. Press releases, marketing material or any other printed or electronic documentation related to this project, shall not be publicized without the written approval of the CO.
D. To the extent that the work under this contract requires that the contractor be given access to proprietary business, technical or financial information belonging to the Government or other companies, the contractor shall treat such information as proprietary business sensitive and agrees not to appropriate such information to its own use or to disclose such information to third parties unless specifically authorized by the CO in writing. A mutually agreed to agreement for exchange of sensitive information or nondisclosure agreement may be required.
E. The Contracting Officer Representative (COR) is responsible for the inspection, technical supervision, and acceptance of the work called for in the contract schedule, including related specifications and contract terms regarding onsite work requirements. Pursuant to the Delegation of Authority (by separate memo), he or she does not have the authority to make changes to the contract in quantity, dollar amount, or time. Coordinate with VA COR before the start of work.
F. General Requirements for Privacy Information:
· Information Systems Officer, Information Protection: The contractor will not have access to VA Desktop computers, nor will they have access to online resources belonging to the government while conducting services.
· Privacy Officer: The contractor will not have access to Patient Health Information (PHI) nor will they have the capability of accessing patient information during the services provided to the VA.
· Records Manager: There will be no federal records created, maintained, used or dispositioned with this contract; regardless of format [paper, electronic, etc.] or mode of transmission [e-mail, fax, etc.].
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
A.5 INSTRUCTIONS TO OFFERORS
PROPOSAL PREPARATION INSTRUCTIONS
1. Introduction: These instructions prescribe the format of proposals along with the development and presentation of the proposal data. These instructions are designed to ensure the proper submission of information necessary to provide for comprehensive evaluation of proposals. Offerors shall carefully review this section prior to commencing proposal preparation and take the necessary measures to ensure that the information submitted is factual, accurate, and complete.
2. Notice: For a proposal to be considered, offerors must strictly comply with all instructions outlined in this solicitation. Furthermore, all solicitation amendments (if any) must be acknowledged in accordance with FAR Clause 52.215-1- Instructions to Offerors. Failure to furnish proposals that comply with all instructions and include complete copies of required documents, at the predetermined due date for submission, shall result in elimination from consideration for the award.
3. Submission instructions: Offers must be submitted by email to the Contracting Officer, Rhonda Richardson, by email at Rhonda.richardson5@va.gov and Contract Specialist, Stephanie Ingersoll, by email at stephanie.ingersoll@va.gov. Proposals may not be submitted by fax. Offers must be submitted on or before the due date and time listed on page one, block thirteen.
Proposals must be submitted in four volumes:
a. Technical Acceptability-Vol. I
b. Past Performance-Vol. II
c. Price-Vol. III
d. Solicitation, Offer, & Award Documents-Vol. IV
Offerors may submit their proposals in one to four emails. Volumes I through IV must be submitted as separate, searchable PDFs. Each volume must be submitted as attachments to their submission email(s). Proposals submitted by any other method, including hyperlinks or drop boxes, will not be considered. The subject of each email shall be in the following format, specifying which volume(s) are included: “36C25726R0032 - CTX 674A4-22-254 – Consolidate Engineering Building 17” – Company Name, Volume I”. Each email must clearly indicate how many total emails the Offeror will be sending.
4. Format Instructions: Proposals must be clearly indexed and logically assembled. Each volume must have a clear title at the top of the first page. All pages of each volume shall be appropriately numbered and identified by the complete company name, date, and solicitation number in the header and/or footer.
Proposal page limitations are applicable to this procurement. The table below indicates the maximum page count for each volume:
| Volume Number |
| Factor |
| File Name |
| Page Limitations |
| Volume I |
| Technical Acceptability |
| Tech.pdf |
| 5 pages |
| Volume II |
| Past Performance |
(One Sanitized Copy)
| Past Perf.pdf |
| 40 pages |
| Volume III |
| Price/Cost |
| Price.docx |
| Complete A.3, Price/Cost Schedule for Project Pricing |
| Volume IV |
| Solicitation, Amendments, Offer & Award Documents, Certifications & Representations |
| OfrRep.pdf |
| None |
If the Offeror submits annexes, documentation, attachments, or the like, such will count against the Offeror’s page limitations unless otherwise indicated in this solicitation. The page count will be determined by counting the pages in the order they come up in the print layout view. Pages in violation of these instructions, including those that exceed the total page limit for a particular volume, will not be evaluated. Proposals must be in at least 12-point font and have at least 1” margins.
If an offeror includes a table of contents or a glossary of terms or abbreviations, those pages will not be included in the page count of that volume. However, substantive information included in the table of contents or glossary pages will not be considered.
1. Content Instructions: Information must be confined to the appropriate volume. The Offeror shall confine submissions to essential matters sufficient to define the proposal and provide an adequate basis for evaluation. Offerors are responsible for including sufficient details, in a concise manner, to permit a complete and accurate evaluation of each proposal. All proprietary information shall be clearly and properly marked.
2. Volume Specific Submittal Instructions:
a. Volume I – Technical Acceptability: Provide proof of Experience Modification Rating (EMR). Each Offeror shall provide their current EMR, or verifiable equivalent, from their insurance company or from their state, based on the offeror’s state of incorporation’s EMR requirements. The Government will consider the most recent timeframe corresponding to the Offeror’s insurance coverage period. If an offeror submits an EMR older than 12 months, using a three-year average at the time of proposal submittal, that offer shall be deemed unacceptable and cause the offeror to be removed from competition. An EMR less than or equal to 1.00 will be considered technically acceptable. If the NCCI cannot issue an EMR because the Offeror lacks insurance history, the Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead and include a letter from the NCCI indicating that it has assigned Offeror a Unity Rating of 1.0
b. Volume II – Past Performance (also provide a sanitized copy)
i. Sub-Factor 1: Past Performance Project History
1. Offerors are encouraged to submit information relating to up to three projects, each with a minimum value of $5 million, that have been completed or is in the process of completing within the last three (3) years. If submitting such information, offerors must provide a detailed summary of these projects, including:
a. Owner Government Agency/Company who awarded contract
b. Location (physical address)
c. Project Name
d. Project Description (Details of construction renovation requirements, challenges, and solutions)
e. Project Cost and Cost Control Measures (original and final contract costs, contract mods, cost containment measures, value engineering, etc.)
f. Project Performance Period (Initial/Actual, schedule impacts and efficiencies)
g. Owner POC (Name, Title, Telephone Number, Email)
h. Subcontractors (Roles, Responsibilities, Percent of work)
i. A narrative description of the project that includes whether the project involved work on healthcare installation. The narrative must also address the complexity and magnitude of the project, any challenges faced and how the offeror responded to those challenges, whether the project stayed on schedule, whether any unforeseen site conditions were encountered, any other unusual factors, and the degree of success obtained. Offerors are encouraged to include supporting documents such as photographs that support the narrative.
c. Volume III – Price: Complete Price/Cost Schedule
(1) Complete the price offer schedule in section A.3
(2) Price shall be addressed using the attached price breakdown worksheet, which is included in Attachment 4.
(3) Provide supporting documentation showing quotes/price breakdowns for both prime and subcontractors.
NOTE: Price breakdown shall be indicative of showing at least 15 percent of the cost of the contract performance incurred for personnel will be spent on the concern's employees or the employees of other eligible service-disabled veteran-owned small business concerns in accordance with VAAR 852.219-73(d)(3).
d. Volume IV - Solicitation, Offer, & Award Documents-Vol. IV
i. Certifications and Representations. An authorized official of the offeror shall sign the SF 1442 and all certifications requiring original signature. Volume 4 must contain the following:
1. Solicitation Section A – Standard Form SF 1442 and Acknowledgement of Amendments, if any. All blocks under section "OFFER" on page 2 of SF 1442 (Item 14 through 20C) shall be completed. Offerors shall be solely responsible for monitoring Government's website SAM.gov for amendments to this solicitation, if any, and acknowledge them in accordance with the requirements stipulated in this solicitation and amendments. The Offeror must acknowledge and agree to all amendments by either 1.) completing block 19 of the SF 1442, or 2.) returning the signed amendment form(s) with the submission.
2. Any proposed exceptions to solicitation terms and conditions. Any Offeror-imposed terms and conditions which deviate from the Government’s material terms and conditions established by the Solicitation, may render the Offeror’s proposal Unacceptable and thus ineligible for award.
3. A copy of the VETS 4212 Federal Contractor Reporting (if applicable).
4. Signed 852.219-75, VA Notice of Limitations on Subcontracting—Certificate of Compliance for Services and Construction. To be eligible for award for an SDVOSB set-aside contract for services and construction, VAAR 852.219-75, Limitations on Subcontracting (LOS) requires certification to be completed, signed, and returned with the offeror’s proposal. The completed and signed forms will become part of the official award documentation.
5. Self-Performed Work Calculation Worksheet
6. Any offeror submitting a proposal as a joint venture must provide a certification from each SDVOSB joint partner, signed by an authorized official of each partner to the joint venture, stating that the parties to the joint venture:
a. have entered into a joint venture agreement that fully complies with paragraph (c) of 13 CFR § 128.402; and
b. will perform the contract in compliance with the joint venture agreement. Failure to submit the certification with the offeror’s proposal will render the offeror ineligible for award.
7. Bid bond - The Offeror must furnish a bid guarantee (see FAR 52.228-1). The bid guarantee must be provided on SF 24. The offeror shall ensure all bonding comes from the Bureau of the Fiscal Service (BFS), Surety Bonds, List of Certified Companies found at: https://www.fiscal.treasury.gov/surety-bonds/list-certified-companies.html. In addition, at time of award offeror shall provide performance and payment bonds IAW FAR 28.102-1(a) for the proposed amount of the project.
8. SDVOSB Certification: Offerors are required to be SDVOSB certified with the Small Business Administration (SBA). Offerors must register their businesses at MySBA Certifications, https://certifications.sba.gov/. Verification of the offerors’ SDVOSB certification will be conducted using SBA Small Business Search, https://search.certifications.sba.gov/.
Offerors must have an active registration in the System for Award Management (SAM), including completed and annually validated representations and certifications. Verification of offerors active SDVOSB registration will be conducted using SAM.gov
EVALUATION FACTORS FOR AWARD
1. Source Selection Process Overview. All proposals shall be subject to evaluation by a team of Government personnel. Proposals will be evaluated strictly in accordance with their written content. Subjective judgment by the government is implicit in the evaluation process.
a. The Government will first review proposals to determine whether they are complete and comply with the instructions set forth in this solicitation. The Government will eliminate all proposals that were submitted late and not subject to an applicable exception, fail to comply with all instructions, or are incomplete. Offerors are to be and will be verified at https://dsbs.sba.gov/ as a SDVOSB under NAICS Code: 236220 – Other Building Equipment Contractors which has a $45 Million small business size standard. The Government will then determine whether remaining offerors are able to meet the following bonding requirements. Each offeror must demonstrate its ability to obtain bonding for a minimum amount of the offeror’s proposed price. The offeror shall demonstrate all bonding comes from the Bureau of the Fiscal Service (BFS), Surety Bonds, List of Certified Companies found at https://www.fiscal.treasury.gov/surety-bonds/list-certified-companies.html. A complete proposal is one that includes all required information and documentation, including any applicable representations, forms, or clauses requiring information or signatures from offerors. Proposals which merely restate a requirement or state that a requirement will be met, without providing supporting rationale, will be deemed incomplete and not considered.
b. Next, the Government will evaluate each remaining offeror’s Volume I Technical Capability. The Government will eliminate any proposals that are not technically acceptable.
c. The Government will then conduct a tradeoff process with all remaining offerors. The Government will consider Volume II Past Performance and Volume III Price in this tradeoff process. In using this source selection process, the Government intends to make an award based on which offeror provides the best value to the Government considering and comparing the past performance and price of each remaining offeror. Past Performance is significantly more important than price in this process.
d. The Government intends to make an award without discussions, but it reserves the right to conduct discussions if doing so would be in the best interest of the Government. Initial proposals should contain the offeror’s best offer. The Government may request clarifications, as described in FAR 15.306(a).
e. A contract will be awarded to the offeror who presents the best value to the Government considering Past Performance and Price.
2. Evaluation Factors
a. Technical Acceptability:
Experience Modification Rating (EMR)
i. The Offeror shall provide their current EMR. Any EMR older than 12 months, at the time of proposal submittal shall be deemed unacceptable and cause the offeror to be removed from competition. An EMR less than or equal to 1.00 is considered Technically Acceptable.
ii. The Offeror shall provide their EMR or verifiable equivalent, from their insurance company or from their state, based off the offeror’s state of incorporation’s EMR requirements. The EMR, or equivalent, shall be newer than 12 months, at time of proposal receipt. It is understood that EMRs may have a future forecasted start date due to how the company who generates EMRs assigns EMRs. As such, EMRs provided with a future start date will be deemed acceptable, if an EMR is not more than three months from the date of solicitation close date. A letter that states there isn’t enough work experience to have EMR will automatically constitute a numbered rating of “1.0”. Any stated equivalents shall be explained thoroughly to the Government. A lack of sufficient detail may deem this Factor as “Unacceptable”.
iii. Any Offeror who receives a rating of Unacceptable as part of the technical acceptability review will be eliminated from consideration for award.
b. Past Performance
i. The Government will assess the relative risks associated with an Offeror's likelihood of success in fulfilling the solicitation's requirements as indicated by that Offeror's record of past performance. In this context, “Offeror” refers to the proposed prime contractor. A joint venture will be assessed on the combined performance of each or as a team of the joint venture offerors.
ii. The Government will conduct a performance risk assessment based on the quality, relevancy, and recency of the Offeror's past performance, as well as that of its major subcontractors, as it relates to the probability of successful accomplishment of the required effort. Offerors are cautioned that the Government will review available past performance data available in the Contractor Performance Assessment Reporting System (CPARS). The Government reserves the right to consider past performance information from any available source and may contact customers other than those identified by the Offeror when evaluating past performance. Since the Government may not necessarily interview all the sources provided by the Offerors, it is incumbent upon the Offerors to explain the relevance of any data provided. Offerors are reminded that the burden of proving low performance risk rests with the Offerors.
Per FAR 15.305(a)(2)(iv), “in the case of an offeror without a record of relevant past performance or for whom information on past performance is not available, the offeror may not be evaluated favorably or unfavorably on past performance.”
The Government intends to use the following rating system to guide its analysis:
Past Performance Rating Key
| Rating |
| Definition |
| Substantial Confidence |
| Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort. |
| Satisfactory Confidence |
| Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort. |
| Limited Confidence |
| Based on the offeror’s recent/relevant performance record, the Government has little expectation that the offeror will be able to successfully perform the required effort. |
| No Confidence |
| Based on the offeror’s recent/relevant performance record, the Government has no expectations that the offeror will be able to successfully perform the required effort. |
| Unknown Confidence (Neutral) |
| No recent/relevant performance record is available, or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. |
The Government intends to use the following rating system to guide its evaluation of the relevance of past performance information:
Past Performance Relevancy Rating Key
| Rating |
| Definition |
| Very Relevant |
| Present/Past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires. |
An example would be a renovation construction project $5M or greater, with the VA in a healthcare installation (internal/external). *Note, $5M is used as a benchmark based off the project’s magnitude Between $5,000,000 and $10,000,000.
| Relevant |
| Past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires. |
An example would be a renovation construction project $5M or greater, with other Government agencies on a healthcare installation (internal/external).
| Somewhat Relevant |
| Past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires. |
An example would be a renovation construction project worth less than $5M on a healthcare installation (internal/external).
| Not Relevant |
| Past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires. |
An example would be a renovation construction project less than $5M not on a healthcare installation.
c. Price: Fixed Price. The Government will evaluate offers by adding the total of all line-item prices. The Total Evaluated Price will be that sum. The Government will evaluate the total proposed price of all Offerors who are not eliminated before the tradeoff process stage as an indicator of the value the Offeror will provide on project. The Government will also evaluate the Total Evaluated Price to determine whether proposals are fair and reasonable.
The Government will strictly enforce all the proposal submission requirements outlined in the solicitation. Failure to comply with these requirements will result in an Offeror's proposal being rejected as being incomplete or non-conforming to solicitation requirements. It is solely the responsibility of offerors to ensure the Government receives proposal before or on the exact due date and time set forth in this solicitation. Offerors shall provide confirmation of the bid bond delivery via email to stephanie.ingersoll@va.gov and Rhonda.richardson5@va.gov prior to the closing date and time.
Deadline for all inquiries for this solicitation is listed on SF1442. Government’s responses to inquiries will be issued in the form of Amendment(s) to be posted on the same website where this solicitation is posted: www.SAM.gov. All interested offerors, including those submitting inquiries, are required to monitor the above website for any posted amendments and acknowledge them in accordance with the instructions provided in the amendments as well as in this solicitation.
Self-performed calculations:
INSTRUCTIONS FOR CALCULATION OF SELF-PERFORMED WORK IAW “Limitations on Subcontracting” (VAAR 852.219-73)
OFFEROR’S SELF PERFORMED ESTIMATED CALCULATIONS
At the time of proposal Offeror’s are required to complete.
a) Offeror’s total proposed price: $ __________
b) Cost of Materials : $ __________
c) Amount projected to be paid on Non-VetCert (SBA.gov) SDVOSBs $__________
d) Offeror’s percentage of estimated Non-VetCert work (d/c X 100 = %) _________%
e) Offeror’s percentage of estimated self-performed work (100 – d = %) _ _________%
A/E-Services. In the case of a contract for services (except construction), it will not pay more than 50% of the amount paid by the government to it to firms that are not VIP-listed VOSBs.
General construction. In the case of a contract for general construction, it will not pay more than 85% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs.
Special trade contractors. In the case of a contract for special trade contractors, it will not pay more than 75% of the amount paid by the government to it to firms that are not VIP-listed SDVOSB.
V.T.C.A. Tax Code §151.311 Offerors are hereby notified that in accordance with V.T.C.A., Tax Code §151.311, the purchase of tangible personal property for use in the performance of a contract for an organization exempted under Section 151.309 or 151.310 of this code is exempt if the…