About this file

This is a revised price sheet for a construction contract to renovate the Sterile Processing Service (SPS) facility at the Veterans' Health Care System of the Ozarks located at 1100 North College Avenue, Fayetteville, Arkansas 72703. The contractor must furnish all supervision, labor, material, tools, and equipment in accordance with project plans and specifications.

The pricing structure includes five line items with a fallback award mechanism based on available funding. Line Item 1 encompasses all renovation work including the lease of a delivery trailer with a 12-month period of performance, requiring the offeror to provide both a total contract price and a monthly lease cost. Line Item 2 covers all work per drawings and specifications with a 720 calendar-day performance period and requires a price breakdown by specification divisions on page 5. Line Item 3 (Alternate #1) excludes demolition of concrete pads and supporting exterior work for mobile SPS and Logistics Trailers with a 720 calendar-day timeline. Line Item 4 (Alternate #2) excludes both the items in Alternate #1 and demolition of the temporary walkway structure with a 706 calendar-day performance period. Line Item 5 is an optional item covering trailer lease and removal for a 6-month/180-day period and will not be awarded with the base contract; the option year pricing applies if FAR clause 52.217-8 is exercised. The award will be made on Line Items 1 and 2 if funds are available, otherwise sequentially on Items 1 and 3, then 1 and 4, based on available funding.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTINUATION OF SF 1442 BLOCK # 17 CONTINUED

REVISED PRICE SHEET

DESCRIPTION OF WORK: Contractor shall furnish all supervision, labor, material, tools, and equipment to Renovate Sterile Processing Service (SPS) as specified herein at the Veterans’ Health Care System of the Ozarks located at 1100 North College Avenue, Fayetteville, Arkansas 72703. All work shall be performed in accordance with the project plans and specifications.

BASIS OF AWARD: A single award will be made on Line Item 1 and 2, but in the event the offer exceeds the funds available, a single award will be made on Line-Items No. 1 and 3, Line-item No. 1 and 4, in that order, based on available funding. Offerors shall provide a total contract price on each line item listed. The project’s period of performance is reflected in each line item. Line-Item 5 is an option and will not be awarded with the base contract.

LINE-ITEM NO.1: Includes all work as indicated in the drawings and the specifications including the lease of a trailer, including delivery, for Renovate SPS, VHSO. The trailer’s period of performance is 12 months.

TOTAL NO.1: $______________________________

TOTAL NO.1 Lease Trailer cost per month $__________________________/month.

LINE-ITEM NO. 2: Includes all work as indicated on the drawings and the specifications for the Renovate SPS at VHSO. The project period of performance is 720 calendar days.

TOTAL NO.2: $ _____________________________

*Offeror shall complete a price breakdown by Specification Divisions as shown on page #5.

LINE-ITEM NO.3: Alternate #1- Includes all work as indicated on the drawings and specifications except deleting all work associated with demolition of concrete pads and supporting exterior work for mobile SPS and Logistics Trailers. The project period of performance is 720 calendar days.

TOTAL NO. 3 (Base- Alternate 1): $_____________________________

LINE-ITEM NO. 4: Alternate #2- Includes all work as indicated on the drawings and specifications except the items listed in line item #3 and deletes all work associated with the demolition of the new, temporary walkway structure leading from the existing, enclosed, permanent walkway to the mobile SPS and Logistics Trailers. The project period of performance is 706 calendar days.

TOTAL NO.4 (Base- (Alternate 1 + Alternate 2): $____________________________

LINE-ITEM NO. 5: (Option) Includes all work as indicated in the drawings and specifications regarding the lease of a trailer, including removal, for Renovate SPS at VHSO. The lease option period of performance is 6 months/180 days. Note: Line-Item No.5 is an option and will not be awarded in the base contract.

TOTAL NO. 5 Lease Trailer costs per month $__________________________/month.

*The option year pricing shall also be used if the options clause 52.217-8 is exercised.