This document is an Infection Control Risk Assessment (ICRA) that outlines the precautions required for a Class III construction/remodel project for the Mammography Site Prep project at the Overton Brooks VA Medical Center.
The key requirements during construction include sealing unused doors, blocking and sealing air vents, placing dust mats, removing or isolating the HVAC system, implementing full containment barriers, maintaining negative air pressure, and following specific waste handling procedures. Upon project completion, the requirements include wiping work surfaces, handling waste, restoring the HVAC system, and scheduling a terminal clean. All control measures must be maintained until the work is fully completed, with any exceptions requiring Infection Prevention approval. The related federal contract opportunity is Solicitation 36C25624R0098 for the Mammography Site Prep project under VA Project #667-24-155, issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Overton Brooks VAMC Infection Control Precautions for Class III Projects Based on the Infection Control Risk Assessment of this construction/remodel project, the following activities are required.
Project: Mammography Site Prep 667-24-155 During Construction Project: Upon Completion of Project:
| Class III |
| 1. Seal unused doors with duct tape. |
2. Block off and seal air vents if the HVAC system is removed or isolated.
3. Place dust mat at entrance and exit of work area
4. Remove or Isolate HVAC system in area where work is being done if required to prevent contamination of adjacent areas.
5. Complete all critical barriers i.e. sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering and sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.
6. Maintain negative air pressure within work site with filtration and pressure monitoring. Utilize HEPA equipped air filtration units if air is recirculated within the building.
7. Construction Waste
a. Transport in tightly covered container,
b. Containers without tight fitting solid lids must have covering taped in place BEFORE transport outside the project area,
c. Outside of containers must be cleaned when visibly soiled
8. When removing construction debris, utilize only the designated construction route.
9. Minimize construction worker traffic within the facility.
1. Wipe work surfaces with cleaner/disinfectant.
2. Handle construction waste the same as during construction.
3. Do not remove barriers from work area until completed project is inspected by Engineering Service, Infection Prevention and the area is thoroughly cleaned.
4. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.
5. Wet mop area with cleaner/disinfectant.
6. Upon completion, restore HVAC system where work was performed.
7. Schedule EMS Terminal Clean once all is complete.
· Maintain control measures until ALL Work is completed. Exceptions must be approved by Infection Prevention on a case by case basis.
· Lined items are deleted from these precautions due to the nature of the work being performed outdoors.