EXHIBIT A PERFORMANCE RELEVANCY SURVEY (1).docx
DOCX document 43 KB Posted
- Attached to
- Project No. 667-18-110, Replace Transformer and Correct Electrical Deficiencies, Bldg 4 Federal contract opportunity
- Solicitation number
- 36C25622R0028
About this file
This document package includes an exhibit for evaluating past performance references related to a federal contract opportunity for replacing a transformer and correcting electrical deficiencies. The opportunity is a 100% set-aside for service-disabled veteran-owned small businesses issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16. Offerors must be verified through the Vendor Information Pages database and registered in the System for Award Management. The solicitation number is 36C25622R0028 with proposals due around February 18, 2022 for a project replacing a transformer and correcting electrical deficiencies at the Overton Brooks VA Medical Center in Shreveport, Louisiana. The contract performance period is 180 calendar days with a construction cost range between $500,000 and $1,000,000. The exhibit includes questions for references and information on past performance for the past five years while the opportunity details work scope, site location, and registration requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25622R0028 0001.docx | DOCX document | |
| Bldg 4 Transformer Laydown Area.pdf | ||
| 36C25622R0028 0002.docx | DOCX document | |
| FCA Basic Report - B4 Electrical.pdf | ||
| RFIs - Bldg 4 Transformer - Shreveport VA.docx | DOCX document | |
| 36C25622R0028.docx | DOCX document | |
| EXHIBIT E SURETY FORM.docx | DOCX document | |
| DRWGS - Replace XFMR and Correct Elec Def B-4.pdf | ||
| Building 4 Transformer Class II Precautions Final.docx | DOCX document | |
| Building 4 Transformer ICRA Final.docx | DOCX document | |
| SPECS - Replace XFMR and Correct Elec Def B-4.pdf | ||
| Exhibit B Past and Present Performance Questionnaire.docx | DOCX document | |
| SOW - Replace XFMR and Correct Elec Def B-4.pdf | ||
| EXHIBIT D CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY v2.docx | DOCX document | |
| EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT.docx | DOCX document | |
| 36C25622R0028- Presolicitation Notice.docx | DOCX document |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOR OFFICIAL USE ONLY
Source Selection Sensitive Information—See FAR 2.101 & 3.104 36C25622R0028 Building 4 Replace Transformer
EXHIBIT A
PERFORMANCE RELEVANCY SURVEY
Offeror Name/Company
PART 1. CONTRACT REFERENCES: Provide the following information requested in this format for each of the projects/contracts you intend to have considered for evaluation. Projects shall have been completed no more than 5 years prior to the solicitation issue date. Provide all information requested regarding YOUR PERFORMANCE on the contracts you elect to reference.
Project Submittal #___________________ (NOTE: Offerors allowed NO MORE than 5 projects- offerors to make appropriate copies) Project/Contract Title: ________________________________ Contract Number/Task Order Number:_______________________ Location of Project:__________________________________ Description of Effort as Prime ( ) or Subcontractor ( ) Original Contract Value: $________________________ Current/completed Contract Value: $_________________________ Was project completed on time: Yes ( ) No ( ) Start date: ___________________ End date:_________________ Reason for delay if applicable:__________________________________________________ Any liquidated damages: Yes ( ) No ( ) CPARS available: Yes ( ) No ( ) (NOTE: Offeror can provide CPARS with proposal; however, the questionnaire has more detailed questions.)
Provide detailed description of the work performed under the contract and describe why you believe the work is VERY REVELANT, RELEVANT, or SEMI-RELEVANT. (Circle one)
Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Relevance detailed description of project to include work by subcontractors:
Point of Contact of Reference on project (who you are sending questionnaire/survey to):
Name: ________________________ Title: ________________________ Agency: ________________________ Email: ________________________ Phone: ________________________ POTENTIAL OFFERORS: IT IS YOUR RESPONSIBILITY TO FOLLOW-UP WITH YOUR REFERENCES IN SUBMITTING QUESTIONNAIRES PRIOR TO THE CLOSE OF THE SOLICITATION.
PART 2. NOT RELATED TO PART 1: Additional offeror information required, but not project specific. THIS INFORMATION NEED ONLY BE PROVIDED ONCE IN YOUR SUBMISSION PACKAGE.
Offeror representative providing the below information:_______________________
1. Provide information regarding the assessment of liquidated damages on any contracts within the last five years. (Frequency, circumstances, severity of problem, etc.)
2. Offerors are strongly encouraged to include with their proposals information on problems encountered on any relevant projects and the specific corrective actions taken to remedy the problems. Furthermore, please provide explanation of any marginal ratings in CPARS if applicable:
3. Other Past Performance Considerations. Information provided shall be limited to the period starting five years prior to the solicitation release date and may include the following:
a. Professional/Industry awards (Identify award type, date of award and copy of certificate if applicable), Letters of appreciation, recognition or commendations
b. Discuss unique skills and accomplishments (Explain unique skills and/or accomplishments and provide supporting information for verification).
4. Address any technical areas about this project you consider uniquely relevant to this solicitation.
· Descriptions must address the following:
· Describe the specific elements of the work performed by your firm.
· Indicate what elements of work were performed by your major subcontractors and indicate if those same subcontractors will be used on this project.