Building 4 Transformer Class II Precautions Final.docx

DOCX document 25 KB Posted

Attached to
Project No. 667-18-110, Replace Transformer and Correct Electrical Deficiencies, Bldg 4 Federal contract opportunity
Solicitation number
36C25622R0028
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16

About this file

This document outlines requirements for a federal construction contract opportunity to replace a transformer and correct electrical deficiencies at a Department of Veterans Affairs medical center. The solicitation will be issued as a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses through request for proposal procedures. Interested offerors must be registered and verified in the Vendor Information Pages and System for Award Management databases. The construction cost is estimated between $500,000 and $1 million. The performance period is 180 calendar days after notice to proceed. Proposals are due around February 18, 2022 for work located at the Overton Brooks VA Medical Center in Shreveport, Louisiana. NAICS code 236220 applies. The first section provides infection control precautions that must be followed during and after the construction project.

View the file

Other files for this federal contract opportunity

Other files attached to Project No. 667-18-110, Replace Transformer and Correct Electrical Deficiencies, Bldg 4, newest first.
File Type Posted
36C25622R0028 0001.docx DOCX document
Bldg 4 Transformer Laydown Area.pdf PDF
36C25622R0028 0002.docx DOCX document
FCA Basic Report - B4 Electrical.pdf PDF
RFIs - Bldg 4 Transformer - Shreveport VA.docx DOCX document
36C25622R0028.docx DOCX document
EXHIBIT E SURETY FORM.docx DOCX document
SPECS - Replace XFMR and Correct Elec Def B-4.pdf PDF
Exhibit B Past and Present Performance Questionnaire.docx DOCX document
DRWGS - Replace XFMR and Correct Elec Def B-4.pdf PDF
Building 4 Transformer ICRA Final.docx DOCX document
SOW - Replace XFMR and Correct Elec Def B-4.pdf PDF
EXHIBIT A PERFORMANCE RELEVANCY SURVEY (1).docx DOCX document
EXHIBIT D CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY v2.docx DOCX document
EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT.docx DOCX document
36C25622R0028- Presolicitation Notice.docx DOCX document
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overton Brooks VAMC Infection Control Precautions for Class II Projects

Based on the Infection Control Risk Assessment of this construction/remodel project, the following activities are required.

PROJECT: Building 4 Transformer 667-18-110

During Construction ProjectUpon Completion of Project
Class II
1. Provide active means to reduce airborne dust from dispersing into atmosphere.

2. Water mist work surfaces to control dust while cutting.

3. Seal unused doors with duct tape.

4. Block off and seal air vents if the HVAC system is removed or isolated.

5. Place dust mat at entrance and exit of work area

6. Remove or isolate HVAC system in areas where work is being performed if required to prevent contamination of adjacent areas.

7. Construction Waste

a. Transport in tightly covered container,

b. Containers without tight fitting solid lids must have covering taped in place BEFORE transport outside the project area,

c. Outside of containers must be cleaned when visibly soiled

8. When removing construction debris, utilize only the designated construction route.

1. Wipe work surfaces with cleaner/disinfectant.

2. Contain and transport construction waste as outline for “During Construction”.

3. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.

4. Upon completion, restore HVAC system where work was performed.

5. Schedule Terminal Clean once work is complete

Maintain control measures until ALL Work is completed. Exceptions must be approved by Infection Prevention on a case by case basis.

Preliminary Final image1.emf image2.emf

File details come from the government source that posted it. Updated .