This document outlines requirements for a federal contract to renovate and expand cath lab services at a Veterans Affairs medical center. The scope of work includes renovating approximately 8,279 square feet in multiple phases over 808 calendar days. Interested offerors must be verified as service-disabled veteran-owned small businesses. The pre-solicitation provides details on procurement procedures, the anticipated schedule for issuing the request for proposals in August 2021 with proposals due in September, and an expected award date within 30 days thereafter. Offerors are advised to check the System for Award Management website for any amendments to the solicitation.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CATH LAB EXPANSION 6-EAST
Project #667-15-104 Statement of Work
Contractor shall provide all labor, materials, and equipment necessary to renovate and expand CATH Lab services on 6-East main hospital, Building 1, Overton Brooks VAMC, Shreveport, LA. The total area to be renovated is approximately 8,279 square feet. All work shall be in accordance with the project construction plans and specification (stamped 4-15-2021) and current applicable code requirements.
PERIOD OF PERFORMANCE: 808 Calendar Days
PROJECT PHASING:
Reference Phasing drawing sheet 1-GI-103.
Contractor will give the VA a 30-Day advance notice that they are ready to start the Phase I work. The VA will have 30 days to vacate the Phase I area, then Notice-to-Proceed (NTP) will be issued. This project will be phased in accordance with the following durations and timeframes:
| CATH LAB CONSTRUCTION |
| PHASE DURATION (Calendar Days) |
NTP ISSUED
| Phase I - Contractor Renovate Phase I Area (Nurse Station & Tunnel) |
| 180 |
| VA Vacate Phase II Area & Occupy Phase I Area |
| 14 |
| Phase II - Contractor Renovate Phase II Area (1st New CATH Lab) |
| 240 |
| Phase III - VA has Phillips Install 1st New CATH Lab in Phase II Area |
| 60 |
| VA Vacate Phase IV Area & Occupy Phase II Area |
| 14 |
| Phase IV - Contractor Renovate Phase IV Area (2nd New CATH Lab) |
| 240 |
| Phase V - VA has Phillips Install 2nd New CATH Lab |
| 60 |
| TOTAL PROJECT DURATION = |
| 808 |
Note: Contractor shall be available during Phase III and Phase V, while the VA has Phillips install each of the new CATH Lab equipment for any required coordination efforts.
WORK HOURS: Reference Phasing drawing for work hours for each phase.
CONTRACTOR ACCESS: Reference Infection Control drawing sheets 1-GI-111, 1-GI-112 & 1-GI-113 for contractor access to each of the phases. Contractor to provide exterior lift as annotated on the plans.
Per ISSO: The C&A requirements do not apply, and that a Security Accreditation Package is not required