This document outlines requirements for a federal construction contract opportunity with the Department of Veterans Affairs. The Overton Brooks VA Medical Center is seeking proposals to renovate and expand its cardiac catheterization lab for a project estimated between $2 million to $5 million. The solicitation will be issued as a 100% set-aside for service-disabled veteran-owned small businesses. Interested offerors must be verified in the Vendor Information Pages database and registered in the System for Award Management by the September 1, 2021 proposal deadline in order to be considered for the anticipated September award and 808-day performance period. The renovation scope of work will be detailed in the solicitation to be posted on beta.SAM on or around August 2, 2021.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Description of Interim Life Safety Measures (ILSM) Used
Project #: _667-15-104____ Title: Renovate Cardiac Catherization Lab Date: April 28, 2021
Based on the responses to the evaluation questions, provide a description of the ILSM that will be implemented during the project to compensate for the deficiency or condition. Attach additional sheets if necessary.
-If the contractor has to block an exit, they will hang signage at each location on the floor that directs traffic towards an exit, using a sign stating, “No Exit Due to Construction,” adding directional signage to the next nearest exit, and covering corridor exit signs. The contractor will remove this signage after removing temporary barriers. At no time, will stairwell egress be blocked, without prior notice to COR and Safety Department.
-A corridor width of 44” shall be maintained at all times for patient care and transport.
-When generating dust, the contractor will tape and bag the smoke detectors within the area under construction. The tape and bags will be removed when workers are not present during construction, ie. at night. The boiler plant operator will deactivate and reactivate the smoke detection system to avoid unnecessary alarms as required.
-Fire sprinklers will be turned up and the heads replaced with correct upright pendant heads. Fire system will be de-energized and re-energized each day on the floor during the time the sprinkler heads and pendants are being changed. These outages will be coordinated through the Safety Department.
-Any Life Safety fire detection/alarm section out of service for greater than 4 hours in a 10-hour period, will require a fire watch.
All asbestos and hazardous materials remediation will be covered under a separate ILSM.
Signatures required as indicated below. Completed form will be maintained in the project file.
Project COR: __________________________________ Date: _____________
Reviewers:
1. Safety Manager: _______________________________ Date: _____________
2. Chief Engineer: ____________________________ Date: ____________
| 2021-04-29T12:51:09-0500 | |
| PAUL M. CELLI 3377041 |
| 2021-04-30T08:16:55-0500 | |
| STACY M. WALDEN 244989 |
| 2021-04-30T08:31:38-0500 | |
| Amanda P Johnson 1073816 |
File details come from the government source that posted it. Updated .