This document is Amendment 0001 to Solicitation 36C25526R0142 issued by the Department of Veterans Affairs Network Contracting Office (NCO) 15 in Leavenworth, Kansas for Project 589A7-25-503, "Prepare Site for Cath Lab Equipment." The amendment was effective August 20, 2026, and extends the offer due date from August 24, 2026 to August 31, 2026 at 5:00 p.m. Central Time. The amendment publishes revised drawings, a sign-in roster from the site visit, and responses to 59 questions submitted by potential offerors. Offerors must acknowledge receipt of this amendment prior to the submission deadline, with failure to do so potentially resulting in rejection of their offer. All previously published drawings are disregarded in favor of the revised versions.

The questions and responses address critical project requirements including: site visit attendance (highly recommended but not required); CLIN structure (additional CLINs are deducts, not additive); bid guarantee requirements (20% of bid price or $3,000,000, whichever is less); limitations on subcontracting for certified SDVOSBs; construction schedule specifications covering phasing, submittals, mobilization, demolition, construction, equipment deliveries, installation, punch list, and de-mobilization within a 365-calendar-day performance period; HVAC air change requirements (20 AC/HR supply, 4 AC/HR outside air); infection control barrier installation requirements; temporary cooling unit provisioning; floor leveling and cove flooring specifications; structural modifications limited to non-structural MEP component bracing; preliminary TAB (Testing, Adjusting, and Balancing) requirements; and fire suppression main modifications. The amendment confirms no delegated design engineering, qualified radiological physicist, or fire alarm reprogramming is required; existing signage is to remain; and final sequencing and means and methods are the contractor's responsibility. Updated Philips vendor drawings and a site visit sign-in roster are referenced as attached documents.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 2

0001 08-20-2026

589A7-25-503

36C255

Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway

Leavenworth KS 66048

36C255

Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway

Leavenworth KS 66048

To all Offerors/Bidders

36C25526R0142

07-22-2026

X

X X

X 1

The purpose of this amendment is to publish revised drawings, sign in roster from site visit, and responses to questions submitted to this solicitation. The due date is changed from August 24, 2026 to August 31, 2026 at 5:00pm Central Time.

This is pertaining to project 589A7-25-503 Prepare Site for Cath Lab Equipment.

Disregard all previously published drawings. All other requirements remain unchanged.

Failure to acknowledge any and all Amendments issued pursuant to this solicitation may be cause for rejection of the offer.

Jennifer Hill Contracting Officer NCO 15

August 20, 2026 Site Visit Questions and Responses

1. Whether attendance at the July 31 site visit is a condition of proposal eligibility.

The attendance at the site visit was highly recommended but not required

2. Whether the five CLINs are additive items, options, or separately funded portions of the work.

There are not five CLINS with this project. The additional CLINS are deducts.

3. Which CLINs are presently funded and whether award may be made for fewer than all five.

This project is funded.

4. The exact bid-bond amount and acceptable delivery method for the original bond.

Bid guarantee shall be 20 % percent of the bid price or $3,000,000 whichever is less.

5. Whether a first-tier Vet-Cert SDVOSB general contractor may be treated as a similarly situated entity for the limitation-on-subcontracting calculation.

For the purpose of limitations on subcontracting, only certified SDVOSBs listed in the SBA certification database (including independent contractors) shall be considered eligible and/or ‘‘similarly situated’’ (i.e., a firm that has the same small business program status as the prime contractor). An otherwise eligible firm further agrees to comply with the required LOS certification requirements in this solicitation.

6. Whether the Government will accept the partner’s directly relevant cath-lab, occupied-hospital, infection-control, hazardous-material-abatement, and medical-equipment site-preparation experience when clearly attributed.

Please refer to the evaluation factors.

7. Whether shutdowns, infection-control barriers, hazardous-material abatement, shielding work, and after-hours activities are fully shown in the drawings and specifications or will be further clarified by amendment.

Specs and drawings are complete.

8. Whether the stated 365-calendar-day performance period includes submittal approval, long-lead equipment procurement, construction, commissioning, and closeout.

Each Offeror's construction schedule must address the following:

• Order of work elements to include project phasing, Submittals, Mobilization, Demolition, Construction, Equipment Deliveries and Lead Time, Installation of new Equipment, Punch List, De-Mobilization.

• Temporary Trailer Rental

• Number of days for each work element

• Identification of long lead time materials

• Identification of separate work elements

• The VA’s review and approval or RFI’s, Submittals and other pertinent documents.

• Interruption of VA Facilities utilities, delivery of Government furnished equipment, rough-in drawings, project phasing and any other specification requirements.

The proposed schedule must include the activities which are consistent with those described within the project specifications and drawings and must not exceed the Government's maximum allowable performance period, as noted in Block 11 of the SF 1442. The project will start at the issuance of the Notice to Proceed. For scheduling purposes, assume the Notice to Proceed will be issued thirty (30) calendar days after the award date. (Note that there is no guarantee that the Notice to Proceed will be issued within this timeframe.)

9. Is the price breakdown and calculation of self-performed/subcontract work get submitted with the bid or after award?

This is submitted with the bid.

10. Request Asbestos report on construction area to confirm no hazardous materials are within project area.

VA possesses previous renovation and asbestos testing reports for this scope area, no asbestos is expected to be present due to previous renovations and clearance tests. Documents are available via COR request.

11. Request Tri-Hat is acceptable opposed to individual Superintendent, Safety Officer, &

QC Officer.

Tri‑Hat staffing is not acceptable. VA standards require three separate, qualified individuals to serve in each role.

12. Request engineered structural drawings pertaining to the project.

Structural Unistrut modification plan and details are provided on sheet SF-101. No modification to the existing structure is a part of this scope, other than non-structural/MEP component bracing and Unistrut support modifications to accommodate new cath equipment.

13. Request to provide a 10–15-line-item preliminary schedule opposed to a full schedule per the RFP.

See factor two for project schedule requirements.

14. Request latest version of Philips site-specific drawings.

Philips drawings will be uploaded as a part of the drawing package as an attachment file.

15. Request to waive floor slab leveling requirement due to the new flooring is a patch only.

a. If leveling the floor slab is required, suggest replacing the entire room flooring to ensure a ramp will not occur between the existing floor and the new floor patch.

No waivers for floor leveling requirements. The extents delineated are required for equipment functionality and cannot be waived. The levelness is achievable.

16. Is the GC to provide any assistance in existing/new equipment removal, delivery, load/unload, storage, or handling from or into the site? If so, what are the requirements?

Existing equipment to be removed by Philips.

17. Will the owner or Philips layout anchor positions and/or provide a full size layout template?

No, the Owner nor Philips will layout anchor positions. Philips will provide a full-size template.

18. Is there an alternate anchorage method if ‘through bolts’ land at an inaccessible location?

See SF101 for bolt options detail

19. Will door frames with hospital stops be accepted as fire rated if determined so by manufacturer?

Not applicable. There are no fire rated doors as part of this project.

To clarify, the equipment room and supply room doors, should be full stop frames.

20. Division 13 49 00 1.5H – Are delegated design drawings and calculations (signed and sealed) required, or will the contract document design be acceptable for lead lined construction?

Construction documents cover the information needed, no new delegated design required.

21. It was noted during the pre-bid site visit that ‘no’ designated engineering will be required (on the part of the GC or trade partners) for any/all structural components related to this project. Is this correct?

Correct

22. It was noted during the pre-bid site visit that ‘no’ Qualified Radiological Physicist will be required as part of the GC’s scope. Is this correct?

Correct

23. Division 13 Radiation Protection has multiple signage requirements not identified in solicitation drawings, are all signs shown in Division 13 required?

The existing signage is to remain, no new signage to be provided by General Contractor scope of work.

24. Will preliminary TAB be required?

Yes, preliminary TAB is required to measure the existing supply and return air quantities from the existing air handling unit.

25. Who is responsible for performing the smoke test at the end of the project, 3rd party (VA or AE supplied) commissioning agent or mechanical contractor?

The Mechanical Contractor is to provide the smoke test on the mechanical equipment.

26. Is Philips above ceiling support system projected to interfere with the mechanical duct, register, or grills?

No, the design was coordinated to avoid these conflicts.

27. What is the access for FCU into the attic space?

To be coordinated with VA COR. Through the Recovery, into Mechiancal access and up to Attic via a ladder and hoistway. A roof access door is present located at the base of the ladder in the hoistway.

28. What is the duration the equipment room can go without cooling during equipment (FCU) and/or duct changeout?

Will depend on the use of the equipment during this change over. To be coordinated with VA COR at the time of construction. GC should plan to provide a temp unit for cooling during this change over. Size for 6,000 BTUs.

29. Do the VAV controllers and existing thermostat(s) need to be replaced? They are likely 20+ years old.

Not in scope.

30. Provided TAB is a requirement, to what extent of the existing HVAC system, outlet – inlet locations are to be balanced?

TAB the existing-to-remain supply and return diffusers, grilles & registers shown on MH- 101 to the air quantities measured at the pre-construction TAB after the construction is complete.

31. Provided TAB is a requirement, is there an adequate adjustment in the existing system to accommodate possible changes?

It is assumed at this point that the existing air handling unit will be adjustable during the final phase of TAB.

32. What is the air change per hour requirements for both Cath Labs?

The AC/HR requirement for both Cath Labs is 20 for supply, 4 for outside air from the existing AHU.

33. No fire suppression drawings have been identified in the solicitation documents. The architect mentioned the fire main would need to be raised during construction to allow for new equipment install requirements. Our understanding is that the fire main feed is from the west which would be the final phase of construction. If we are understanding correctly, this would require multiple fire suppression and fire alarm outages throughout construction, do you concur?

The floor main will need to be shut off to allow installation of valves at the two branch mains west of lab 1 prior to the line height change, to allow the floor main to be open while performing the remainder of the work above the scope area.

34. Please confirm that all ‘removable movable’ equipment, shelving, etc. will be removed prior to the start of construction at each phase.

Confirmed.

35. What are the MEP requirements needed prior to existing Cath Lab equipment removal?

N/A

36. Will Philips ‘grid load ratings’ and contractors ‘means & methods’ be reviewed by the A/E – VA team as final approval for installation?

No.

37. Will any/all portable/temporary medical gas requirements needed be supplied and distributed by the VA?

Yes.

38. It was noted during the pre-bid site visit that infectious control – negative air access for venting through the attic could be utilized during construction. Is this access expected to be available through all phases/areas of construction including phase 1?

Yes.

39. Will a crane ‘lift plan’ be required for staging the equipment on the roof?

Yes.

40. Will the required work at the medical gas zone valve boxes require additional infectious control containment?

Yes.

41. Will the required work at the medical gas zone valve boxes require additional gyp removal/replacement along with finishes to box location wall?

Yes. The extent dependent upon provided box.

42. We believe replacement of Clean Utility room 217A-2 door will likely require additional infectious control containment outside of the room for door demo, and frame installation. Please revise phasing requirements - provided the VA team concurs.

The minimum amount of room needed is what will be granted. Actual barrier locations to be submitted for review prior to the start of construction. See notes on 02-GI-100

43. We believe replacement of Clean Utility room 217A-2 door will likely require gypsum demolition and replacement inside and outside of the room for door demo, and frame installation. Please define demo & finish requirements at 217-2 and 217A-2 walls.

Demo: minimize adjacent disturbances to existing conditions.

Finish to be level 4 and appropriate paint per Specification 09 91 00. Paint per 02-AF-701.

44. We believe replacement of Clean Utility room 217A-2 door will likely require floor replacement/patch inside and outside of the room for door demo, and frame installation. Please define floor finish requirements at 217-2 and 217A-2 walls – to include coved flooring requirements.

Information is added to the architectural drawings for considerations regarding patching and material matching.

45. We believe replacement of Equipment room 216A-2 doors (217A-2 & 217A-2B) will likely require additional gypsum removal, replacement, finishes, along with floor/cove patch/replacement at these locations. Please define extent of ‘finishes’ required at these locations?

Information is added to the architectural drawings for considerations regarding patching and material matching.

46. It was noted during the pre-bid site visit that no fire alarm programming/reprogramming will be required, please verify.

Confirmed, only line height modifications over scope area, and relocation of few sprinklers to accommodate ceiling layout changes in cath labs.

47. Will any ceiling access panels be required?

No.

48. Several ‘existing’ vinyl floor welds were identified as deteriorated during the site visit, will repair of existing flooring be expected as part of the construction requirements?

Yes.

49. Per drawing 02-GI-101 - Control Room 217-2, infectious control barriers are to be installed as split across the room. How is infectious control integrity expected to be maintained above ceiling between construction zone and non-construction zone during hard ceiling demolition?

As noted on 02-GI-100.

The infection control barrier should extend above the ceiling as indicated in detail 5/ 02-

GI-100.

50. Per drawing 02-GI-101 - Control Room 217-2, infectious control barriers are to be installed as split across the room. How are final finishes expected to be completed across the control barrier dividing line? I.E. mud/tape, paint.

As noted on 02-GI-100

Final sequencing of construction and means and methods for completion of fully functional and completed project is the responsibility of the contractor.

51. Per drawing 02-EL-101 - Control Room 217-2, infectious control barriers are to be installed as split across the room. How are lighting/HVAC registers - demolition and installation - to be completed while crossing two phases of construction?

General Contractor to coordinate across their proposed phasing.

52. Wall mounted bumper rails were identified during the site visit, what are the requirements for removal/replacement?

There are no bumper rails in the scope of work. The existing bumper rails are in Corridor C-2-3 are to remain and the extent of new work in that corridor is minimal. No bumper rails are expected to be modified unless damaged during construction.

53. Per demo drawing D1/02-AD-100, remove ceiling tiles – what are the infectious control requirements for this area during construction?

A cart containment option may be acceptable. To be coordinated with VA COR and VA Infection Control Team prior to the start of construction.

54. Per demo drawing D1/02-AD-100, remove ceiling tiles – will full tile replacement be expected?

Per Note D1: REMOVE EXISTING CEILING TILES FOR ACCESS TO COMPLETE SCOPE

OF WORK ABOVE FIRST FLOOR CEILING AND BELOW SECOND FLOOR SLAB.

REPLACE ALL HOLD DOWN CLIPS THAT ARE DAMAGED IN THE REMOVAL OF CEILING

TILES. TYPICAL.

If any tiles are damaged in the process of removal, full replacement is expected.

55. Drawing 02-AE-103 indicates a new ceiling elevation above previous elevation. Are perimeter walls expected to have gyp installation to deck, or will additional wall finishes be required?

The perimeter walls have been confirmed to extend to the deck above.

56. Is the new mechanical equipment designed to handle additional square footage added to the Cath Lab rooms due to ceiling elevation change?

Yes.

57. Please provide vendor (Philips) drawings.

Updated Philips Drawings will be uploaded as a separate file and provided to bidders.

58. Please provide structural drawings for Philips grid installation and floor mounting equipment.

See sheet SF-101

59. Please provide fire suppression drawings.

See sheet FP-101

See attached document: Updated Drawings-589A7-25-503.

See attached document: Sign in Roster-589A7-25-503-Cath Lab.