36C25524R0096 0001.docx
DOCX document 18 KB Posted
- Attached to
- Z1DA--657-23-115JB Correct Campus Steam System Failures, JB Federal contract opportunity
- Solicitation number
- 36C25524R0096
About this file
This document is an amendment to Solicitation 36C25524R0096, which is for construction services to correct campus steam system failures at the Jefferson Barracks Division of the St. Louis VA Medical Center in St. Louis, MO. The amendment extends the solicitation period until August 19, 2024 at 2:00 PM and publishes questions, an updated Basis of Design, a pre-construction sign-in sheet, and a pre-proposal conference site visit agenda. The scope of work includes architectural, mechanical, and electrical construction to improve steam and condensate system functionality, manhole access, safety, remote valve operation, monitoring, and compliance with VA and industry standards. The period of performance is estimated to be 180 days. This is a VA project under Project Number 657-23-115JB.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 03-17-2021
657-23-115JB
36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth
KS
66048 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth
KS
66048 To all Offerors/Bidders
36C25524R0096 07-25-2024
X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to:
Extended until 8/19/2024 @ 2:00 PM X
The above cited solicitation is hereby amended as shown below:
1- This amendment extends the solicitation until August 19, 2024 at 2:00PM
2. This amendment publishes questions and an updated Basis of Design. There will be another amendment that will publish revised documents per the note on power metering on the following sheet.
3. This amendment also publishes the Pre-Construction Sign-in Sheet and Preproposal Conference Site Visit Agenda.
All other terms and conditions remain the same.
Jennifer Hill Contracting Officer Current design drawing E-702 (page 58 of 58) General Note #2, dated 04 April 2024, states: “PRIOR TO COMMENCING ANY WORK, CONTRACTOR SHALL CONDUCT 30-DAY DEMAND POWER METERING PER NEC 220.87 FOR ALL PANELBOARDS WITH LOAD ADDED UNDER THIS PROJECT. ALL METERING DATA SHALL BE PROVIDED VIA SUBMITTAL PROCESS TO ENGINEER FOR REVIEW; ENGINEER SHALL HAVE APPROXIMATELY 7-DAYS TO REVIEW DATA AND PROVIDE ADDITIONAL DIRECTION AND/OR APPROVE WORK TO COMMENCE AS INDICATED ON DRAWINGS.” This keynote was entered in error and will be removed from the design documents in the next design amendment.
See attached document: Contractor Pre-Bid RFI Log - 657-23-115JB - REV1.3.
See attached document: 100 BOD COMBINED - 657-23-115JB UPDATED 7.23.24.
See attached document: Pre-Construction Conference Sign-in Sheet 657-23-115.
See attached document: PreProposal Conference Site Visit Agenda 657-23-115JB.
36C25523R0026 657-21-106JB, FCA Replace Air Handling Units Buildings 52 & 53