This amendment to a federal solicitation provides changes to the requirements for a project to renovate an unfinished specialty clinic and inpatient pharmacy at a Veterans Affairs medical center. Key details include:
-
The amendment extends the proposal due date to September 1, 2021 at 2:00 PM CDT. It also provides narrative changes and drawing revisions to the statement of work. Renovations to the specialty clinic on the third floor will be conducted in one phase, while the basement pharmacy renovations will occur in multiple phases to maintain 24/7 operations.
-
The scope of work involves renovating approximately 6,490 square feet for an outpatient hematology/oncology clinic and 6,290 square feet for the main inpatient pharmacy to comply with USP compounding standards. Renovations will include exam rooms, infusion bays, support spaces, new construction, and mechanical/infrastructure upgrades on both floors. The estimated price range is $2-5 million.
-
The opportunity is set aside for service-disabled veteran-owned small businesses and issued by the VA Network Contracting Office. The NAICS code is 236220 for general construction over $39.5 million. The period of performance is up to 300 calendar days from notice to proceed.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
589A4-20-155
36C255
Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway
Leavenworth KS 66048
36C255
Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway
Leavenworth KS 66048
To all Offerors/Bidders
36C25521R0106
X
X X
September 1, 2021 by 2:00 PM CDT
Complete Unfinished Specialty Clinic, 589A4-20-155 This amendment provides the following :
a. Extends the closing due date to September 1, 2021 by 2:00 PM CDT.
b. Attached Amendment 3 narrative changes and drawing changes.
CONTINUATION PAGE
See attached document: QH102 - THIRD FLOOR EQUIPMENT PLAN.
See attached document: QH101 - BASEMENT EQUIPMENT PLAN.
589A4-20-155 Complete Unfinished Specialty Clinic
Amendment 3 – Narrative
Description of Changes:
1. Sheet QH101 - In the equipment list, item “M2050 – Shelving, Storage, 75hx36wx14d” has been change to VC (Government Furnished, Contractor Installed).
2. Sheet QH102 - In the equipment list, items “M2050 – Shelving, Storage, 75hx36wx14d” / “E0954 – Crash Cart” / “M4020 – Scale, with wheelchair ramp” have been change to VC (Government Furnished, Contractor Installed).
3. Sheet QH102 – Item “X008 – Manufactured Wall Panels” shall be purchased (furnished) the contractor and installed by the contractor.
4. The basement pharmacy construction shall be completed during normal operating hours.
However, the contractor shall need to account for some construction activities that will need to be completed during non-normal working hours. Examples include but are not limited to major utility tie ins, instances where utilities are required to be completely shut down for the construction activity, and instances where work is required out of the construction zone and will drastically effect normal work of the VA operations.