This solicitation is for project number 589A5-15-117B to perform corrective design work at the sterile processing services department of the Colmery O'Neil VA Medical Center in Topeka, Kansas. The scope of work includes modifying air handling units, supply ductwork, adding return air grilles, modifying supply and exhaust ductwork for other areas, removing abandoned HVAC components, changing sterilizers from boilers to central steam, installing a new exterior door, adding an exhaust fan, and testing and balancing the HVAC system. The estimated cost is between $1,000,000 to $5,000,000. The projected completion time from notice to proceed is 182 calendar days. The solicitation will be posted on July 30, 2021. Offerors must submit pricing and technical proposals in response.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25521R0102 Attachments
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C25521R0102
X 07-30-2021
589A5-15-117B 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway
Leavenworth KS 66048 Y Network Contracting Office (NCO) 15
3450 S 4th Street Trafficway Leavenworth KS 66048 Gislaine Dorvil 913-946-1139 Request for Proposal for project 589A5-15-117B, Correct AE Design for Sterile Prosessing Services at the Topeka VA Medical Centerin Kansas
See attached Schedule, Statement of Work, Specifications and Drawings.
See site visit information below
Provide Contractor Duns Number:__________________________ Contractors working on this project are exempt from state sales tax, and a Project exemption Certificate will be issued upon award of this contract.
Note: The term offer and bid are interchangeable.
PROPOSALS ARE TO BE SUBMITTED THROUGH THE VENDOR PORTAL. To ensure timely delivery due to electronic system malfunctions the contractor shall also provide the proposal in two separate binders along with a CD of the proposal containing the technical & price information by the request due date at the NCO 15 Contracting Office 3450 S 4th St Leavenworth KS66048 The NAICS code and size standard for this project are: NAICS 236220-Commercial and Institutional Building Construction with a size standard of $39.5 million.
Site Visit: A site visit will be conducted on August 11, 2021 at 10:00 AM CST. Location: VAMC, Sunflower Conference Room B-207, Building 5, 2nd Floor, Topeka VAMC, 2200 Gage Blvd., Topeka, Kansas 66622.
Due to COVID 19, all contractors are required to wear protective face masks on site.
Facility COR: Steve Hampton (785) 350-3111 ext 52980 Contracting Officer: Gislaine Dorvil, 913-946-1139, gislaine.dorvil@va.gov
52.211-10
2:00PM
CST
09-07-2021
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway
Leavenworth KS 66048 36C255 Department of Veterans Affairs Financial Services Center http://www.fsc.va.gov/einvoice.asp
Austin TX 877-353-9791 512-460-5429
Gislaine Dorvil Contracting Officer
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| 1.3 STATEMENT OF BID ITEM(S) | 4 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 5 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 6 |
| STATEMENT OF WORK | 7 |
| TASK ORDER TERMS AND CONDITIONS | 12 |
| A.1 52.228-1 BID GUARANTEE (SEP 1996) | 12 |
| A.2 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021) | 12 |
| A.3 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 13 |
| A.4 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) (JUL 2020) (DEVIATION) | 13 |
| A.5 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018) | 17 |
| A.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 18 |
| A.7 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 19 |
| A.8 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 19 |
| PROPOSAL SUBMITTAL INSTRUCTIONS | 24 |
| CONTRACTOR CERTIFICATION REGARDING SAFETY AND ENVIRONMENTAL | 30 |
| CALCULATION OF SELF-PERFORMED/SUBCONTRACTED WORK | 31 |
1.3 STATEMENT OF BID ITEM(S)
BID ITEM 1 (BASE BID)- $
This project shall include all scope related to Relocation Sterile Processing 589A5-15-117B as communicated in the drawings and specifications. The time frame allowed for this work is 270 calendar days.
BID ITEM 2 (DEDUCT NO. 1)- $
This item includes all the work in BID ITEM 1, except: changing SPS Sterilizers from free-standing boilers to Central steam to steam generator. Work includes all labor, material, equipment, and supervision to perform the required construction work on this project needed to install new Steam to Steam generator, including required steam and condensate piping, electrical power and controls for Steam generator and infrastructure support. Infrastructure support includes supplemental structural support in crawl space to support new concrete housekeeping pad for Steam generator, demolition of abandoned AHU, removal of exterior louvers and wall for the installation of new exterior doorway and louver. The time frame for this work is 270 calendar days.
BID ITEM 3 (DEDUCT NO. 2)- $
This item includes all work in BID ITEM 2, except Remove DX System Components: Work includes all labor, material, equipment, and supervision to perform the required construction work on this project needed to remove all abandoned DX coiling components , including refrigerant lines, exterior condensing unit, and electrical power. The time frame for this work is 270 calendar days.
BID ITEM 4 (DEDUCT NO. 3)- $
This item includes all work in BID ITEM 3, except delete new ceiling suspended fan coil unit and related work. This work includes all labor, material, equipment, and supervision to install new ceiling suspended chilled water fan coil unit, associated chilled water lines, controls, and electrical power. The time frame for this work is 270 calendar days.
Page 1 of Page 1 of
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
36C25521R0102
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
Page 1 of
Page 1 of
STATEMENT OF WORK
COLMERY ONEIL VA MEDICAL CENTER
TOPEKA, KANSAS
SPS STATEMENT of WORK Project # 589A5-15-117B
(SOW) CONSTRUCTION
I. SCOPE:
This specification herein describes a construction project modification SOW. This work includes the following items:
· AHU Cooling Replacement
· CAV-3 Ductwork Modification
· Add Return Grill in Vestibule B011
· Cartwash Ductwork Modification
· Remove DX System
· Change SPS Sterilizers from free standing boilers to central steam
· Install new Chilled Water Fan Coil Cooling for Mech Room Conditioning
· Install New Exterior HM Doorway
· Install N+1 Exhaust Fan Addition
· Test and Balance System
The contractor shall provide all equipment, materials and labor to complete the above items. The contractor will be responsible for meeting all contract specifications for the VAMC. The contractor shall provide all labor, material, and equipment to perform the work. All installation details shall be fully coordinated with VA CO and on-site Contracting Officer’s Representative (COR). Period of Performance is 270 days.
2. STATEMENT OF WORK:
2.1 AHU Cooling Replacement
2.1.1 The contractor shall provide pricing for all labor, materials and equipment to modify existing AHU, including changing cooling coil from DX to central plant chilled water, including piping, power, and control systems, as indicated on the revised drawings.
2.1.2 The contractor shall provide pricing for all labor, materials and equipment to install new chilled water piping, valving, pumps, and controls as indicated on the revised drawings.
2.1.3 The contractor shall provide pricing for all labor, materials and equipment to remove and replace of all existing architectural finishes as required to complete the work properly. Replacement finishes, if needed, shall match adjacent construction.
2.2 CAV-3 Ductwork Modification
2.2.1 The contractor shall provide pricing for all labor, materials and equipment to modify supply ductwork to CAV-3 as indicated on the drawings, including installation of new fire dampers. Remove and seal previous supply duct penetrations.
2.2.2 The contractor shall provide pricing for all labor, materials and equipment to remove and replace all existing architectural finishes as required to complete the work properly. Replacement finishes, if needed, shall match adjacent construction.
2.3 Add Return Grill in Vestibule B011
2.3.1 The contractor shall provide pricing for all labor, materials and equipment to add return air grilled in vestibule B011 as indicated on the drawings, including tap into the existing exhaust duct.
2.3.2 The contractor shall provide pricing for all labor, materials and equipment to include removal and replacement of all existing architectural finishes as required to complete the work properly. Replacement finishes, if needed, shall match adjacent construction.
2.4 Cart Wash Ductwork Modification
2.4.1 The contractor shall provide pricing for all labor, materials and equipment to modify supply and exhaust ductwork to Cart Wash as indicated on the drawings, including installation of new dampers and controls.
2.4.2 The contractor shall provide a credit for all labor, materials and equipment to include removal and replacement of all existing architectural finishes as required to complete the work properly. Replacement finishes, if needed, shall match adjacent construction.
2.5 Remove DX System
2.5.1 The contractor shall provide pricing for all labor, materials and equipment to remove all abandoned DX coil and components, including refrigerant lines, exterior condensing units, and electrical power and controls.
2.5.2 The contractor shall provide pricing for all labor, materials and equipment to include removal and replacement of all existing architectural finishes as required to complete the work properly. Replacement finishes, if needed, shall match adjacent construction.
2.6 Change SPS Sterilizers from free standing boilers to central steam
2.6.1 The contractor shall provide pricing for all labor, materials and equipment to modify existing steam piping to SPS sterilizers as indicated on the drawings. Work to include installation of a new steam to steam generator and piping to existing SPS sterilizers as indicated on the drawings. Work to include new steam to steam generator with manual isolation valves and steam line piping from service lines to steam generator, pipe insulation, valves, and controls systems.
2.6.2 The contractor shall provide pricing for all labor, materials and equipment to completely remove the existing AHU as indicated on the drawings. Scope of work to include removal of exterior window/louver system for delivery access of new Steam Generator.
2.6.3 The contractor shall provide pricing for all labor, materials and equipment to provide supplemental floor support and foundations per structural documents to support the installed weight of the new steam generator, including concrete housekeeping pad.
2.6.4 The contractor shall provide pricing for all labor, materials and equipment to maintain existing free-standing steam boilers to remain in-place as emergency backup, including manual by-pass valves and controls.
2.6.5 The contractor shall provide pricing for all labor, materials and equipment to include removal and replacement of all existing architectural finishes as required to complete the work properly. Replacement finishes, if needed, shall match adjacent construction.
2.7 Install new Chilled Water Fan Coil Cooling for Mech Room Conditioning
2.7.1 The contractor shall provide pricing for all labor, materials and equipment to install new ceiling-suspended fan coil cooling unit as indicated on the mechanical plans, including required chilled water piping and infrastructural support.
2.7.2 The contractor shall provide a credit for all labor, materials and equipment to include removal and replacement of all existing architectural finishes as required to complete the work properly. Replacement finishes, if needed, shall match adjacent construction.
2.8 Install New Exterior HM Doorway
2.8.1 The contractor shall provide pricing for all labor, materials and equipment to replace AHU exterior louver and lower brick wall with new insulated HM Door and frame as indicated on the drawings and painted to match existing window systems. System to be complete with all operating hardware, weather seals, and locking systems as specified.
2.8.2 The contractor shall provide pricing for all labor, materials and equipment to include removal and replacement of all existing architectural finishes as required to complete the work properly. Replacement finishes, if needed, shall match adjacent construction.
2.9 Install N+1 Exhaust Fan Addition
2.9.1 The contractor shall provide pricing for all labor, materials and equipment to revise existing rooftop exhaust fan as indicated on the Drawings, including ductwork modifications, installation of new equipment curbs, installation of a new concrete mounting platform and guard rails, installation of new single-ply roofing, including all accessories, electrical service, and fan control systems.
2.9.2 The contractor shall provide pricing for all labor, materials and equipment to work to including removal and reinstallation of the existing exhaust fan, plus new redundant exhaust fan, electrical and controls, including rigging/hoisting and scaffolding required for installation of the platform and exhaust fans.
2.9.3 The contractor shall provide pricing for all labor, materials and equipment to include removal and replacement of all existing architectural finishes as required to complete the work properly. Replacement finishes, if needed, shall match adjacent construction.
2.10 Test and Balance System
2.10.1 The contractor shall provide pricing for all labor, materials and equipment to provide full testing, adjusting, and balancing (TAB) of the HVAC system, per Specification Section 23 05 93
2.10.2 The contractor shall provide pricing for all labor, materials and equipment to schedule and coordinate TAB with the owners' 3rd party Commissioning Agent so that Commissioning Agent can witness TAB completion.
Exceptions:
36C25521R0102 Contractor shall be responsible for meeting all fire, safety and VA standards (VA handbook) as specified in Statement of Work, Drawings, and Specifications.
Page 1 of Page 1 of
TASK ORDER TERMS AND CONDITIONS
NOT SPECIFIED IN THE CONTRACT
A.1 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be percent of the bid price or , whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
A.2 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)
(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and
(2) Standard Form 28, Affidavit of Individual Surety.
(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.
(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.
(End of Provision)
A.3 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
(End of Provision) A.4 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) (JUL 2020) (DEVIATION) (a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.
(2) The small business size standard is $39.5 Million.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.204-26, Covered Telecommunications Equipment or Services—Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.
(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(x) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.
(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xvi) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.
(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.
(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)
(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xxi) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates II and III.) This provision applies to solicitations containing the clause at 52.225-3.
(A) If the acquisition value is less than $50,000, the basic provision applies.
(B) If the acquisition value is $50,000 or more but is less than $83,099, the provision with its Alternate II applies.
(C) If the acquisition value is $83,099 or more but is less than $100,000, the provision with its Alternate III applies.
(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.
(xxiii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan—Certification. This provision applies to all solicitations.
(xxiv) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications. This provision applies to all solicitations.
(xxv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.
(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and
(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.
(2) The following representations or certifications are applicable as indicated by the Contracting Officer:
[X](i) 52.204-17, Ownership or Control of Offeror.
[X](ii) 52.204-20, Predecessor of Offeror.
[](iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.
[](iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Certification.
[](v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services—Certification.
[](vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Alternate I only).
[](vii) 52.227-6, Royalty Information.
[](A) Basic.
[](B) Alternate I.
[](viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.
(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
| FAR Clause # |
| Title |
| Date |
| Change |
Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.
(End of Provision) A.5 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018)
(a) Definitions. As used in this clause—Covered article means any hardware, software, or service that—
(1) Is developed or provided by a covered entity;
(2) Includes any hardware, software, or service developed or provided in whole or in part by a covered entity; or
(3) Contains components using any hardware or software developed in whole or in part by a covered entity.
Covered entity means—
(1) Kaspersky Lab;
(2) Any successor entity to Kaspersky Lab;
(3) Any entity that controls, is controlled by, or is under common control with Kaspersky Lab; or
(4) Any entity of which Kaspersky Lab has a majority ownership.
(b) Prohibition. Section 1634 of Division A of the National Defense Authorization Act for Fiscal Year 2018 (Pub. L. 115–91) prohibits Government use of any covered article. The Contractor is prohibited from—
(1) Providing any covered article that the Government will use on or after October 1, 2018; and
(2) Using any covered article on or after October 1, 2018, in the development of data or deliverables first produced in the performance of the contract.
(c) Reporting requirement. (1) In the event the Contractor identifies a covered article provided to the Government during contract performance, or the Contractor is notified of such by a subcontractor at any tier or any other source, the Contractor shall report, in writing, to the Contracting Officer or, in the case of the Department of Defense, to the website at https://dibnet.dod.mil. For indefinite delivery contracts, the Contractor shall report to the Contracting Officer for the indefinite delivery contract and the Contracting Officer(s) for any affected order or, in the case of the Department of Defense, identify both the indefinite delivery contract and any affected orders in the report provided at https://dibnet.dod.mil.
(2) The Contractor shall report the following information pursuant to paragraph (c)(1) of this clause:
(i) Within 1 business day from the date of such identification or notification: The contract number; the order number(s), if applicable; supplier name; brand; model number (Original Equipment Manufacturer (OEM) number, manufacturer part number, or wholesaler number); item description; and any readily available information about mitigation actions undertaken or recommended.
(ii) Within 10 business days of submitting the report pursuant to paragraph (c)(1) of this clause: Any further available information about mitigation actions undertaken or recommended. In addition, the Contractor shall describe the efforts it undertook to prevent use or submission of a covered article, any reasons that led to the use or submission of the covered article, and any additional efforts that will be incorporated to prevent future use or submission of covered articles.
(d) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (d), in all subcontracts, including subcontracts for the acquisition of commercial items.
(End of Clause)
A.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
(End of Clause)
| FAR Number |
| Title |
| Date |
| 52.209-5 |
| CERTIFICATION REGARDING RESPONSIBILITY MATTERS |
| AUG 2020 |
| 852.228-70 |
| BOND PREMIUM ADJUSTMENT |
| JAN 2008 |
A.7 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)
(a) This solicitation includes FAR 52.219-4 Notice of Price Evaluation Preference for HubZone Small Business Concerns.
(b) Accordingly, any contract resulting from this solicitation is subject to the limitation on subcontracting requirements in 13 CFR 125.6, or the limitations on subcontracting requirements in the FAR clause, as applicable. The Contractor is advised that in performing contract administration functions, the Contracting Officer may use the services of a support contractor(s) retained by VA to assist in assessing the Contractor's compliance with the limitations on subcontracting or percentage of work performance requirements specified in the clause. To that end, the support contractor(s) may require access to Contractor's offices where the Contractor's business records or other proprietary data are retained and to review such business records regarding the Contractor's compliance with this requirement.
(c) All support contractors conducting this review on behalf of VA will be required to sign an “Information Protection and Non-Disclosure and Disclosure of Conflicts of Interest Agreement” to ensure the Contractor's business records or other proprietary data reviewed or obtained in the course of assisting the Contracting Officer in assessing the Contractor for compliance are protected to ensure information or data is not improperly disclosed or other impropriety occurs.
(d) Furthermore, if VA determines any services the support contractor(s) will perform in assessing compliance are advisory and assistance services as defined in FAR 2.101, Definitions, the support contractor(s) must also enter into an agreement with the Contractor to protect proprietary information as required by FAR 9.505-4, Obtaining access to proprietary information, paragraph (b). The Contractor is required to cooperate fully and make available any records as may be required to enable the Contracting Officer to assess the Contractor's compliance with the limitations on subcontracting or percentage of work performance requirement.
(End of Clause)
A.8 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)
(a) Definitions. As used in this clause—
(1) Contract financing payment has the meaning given in FAR 32.001;
(2) Designated agency office means the office designated by the purchase order, agreement, or contract to first receive and review invoices. This office can be contractually designated as the receiving entity. This office may be different from the office issuing the payment;
(3) Electronic form means an automated system transmitting information electronically according to the accepted electronic data transmission methods and formats identified in paragraph (c) of this clause. Facsimile, email, and scanned documents are not acceptable electronic forms for submission of payment requests;
(4) Invoice payment has the meaning given in FAR 32.001; and
(5) Payment request means any request for contract financing payment or invoice payment submitted by the contractor under this contract.
(b) Electronic payment requests. Except as provided in paragraph (e) of this clause, the contractor shall submit payment requests in electronic form. Purchases paid with a Government-wide commercial purchase card are considered to be an electronic transaction for purposes of this rule, and therefore no additional electronic invoice submission is required.
(c) Data transmission. A contractor must ensure that the data transmission method and format are through one of the following:
(1) VA’s Electronic Invoice Presentment and Payment System at the current website address provided in the contract.
(2) Any system that conforms to the X12 electronic data interchange (EDI) formats established by the Accredited Standards Center (ASC) and chartered by the American National Standards Institute (ANSI).
(d) Invoice requirements. Invoices shall comply with FAR 32.905.
(e) Exceptions. If, based on one of the circumstances in this paragraph (e), the Contracting Officer directs that payment requests be made by mail, the Contractor shall submit payment requests by mail through the United States Postal Service to the designated agency office. Submission of payment requests by mail may be required for—
(1) Awards made to foreign vendors for work performed outside the United States;
(2) Classified contracts or purchases when electronic submission and processing of payment requests could compromise the safeguarding of classified or privacy information;
(3) Contracts awarded by contracting officers in the conduct of emergency operations, such as responses to national emergencies;
(4) Solicitations or contracts in which the designated agency office is a VA entity other than the VA Financial Services Center in Austin, Texas; or
(5) Solicitations or contracts in which the VA designated agency office does not have electronic invoicing capability as described above.
(End of Clause)
PROJECT SPECIFIC INFORMATION
PROJECT SPECIFIC INFORMATION
PROJECT TITLE AND NO: Sterile Processing Services Design Correction-Topeka, Project Number 589A5-15-117B
PROJECT LOCATION: Department of Veteran Affairs, 2200 Gage Blvd, Topeka, Kansas 66622
MAGNITUDE OF PROJECT: Between $1,000,000 and $5,000,000 (VAAR 836.204)
TYPE CONSTRUCTION:
· NAICS: 236220, Commercial and Institutional Building Construction
· Small Business Size: $39.5 Million
PERFORMANCE PERIOD: The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use no later than the respective time period reflected below. The time stated for completion shall include final cleanup of the premises.
Bid Item 1 (Base Bid): 270 Calendar Days Bid Item 2 Deductive Alternate 1: 270 calendar days Bid Item 3 Deductive Alternate 2: 270 calendar days Bid Item 4 Deductive Alternate 3: 270 calendar days
SITE VISIT: A site visit will be conducted on: Wednesday, August 11, 2021, 10:00 AM CST.
Location: Colmery O’Neil VA Medical Center is located at 2200 SW Gage Blvd. Topeka, KS 66622.
RFI(s): All request for information in response to this solicitation are due Friday, August 20, 2021, 10:00 AM CST.
BID GUARANTEE
A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish a photocopy of the original bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then. Bidders shall provide an original bid guarantee within two business days after notification by the Contracting Office.
PERFORMANCE & PAYMENT BONDS: In accordance with FAR 28.102-1 and Contract Clause 52.228-15, Contractors are reminded that any amount awarded over $30,000 shall require Payment Protection (Bonds) (See Clause 52.228-13), and awards exceeding $150,000 shall require both Payment and Performance Bonds. All bonds are due no later than 10 days after award.
AFFIRMATIVE ACTION GOALS AND GEOGRAPHICAL AREA (reference 52.222-23):
Goals for Minority Participation for each trade: 9% Goal for Female Participation for each trade: 6.9% The Geographical covered area for this solicitation (project) is Topeka, KS
LIQUIDATED DAMAGES: (__) YES or (_X_) NO (reference Contract Clause 52.211-12) Amount Per Day: _____NA_______
WARRANTY OF CONSTRUCTION FOR GUARANTEE PERIOD SERVICES: ( ) YES or (X) NO (reference VAAR 852.246-75).
RESTRICTION ON SUBMISSION AND USE OF EQUAL PRODUCTS: ( ) YES or (X) NO (reference VAAR 852.236-90)
METRIC PRODUCTS: Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch/pound units, providing they fall within the tolerances specified using conversion tables contained in the latest revision of Federal Standard No. 376B, and all other requirements of this document are met. If a product is manufactured to metric dimensions and those dimensions exceed the tolerances specified in the inch/pound units, a request should be made to the contracting officer to determine if the product is acceptable. The contracting officer, in concert with the Contracting Officer’s Representative, will accept or reject the product, (reference VA Handbook 0100, Metrics).
WAGE DETERMINATION APPLICABLE TO THIS PROJECT:
General Decision Number: KS20210058 07-16-2021
PROPOSAL DUE DATE: Tuesday September 07, 2021 2:00 PM CST. (Submit pricing and all documentation through the vendor portal)
PROPOSAL SUBMITTAL CONTENTS SHALL INCLUDE:
· Signed copy of the SF1442 (front and back) with amendments
· Volume 1 Technical Proposal
· Volume 2 Price Proposal
· Cost Summary Sheet
· 52.209-5 REPRESENTATION BY CORPORATIONS REGARDING AN UNPAID TAX LIABILITY OR A FELONY CONVICTION UNDER ANY FEDERAL LAW (DEVIATION) (MARCH 2012)
· Calculation Worksheet for Self-Performed and Subcontracted Work
· Contractor Certification Regarding Safety and Environmental
· Bid Bond (Photo Copy)
· Any other information called out by this request for proposal documents.
BASIS FOR AWARD: Lowest Price Technically Acceptable.
COVID-19 REQUIREMENTS: COVID-19 Masks are always required. If you refuse or can’t wear a mask properly you will be asked to leave the campus. Only Masks that are cloth, surgical type or N95 are allowed. Gaiters and masks with vents are prohibited.
SAFETY OR ENVIRONMENTAL VIOLATIONS AND EXPERIENCE MODIFICATION RATE
All Bidders/Offerors shall submit the following information pertaining to their past Safety and Environmental record. The information shall contain, at a minimum, a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.
All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information shall be obtained from the bidder’s/offeror’s insurance company and be furnished on the insurance carrier’s letterhead.
Self insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.
A Determination of Responsibility will be accomplished for the apparent awardee prior to processing the award. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines above or submit this information will result in a determination of “Non-Responsibility” for the bidder/offeror. NOTE: Any information received by the Government that would cause for a negative Determination of Responsibility will make the bidder/offeror ineligible for award.
This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.
Page 1 of Page 1 of
PROPOSAL SUBMITTAL INSTRUCTIONS
FOR LOWEST PRICE TECHNICALLY ACCEPTABLE COMPETITION
SOLICITATION: 36C25521R0102
PROJECT: 589A5-15-117B: SPS DESIGN CORRECTION SOLICITATION
LOCATION: Department of Veteran Affairs, Colmery-O’Neil VA Medical Center, 2200 SW Gage Blvd., Topeka, KS 66622.
1. PREPARATION AND SUBMITTAL OF PROPOSALS
a. GENERAL INFORMATION.
Selection of an offeror for contract award will be made on the basis of an assessment of each offeror’s response to the Request for Proposal (RFP). As a Request for Proposals (RFP) based on Lowest Price Technically Acceptable (LPTA) Source Selection Process, in accordance with Federal Acquisition Regulation (FAR) Part 15.101-2, the VA will make the award based on the lowest evaluated price of proposals meeting or exceeding the acceptability standards for non-cost factors. The Five (5) evaluation factors for determination of technical acceptability consist of:
| 1. | Relevant Past Performance of Prime Contractor; |
| 2. | Technical Construction Experience of Prime Contractor; |
| 3. | Technical Qualifications of Proposed Staffing |
NOTE: Failure to comply with the RFP requirements will raise serious questions regarding an Offeror’s technical ability to perform the services and may be grounds to eliminate the proposal from further consideration for contract award.
b. THE OFFER.
The submission of the documentation specified below will constitute the Offeror’s acceptance of the terms and conditions of the RFP, including the Plans & Specifications for the construction of this project. These instructions prescribe the format for the proposal and describe the approach for the development and presentation of proposal data. These instructions are designed to ensure the submission of necessary information to provide for the understanding and comprehensive evaluation of proposals.
c. AWARD BASED ON INITIAL OFFERS.
Pursuant to clause 52.215-1 the Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price, and technical qualifications standpoint. The VA reserves the right to conduct discussions if the Contracting Officer later determines such discussions to be necessary.
d. NUMBER OF COPIES TO SUBMIT.
Offerors shall submit a SINGLE PACKAGE to the address shown in Block 8 of the Standard Form 1442. The package shall include:
(a) One (1) Envelope, Marked:
ORIGINAL - RESPONSE TO RFP 36C25521R0102
589A5-15-117B SPS Design Correction – VAMC – TOPEKA, KANSAS This envelope is to contain the signed original copy (1) of the documents listed below; and one electronic copy on a CD. Files must be readable using Microsoft Office 2007, Work, Excel, PowerPoint, PDF, or Access. Scanner resolutions must be set at least 200 dots per inch (dpi) when submitting files in Adobe PDF. If submitting in PDF, please create as Word and then save as PDF (scanning documents greatly increases the memory used). Ensure that attachments are less than 20 Megabytes. When splitting up the attachment, be sure to identify on the email subject line, i.e., 36C25521R0102/ABC Company/1 of 4. Note: Zip files are not acceptable. It is incumbent upon the offeror to ensure that their proposal is received by the due date and time.
(a) One (1) file will be marked Technical: RESPONSE TO RFP 36C25521R0102 PROJECT:
589A5-15-117B: SPS Design Correction. This submittal is to contain the signed original copy of the documents and the response for the three (3) technical factors listed below.
(b) One (1) file containing the pricing information for each Bid item as indicated on the price schedule. This file should also include the bid schedule and the Calculation of Self-Performed/Subcontracted Work.
2. DOCUMENTS TO SUBMIT.
Submit the proposal response by mail or in person to the address listed in Block 8 of the Standard Form 1442 containing the technical and price information by the request due date: