S06 - 36C25226B0032 0001.docx
DOCX document 118 KB Posted
- Attached to
- Y1DZ--556-24-122 B132 Pool and HVAC Replacement
- Solicitation number
- 36C25226B0032_01
About this file
This is an Amendment to Solicitation (Standard Form 30) issued by the Department of Veterans Affairs Great Lakes Acquisition Center for solicitation 36C25226B0032, effective August 5, 2026. The amendment pertains to Project #556-24-122, B132 Pool and HVAC Replacement at Captain James A. Lovell FHCC in North Chicago, Illinois. The primary requirement is to provide all labor, materials, equipment, qualified supervision, and other items necessary to renovate the pool to achieve compliance with current codes and Architectural Barriers Act (ABA) requirements, modernize pool plumbing and associated systems, make staff and patient locker rooms ABA compliant, and demolish and replace the old air handling unit (AHU) on the elevated platform with a new exterior pad-mounted AHU.
The amendment documentation requires bidders to provide a sign-in sheet from the organized site visit conducted on July 28, 2026, at 9:00 AM local time. No additional pre-bid site visits or project site access will be granted to maintain the solicitation schedule and avoid disruption to ongoing facility operations. The Request for Information (RFI) due date remains Friday, August 7 at 10:30 AM CST, and the bid submission due date remains Friday, August 21 at 9:30 AM CST. Bidders must acknowledge receipt of this amendment prior to the bid due date and time through submission of completed amendment copies, acknowledgment on offer copies, or separate written communication referencing the solicitation and amendment numbers.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
08-05-2026
556-26-1-6935-0001
556-24-122
Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101
Milwaukee WI 53214-1476
Department of Veterans Affairs 36C252 Great Lakes Acquisition Center - HC 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476 To all Offerors/Bidders
36C25226B0032 07-17-2026
X
SEE CONTINUATION PAGE
RYAN MCMILLIN
CONTRACTING OFFICER
RENOVATE B132 POOL AND HVAC
PROJECT# 556-24-122
CAPTAIN JAMES A. LOVELL FHCC, NORTH CHICAGO, IL
I. THE FOLLOWING CHANGES ARE TO BE MADE TO THE SOLICITATION:
1. PROVIDE SIGN-IN SHEET FOR THE ORGANIZED SITE VISIT WHICH WAS CONDUCTED ON JULY 28, 2026, AT 9:00AM LOCAL TIME.
II. THE FOLLOWING CHANGES ARE MADE ON PROJECT SPECIFICATIONS:
N/A
III. THE FOLLOWING CHANGES ARE MADE ON PROJECT DRAWINGS:
N/A IV. THE FOLLOWING QUESTIONS AND ANSWERS / CLARIFICATIONS ARE THE RESULT OF POTENTIAL BIDDERS REQUEST(S) FOR INFORMATION:
N/A
V. GENERAL INFORMATION:
1. THE SCHEDULED PRE-BID SITE VISIT HAS CONCLUDED. NO ADDITIONAL PRE-BID SITE VISITS OR ACCESS TO THE PROJECT SITE WILL BE GRANTED. THIS IS NECESSARY TO MAINTAIN THE SOLICITATION SCHEDULE AND AVOID DISRUPTION TO ONGOING FACILITY OPERATIONS AND PROJECT ACTIVITIES. BIDDERS ARE EXPECTED TO PREPARE THEIR BIDS BASED ON THE SOLICITATION, ISSUED AMENDMENTS, AND INFORMATION PROVIDED DURING THE SCHEDULED SITE VISIT.
2. REQUESTS FOR INFORMATION (RFI) DUE DATE OF FRIDAY, 7 AUGUST AT 10:30AM CST REMAINS UNCHANGED.
3. BID DUE DATE OF FRIDAY, 21 AUGUST AT 9:30AM CST REMAINS UNCHANGED.
******NOTHING FOLLOWS******
File details come from the government source that posted it. Updated .