S05 - Pre-Bid RFIs Log with Answers 578-26-006 Repair Building 1 Steam and Condensate Risers-Phase 2.pdf

PDF 155 KB Posted

Attached to
Z1DA--578-26-006 - Repair Steam and Condensate Risers Building 1 - Phase 2 (CON)
Solicitation number
36C25226B0012
Issued by

About this file

This is a Pre-Bid Requests for Information (RFIs) Log with Answers document for contract 578-26-006, "Repair Steam and Condensate Risers Building 1 - Phase 2," a Department of Veterans Affairs (VA) construction project. The document contains 17 pre-bid RFIs submitted between March 18 and April 1, 2026, with official responses from the VA (identified as "MM").

The RFIs address critical project execution details including work sequencing, access, and specifications. Key responses clarify that contractors will have access to all necessary floors to complete work, may work on up to 5 riser locations simultaneously with Contracting Officer Representative (COR) coordination, and can move through project phases without schedule delays with COR approval. All risers are identified as top-fed (not bottom-fed) steam risers with new isolation valves required at all valve locations on both new and existing fin tube radiators. The project is structured in four phases: Phase 1 (Asbestos Abatement - 30 days), Phase 2 (New Riser and Chase Installation - 200 days), Phase 3 (Disconnect and Connect in Sections A-F - 170 days), and Phase 4 (Disconnect and Connect in Section G - 20 days). The contractor is responsible for removing obstructing equipment, wall fixtures, cabinetry, radiator covers, and furniture; restoring surface damage; and submitting shop drawings for all riser locations. Finishes must match existing conditions, with entire walls painted "corner to corner" for paint matching. Fin tube radiators require Danfoss RA2000 thermostatic radiator controls and shut-on/off valves at each new installation location, with contractor submittal of schedules and manufacturer specifications required during the submittal period. All responses were incorporated into Amendment 0001.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

No. Date Submitted SUBJECT/COMMENT Responder Response

Included in Amendment

1 3/18/2026 Are we going to be able to work a complete riser from attic to crawl space at once? MM Yes, the contractor will have access to all the floors they need to finish their work 0001

2 3/18/2026 How many of these will be available to work at a time? MM The contractor may work on 5 riser locations at a time in coordination with the COR 0001

3 3/18/2026 According to the riser detail, we are not installing new isolation valves off the new risers to the existing fin tube. Is this correct? MM

New isolation valves will be installed to the new and existing fin tube radiators from new risers with an access panel at all valve locations 0001

4 3/20/2026 Please identify which risers are bottom feed steam risers and which are top feed steam risers, per S02-8 MM All risers are top fed. 0001

5 4/1/2026 Please identify and clarify which risers are bottom feed steam risers and which are top feed steam risers as shown on S02-8 Chase Riser & Pipe Size Details 2. MM All risers are top fed. 0001

6 4/1/2026 Does the VA have a proposed, or planned, phasing outlook for the project? If so, please provide. MM

Section H) Scope of Work in the Statement of Work says the following

Phases – The project work will be performed in Four (4) phases:

Phase 1 – Asbestos Abatement – 30 Days Phase 2 – New Riser and Chase installation – 200 days.

Phase 3 – Disconnect old risers and connect new risers for steam and condensate lines in Sections A-F – 170 days.

Phase 4 – Disconnect old risers and connect new risers for steam and condensate lines in Section G – 20 days.

The contractor may execute work in more than one phase at a time with COR/CS/CO approval. 0001

7 4/1/2026

Will work in all areas/floors be uninterrupted by owners and/or staff, once a complete riser is given to the general contractor to perform all scopes of work involved in the demolition of existing and installation of new riser? MM

Once the project area is given, the construction work will not be interrupted. 0001

8 4/1/2026 During the phasing of the project will multiple risers be able to be worked on simultaneously and in a parallel format? MM Please see the response for item 2 above. 0001

9 4/1/2026 While working in an administrative/office location will the entire room be vacant by hospital staff? MM

Depending on the location, there may be staff occupying sections of the room outside of the infectious control barrier.

In such cases patient/staff access must be maintained outside the Infection Control Barriers (ICB). 0001

10 4/1/2026 Will the VA be responsible for removal of all FF&E in rooms/offices prior to work being performed? MM

Section H) Scope of Work in the Statement of Work says the following

The contractor is responisble for any accessories and equipment that hinder construction

Demolition, relocation, or modifications of wall fixtures, equipment, cabinetry, radiator covers, OIT equipment and all furniture necessary to accommodate new pipe chase is the responsibility of the contractor. Surface damage or alterations must be restored to previous conditions including damage to paint. Contractor shall send shop drawings for all riser locations and where room modifications are needed to fit new pipe chases.

578-26-006 - Repair Steam and Condensate Risers Building 1 - Phase 2 (CON) Pre-Bid RFIs

S05 - Pre-Bid RFIs Log with Answers 578-26-006 Repair Building 1 Steam and Condensate Risers-Phase 2 1 of 2

No. Date Submitted SUBJECT/COMMENT Responder Response

Included in Amendment

11 4/1/2026 Is general contractor required to remove associated accessories (shelves, countertops, etc…) in offices/rooms prior to work being performed? MM

Please see the response to item 10 above

12 4/1/2026 Will contractors be able to move throughout phases without delay in schedule? (This pertains to being able to maintain continuous work-flow). MM

Yes. The contractor will be able to move throughout the phases without delay in coordination with COR. 0001

13 4/1/2026 The building is made up of plaster walls, is it acceptable to use 5/8” fire treated drywall for repairs and patching? MM Yes, that is acceptable. 0001

14 4/1/2026 While painting the newly constructed chase, will the entire wall(s) it adjoins with be required to be painted? MM

All surfaces altered or damaged by construction shall be repaired by the contractor to it's original state. The entire wall(s) will need to be painted "Corner to Corner" to ensure paint matches. 0001

15 4/1/2026 Does the VA have a finish plan available for all rooms/areas to be affected by construction? MM The contractor must match existing finishes in coordination with the COR. 0001

16 4/1/2026 Please provide a schedule for new FIN tube including manufacturer’s specifications, quantity, and location. MM

The contractor shall submit schedule for fin tube and related accessories for all rooms during the Submittal period. For manufacturer basis, provide a steam rated fin tube product in compliance with VA specs. Exact model configurations shall be confirmed in shop drawings and coordinated with

Attachment 7 locations. 0001

17 4/1/2026 Please confirm valve specification is to be Danfoss (manually operated) and not Capillary T-Stat.

Also, confirm each location that is to receive a new valve. MM

The Danfoss RA2000 is a thermostatic radiator control..

Each location where a new fin tube radiator is installed, a Danfoss control is to be installed. Each new radiator will receive a shut on/off control valve. 0001