This document is an amendment to a federal solicitation for the upgrade of Building 112 power at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The solicitation number is 36C25222B0030 and the project number is 695-20-104.
The amendment provides responses to contractor questions, revises specifications and drawings, and notes additional forthcoming responses from the VA. Key changes include adding specifications for commissioning requirements, engine generators, and helical piers. The staging area and construction fence locations are revised on drawing A-001. Clarification is provided around asbestos abatement scope, lead paint removal, soil contamination, fuel tank pumping, and generator information and testing requirements. Contractors must acknowledge receipt of the amendment by the specified date to be considered for award of the contract.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 695-23-1-6970-0001 695-20-104 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee
WI
53214-1476 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee
WI
53214-1476 To all Offerors/Bidders
36C25222B0030 09-26-2022
X X X
SEE ATTACHED SUMMARY OF CHANGES.
CONTINUE TO MONITOR CONTRACT OPPORTUNITIES FOR ANY AND ALL CHANGES TO THIS SOLICITATION.
Stacy Hoover Contracting Officer Upgrade Bldg. 112 Power PROJECT# 695-20-104
CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI
I. The following changes are to be made to the solicitation:
a. See sections II, III, and IV.
b. Additional VA responses to contractor questions/RFI’s are forthcoming.
II. The following changes are made on project specifications:
a. Geotechnical Report - ADDED
b. Specification 01 91 00 COMMISSIONING REQUIREMENTS - ADDED
c. Specification 26 32 13 ENGINE GENERATORS – UPDATED
d. Specification 31 62 16 HELICAL PIERS – ADDED III. The following changes are made on project drawings:
a. Drawing A-001 - REVISED.
IV. The following Questions and Answers / Clarifications are the result of bidders request(s) for information:
Q1: Can all work be done during normal daytime work shifts?
A1: No, see specification 01 01 10SN 3.21 and question 57.
Q2: Can the Site Superintendent fulfill the duties of the SSHO as well?
A2: Yes Q3: Is there a specific location for a site construction Trailer / Staging Area? If so, can you please advise where it is located?
A3: South of Building 112, east of Buildings 49 and 50. See revised Architectural Site Plan (drawing A-001) showing staging area and construction fence areas.
Q4: In section 01 00 00 1.5.S, referring to Construction Fence. There is nothing indicated on the drawings as referenced in the specifications.
A4: See question 3.
Q5: Will a Construction Fence be required around the staging area, trailer and Construction Site?
A5: See question 3.
Q6: In section 01 00 00 1.12.F, referring to delivering two electronic copies of complete As Builts after each completed phase. This also applies to shop drawings. If electronic, does the VA require two?
A6: VA does not require 2 copies if electronic, one copy is sufficient Q7: Per section 01 00 00.1.23.Z, Does the VA require two hard copies of the completed O&M?
A7: Yes Q8: Considering an electronic version will be uploaded to OpCenter. Do the manuals require delivery when the equipment arrives or at substantial completion?
A8: Substantial completion Q9: Per Specification Section 01 01 10SN, section 3.10.A. Will a construction Site Phone be required on this project?
A9: No Q10: Is a submittal log/register required for submission by the contractor for this project? Reference 01 33 23 1.3.C, the VA provides the initial submittal register.
A10: No Q11: Reference 01 81 13, is sustainable construction required on this project?
A11: Specification 01 81 13 is not included in this project.
Q12: Specification Section 01 91 00 General Commissioning Requirements is referenced in many spec sections thru out the Specifications. There was no section 01 91 00 included in the table of contents or in the specifications. Is any “Commission” required on this project? If so, please advise as to the specific requirements, trades, items to be commissioned, who will lead the commissioning, Will there be a CxA? Who will hire the CXa?, Who pays for the CxA?
A12: Contractor required to perform regular commissioning as per applicable specification sections – The VA will hire a commissioning agent to monitor all commissioning.
Q13: Will crane picks for the rigging of HVAC equipment (or any other equipment) and materials be restricted to federal holidays and weekends?
A13: No Q14: Is AISC Steel Certification required for both the fabricator AND the installer?
A14: Yes Q15: Specification Section 07 08 00 is included in the Specifications and references 01 91 00 – Please clarify what is expected / required. Please advise if reference is to be removed?
A15: See attached specification section 01 91 00 as part of this amendment.
Q16: Section 07 11 13 is included in the specifications, but there does not appear to be any details included in the drawings for foundation waterproofing. Please advise if this specification Section is applicable to this project. If it is can you, please clarify where it is required?
A16: Spec 07 11 13 will remain in the contract documents for this project, but there does not appear to be a requirement for waterproofing since there is no below grade concrete with exposure to the interior spaces.
Q17: Is the Third-Party Fire Penetration inspector hired by contractor or the VA?
A17: Contractor, See specification section 07 84 00 1.5.C Q18: Reference 09 91 00 Painting, are sample panels required or will draw down samples suffice?
A18: Drawdowns are acceptable Q19: Is there is a preferred water treatment vendor for the chemicals specified in specification section 23 25 00?
A19: Specification section 23 25 00 is not part of this project Q20: Specification Section 23 31 00, Section 3.1 “K”. Please clarify the expectations of ductwork cleaning. How far back do we clean when connecting new ductwork to existing. It would seem unreasonable to clean all the way back to the existing equipment / Chase.
A20: All ductwork in scope is being removed and replaced so no reconnection to or cleaning of existing ductwork is anticipated.
Q21: Specification Section 23 31 00, duct cleaning. During construction we have will the ends of all new ductwork wrapped in plastic to protect the integrity of the ductwork. Plastic will be removed just prior to system start up. Will machine cleaning of protected ductwork be a requirement of the project A21: No Q22: Has the VA tested the ductwork and mechanical systems scheduled for demolition or relocation for biohazards? If the ductwork or equipment are contaminated, remediation will be required and due to insurance protocol, we cannot subcontract for the remediation.
A22: There are no known biohazards – area/ system not used for biohazard operations.
Q23: Specification Section 23 31 00, Section 3.2, items “B” thru “H”, will leak testing be required on ductwork down stream of air terminal units?
A23: No air terminals are within the mechanical scope of this project so no testing will be required.
Q24: Please clarify the scope of work associated with duct testing as there is minimal to no supply air ductwork. Please be specific what the VA needs tested. Is the Exhaust Duct from the muffler to be leak tested?
A24: Ductwork should be sealed, but no leak testing is required on exhaust duct from the generator.
Q25: Per Section 31 20 11 Part 3.5-C excavated soils, suitable for backfill are to be stockpiled on site as directed.
A25: Section 31 20 11 not part of this project. See section 31 20 00 part 3.5.C Q26: Can you advise of the location for stockpiling?
A26: Within the project boundaries.
Q27: If materials are “contaminated”, are they to be stockpiled on 6 mil polyethylene sheets with a polyethylene cover at a designated area?
A27: Yes Q28: Will the designated area for stockpiling contaminated soils be located with the project boundaries?
A28: See question 25.
Q29: Is all the soil considered contaminated or is there only isolated areas?
A29: VA is unaware of any soil in this project that can’t be reused as fill. See specification section 31 20 00 Part 3.5 DISPOSAL OF UNSUITABLE AND EXCESS EXCAVATED MATERIAL Q30: Per Section 31 20 11 Part 3.5-E conflicts with Part E referenced above. Please clarify?
A30: Section 31 20 11 not part of this project. See section 31 20 00. The above references Part C gives information on “stockpiling,” Part D gives information on when excess excavated materials suitable for fill and/or backfill may be disposed of, and Part E gives instructions on how to dispose of it.
Q31: Can any of the “contaminated” soils designated by the Resident Engineer be used as backfill?
A31: Yes, in compliance with specification 31 20 00. VA is unaware of any soil in this project that can’t be reused as fill Q32: Will the VA provide direction as to when the stockpiled contaminated soil is to be removed and where it is to be taken to?
A32: See question 30 Q33: Is there a Soil Profile showing the levels of contaminates for this project and will it be provided? If not, where should we figure the contaminated soils need to and will the VA be providing that paperwork showing compliance with all State and Local requirements?
A33: See specification 31 20 00 3.5 E and F Q34: Will the contractor be responsible to carry in their bid and pay for the tipping fees associated with the disposal of the contaminated soils?
A34: See specification 31 20 00 3.5 E Q35: Is 16 hours of training on the DDC controls required? If so is 16 hours needed? Please confirm the training hours required.
A35: 4 hours of training is required.
Q36: Is there any additional Training required by the VA on this project?
A36: Provide training per specifications Q37: Above ceiling demolition of MEP’s that are not shown on the drawing and not able to be investigated at the walk thru. How are these to be handled?
A37: There is no above-ceiling demolition on this project.
Q38: Is the existing Generator to be salvaged and turned over to the VA or will it become the Contractors to get rid of?
A38: Contractor is to disconnect and move generator to VA designated location on campus. The VA will retain ownership of the generator.
Q39: Can the existing drawings for the in-ground fuel tank and the route of the fuel lines be provided? The As-Builts from the installation would be appreciated.
A39: Existing drawings of the fuel system are not available.
Q40: Confirm the contractor is to include provisions / costs for a Temporary Back Up generator system. Can the requirements be more clearly defined as far as capacity?
A40: Temporary generator will need to be provided; this building cannot be without power. Size of temporary generator should be 250kW/300kVA to replace existing while new is being installed
Q41: Per the Asbestos Sections of the spec the Survey conducted by Terracon is to be referenced for QTYS. The survey indicates the following A41: See answers below.
(a) 450 SF of CMU block filler to be abated – Can you please clarify where the block will need to be abated as a location is not shown on the plan?
(i) Answer: Abate only the areas impacted by demolition and construction.
(b) 21 LF of window glazing is to be abated, but the windows are not being replaced. Please advise what is to be included in the contract? Are we to abate the glazing and recaulk the windows interiors?
(i) Answer: Abate only the areas impacted by demolition and construction.
(c) A reference to cloth coated wire is made to assume it is ACM. Are we to include abatement of this item? If so please provide a quantity, or advise if this will be dealt with as an unforeseen condition if any wire is encountered.
(i) Answer: Abate only the areas impacted by demolition and construction.
(d) The Survey provides a list of Hazardous / Universal Waste Inventor. Are any of these materials to be removed or expected to be removed by the contractor? If so please provide quantities to be included.
(i) Answer: Abate only the areas impacted by demolition and construction.
Q42: Per the specifications there is a spec for lead based paint removal and disposal, but no quantities are given. Can a list of quantities be provided to clarify this scope of work? Are the windows to be stripped of LBP and repainted? Are the steel beams to be stripped of LBP and re-Painted? The generator rooms have LCP on the floor, is this LCP to be stripped prior to any new housekeeping pads? Is the floor to be re-Painted after new construction / Expansion?
A42: The windows are not being removed for this project, the only place where lead-based paint should occur is within the Generator space and those dimensions are known. Some of the quantities and the areas that have LBP and other hazardous material is shown in the Terracon report which is the appendix of the Asbestos abatement spec section.
Q43: Plan Page A101 – Key Note #7 is used on both the reflected ceiling plan and the floor pan. Can this be clarified as to what Key Note #7 is for each the floor plan and the ceiling plan. The note refers to painting walls and underside of deck and Structure P-1. No finish Schedule is provided on the plans. Please Clarify A43: The walls and the ceiling are both to be painted to match the existing color scheme of the interior of this space. The ceiling is an exposed metal deck, and the walls are gypsum board. The requirements for the paints to be used are indicated for those materials in spec section 09 91 00.
Q44: The new structural Drawings indicate new Helical Piers to be installed. There is no specification for Helical Piers. Please provide a specification for the Helical Piers A44: See attached specification section 31 62 16
Q45: Will the VA be pumping / Draining the Fuel Oil Day Tank? If not please advise if the contractor is to pump out the tank and what volume needs to be pumped out.
A45: VA will pump out tank.
Q46: If the contractor is to pump out any fuel oil will become the contractor’s responsibility to dispose of the fuel oil?
A46: See question 45
Q47: There do not appear to be any wall types labeled on the Floor Plan and a wall type legend cannot be found on the drawings. Please advise of wall types, and location on the plans. Also please provide a schedule of wall types.
A47: The new walls are all detailed showing their construction, there are no interior partition types since the framing and gypsum board on the exterior walls are clearly called out. See wall section/details showing construction on drawing A-201.
Q48: Does the project require an SSHO with no other duties on the project, per spec section 01 35 26?
A48: No. See question 2
Q49: Do the EM feeders on the project have to be run in rigid conduit?
A49: Unless indicated otherwise within specification, drawings, or required by code, EM feeders do not have to be run in rigid conduit.
Q50: Storage of materials allowed onsite?
A50: The lay down area will be shown on the revised site plan to be submitted as part of RFI response.
Q51: Per spec section 01 35 26, What qualifies for SSHO construction experience?
A51: Refer to Spec Section 01 35 26, paragraph 1.8. Further explanation can be found on the following site: www.osha.com/blog/ssho-meaning.
Q52: Is the existing generator to be returned to the VA?
A52: See question 33
Q53: What is the make and model number of the existing generator and how many hours are on it?
A53: Make: Baldor Industrial Generator, Model #: IDLC250-4JU, Serial Number: 1307090001, Hours: 662.4 Date hours recorded: 9/7/22
Q54: Is there a minimum clearance between the generator and the interior walls of the generator room?
A54: Minimum clearance is 42” between generator and walls
Q55: Are any new foreseer meters to be installed under this contract?
A55: Yes, there should be two; one for the ATS and one for the new panel DH-SB-BLD112-1 Q56: Is the contractor responsible for providing fuel for the temp generator?
A56: Yes, all equipment and supplies necessary for the running and connection of the temporary generator are to be provided. See phasing schedule sheet E-001.s
Q57: Are MV outages to be done on a certain day of the week?
A57: Yes, Sundays
Q58: What termination type will need to be used to attach to the existing MV system? Are we to assume MV connection is allowable under existing conditions without modification of the existing system?
A58: MV conductors to be spliced into existing MV conductors at MV Switch being removed, sheet E-001 phasing 1.a. Termination to equipment will be dependent on the type of equipment submitted.
Q59: Is there a BoD for light switches?
A59: No, there is not a BoD for light switches, but if new switches are added they must be similar to, and work with, the existing switches in the same area, i.e., 3-way switch.
Q60: Electrical General note 18 on page E-001 states that no set screw fittings are to be used, does this pertain to ALL trade sizes?
A60: Specification 26 05 33, 2.1.C.2.c indicates that compression fittings are to be used for 3/4” to 2” and set screw hardened tip for 2-1/2” to 4
Q61: Can you please confirm the generator size? The one-line e-601 states the new generator is a 600kW but the specification sheet page 6 calls for a 400kW.
A61: See attached, revised specification section 26 32 13 Q62: Currently, below specification (07 27 26) calls for FLUID-APPLIED, VAPOR PERMEABLE regard to above project. We would like to request that our AIR-SHIELD LMP please reviewed as a liquid membrane vapor permeable material here.
A62: From what can be seen about the W.R. Meadows product it appears that it would meet the requirements for this project, but a full submittal per the requirements of the contract documents was not provided and further evaluation cannot be performed.
Q63: Please provide the following report per the structural notes: "FOUNDATION DESIGN IS BASED ON THE RECOMMENDATIONS IN THE GEOTECHNICAL REPORT PREPARED BY TERRACON, REPORT NUMBER 58215015 DATED 10 MARCH 2021." We will need this to estimate type of helical pile, depth, flight configuration etc.."
A63: See attached Geotechnical Report Q64: Please clarify the ASTM spec to be used for the load tests referenced on the Structural Notes. "A MINIMUM OF TWO LOAD TESTS SHALL BE MADE. PIERS SHALL BE TESTED FOR 2x THE ALLOWABLE LOAD CAPACITY. ALLOWABLE LOAD, CAPACITY OF A SINGLE HELICAL PIER SHALL BE 6,000 POUNDS MINIMUM."
A64: See ASTM D1143 Q65: If ASTM Static load tests are specified, the cost will be significant due to the reaction piles that will need to be installed, test frame setup etc... Please keep in mind there are only 4 helical piles on this job designed for an allowable load of 6k per pile and will be designed in accordance with IBC for a 2.0 safety factor. It is our professional opinion that the requirement for 2 load tests is excessive and can be eliminated for cost savings measures considering the quantity and light load per pile. Please consider eliminating this requirement.
A65: Helical pile testing is not required. Piers shall be designed with a 3.0 safety factor, in lieu of testing.
Q66: Spec section 23 05 93 Testing, Adjusting and Balancing for HVAC is included in the specifications section. But there are no air distributions systems to be leak tested or balanced. The only duct work on this project is the exhaust duct for the new generator. Is the Specification section 23 05 93 needed for this project? If so, what scope of work should they be including?
A66: Confirmed, Spec section 23 05 93 Testing, Adjusting and Balancing for HVAC is NOT required for this project
** Additional VA Responses to vendor questions/RFI’s are forthcoming.
V. General Information:
1. REMINDER: VAAR 852.219-77 VA Notice of Limitations on Subcontracting – Certificate of Compliance for Services and Construction is included in this solicitation (see SF1442 pages 51-52); signed certification must accompany bid to be considered for award.
2. NOTE: Ensure all correspondence is mailed or hand-carried to the following address:
Department of Veterans Affairs Great Lakes Acquisition Center ATTN: Stacy Hoover and Rosalyn Howard 115 S. 84th St., Suite 101 Milwaukee, WI 53214-1476
UPGRADE BUILDING 112 POWER, PROJECT# 695-20-104, AT THE CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI See attached document: S06 - Geotechnical Report - ADDED.
See attached document: S06 - Specification 01 91 00 COMMISSIONING REQUIREMENTS - ADDED.
See attached document: S06 - Spedification 26 32 13 ENGINE GENERATORS - UPDATED.
See attached document: S06 - Specification 31 62 16 HELICAL PIERS - ADDED.
See attached document: S06 - Drawing A-001 Revised.
ACCOMPANYING 36C25222B0030 0003