- Z1DA--Project 556-20-013 Renovate Bldg 134 CLC 3A/C at the Captain James A. Lovell FHCC in North Chicago, IL
- Solicitation number
- 36C25222B0022
About this file
This federal government solicitation seeks proposals to renovate Building 134 at the Captain James A. Lovell Federal Health Care Center in North Chicago, Illinois. The project includes renovations to wings C, A, and associated common areas, with an optional bid to only complete wing C. Key details include a bid opening date of August 8, 2022 at 1:00 PM Central Time at the Department of Veterans Affairs Great Lakes Acquisition Center. The estimated period of performance is 235 calendar days. Interested vendors must comply with Department of Veterans Affairs solicitation requirements and all applicable Federal Acquisition Regulation provisions. The scope of work involves demolition, hazardous material abatement, mechanical, electrical, and architectural construction services.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 07/28/2022 556-22-1-6959-0001 556-20-013 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 To all Offerors/Bidders
36C25222B0022 06-29-2022
X X Monday, 8/8/2022 at 13:00 CST.
X
PROJECT NO. 556-20-013 (CONST) RENOVATE CLC BUILDING 134 3A/3C AT THE CAPTAIN JAMES A. LOVELL FEDERAL HEALTH CARE CENTER
(FHCC) NORTH CHICAGO, IL 60064:
The Purpose of Amendment 0003 is to provide additional details to the original solicitation package.
See continuation page(s) and attachments for specific details.
Kristi Kluck Contracting Officer Continuation page -- Amendment: 0003
SF30 Block 14 Continuation Page
| Project: | 556-20-013: Renovate CLC Bldg. 134 – 3A and 3C |
| Solicitation: | 36C25222B0022 |
| Amendment: | 0003 |
The Purpose of Amendment 0003 is to incorporate/clarify the following information to solicitation 36C25222B0022:
A. Interested vendor questions and answers
| No. |
| QUESTION(S), July 15, 2022 |
| Response |
| 4.1 |
| Regarding roofing work: |
We [roofing subcontractor] are looking at this ITB [IFB] and see that the only roofing is related to mechanical work, and there is mention of the roof being under warranty. If the roof is under warranty, we need to know the manufacturer and roof system before we can let you know if we will be bidding.
Usually, the subcontractor needs to know if it’s under warranty, because if it is, then a certain person/company needs to do the work versus any roofing company. That would be the only reason they [a roofing subcontractor] would not bid it, that it is under warranty, roofs usually carry a 20+ year warranty. A roofing subcontractor was asking this question, [not a prime contractor].
See existing roofing warranty information (0003, Attachments 1 and 2).
Q5.1 – Q5.9 VOIDED5/RESCINDED QUESTIONS
Q6.1 – Q6.44
| No. |
| Contractor Questions, July 22, 2022 |
| Response |
| 6.1 |
| Please confirm personnel requirements for this project. Can (1) superintendent fulfill SSHO requirements? Or does (1) superintendent and (1) SSHO need to be on site full-time? Can superintendent and QC manager be the same person, or must superintendent and QCM be separate individuals? |
| Review and comply with 01 35 26 Safety Requirements. |
| 6.2 |
| Please confirm work hours for this project. Are there any specific tasks or trade division that must be on overtime (01 Infection Control, 02 Demolition, 02 Abatement)? Are there any areas of work that must be on overtime (Hallways, Occupied Areas, Etc. |
| Review and comply with Scope of Work. |
Normal work hours are clearly stated in the SOW, as are restrictions on certain activities and areas. The work hours indicated in the drawings which conflict with that of the SOW are erroneous.
All costs associated with planning and executing the work are borne by the contractor.
“Overtime” is not work outside of the described normal working hours unless performed by workers who have already performed their regularly scheduled eight-hour day, which can be avoided with attentive planning. Shift differential incentives and the like are common, but not overtime.
| 6.3 |
| Please confirm who has the existing roofing warranty and provide point of contact for the facility. |
| COR will provide awarded contractor with whatever information may be available. |
| 6.4 |
| Please confirm if contract has material staging location at facility. If so, where is it? Is prime contractor responsible for any costs associated with staging |
| All costs associated with planning and delivering a project are borne by the contractor, including temporary facilities and site logistics. |
| 6.5 |
| Concrete work is shown in the project drawing set; however, no concrete specification section is included. Please provide a specification section for the concrete work required. |
| Advise where concrete work is shown without corresponding note regarding product to be used. |
Example: SF102 notes Sikaquick VOH (or approved equiv) for repair of existing columns.
All concrete work is non-structural other than demolition that is covered in Specification 02 41 00 Demolition. Also note non-structural concrete/cementitious floor leveling requirements.
| 6.6 |
| Does phase 1 have to be entirely completed and approved prior to beginning phase 2? Can phases overlap or run concurrently? |
| Work is programmed to be performed in sequence. Time between is a function of Contractor quality assurance and completing all requirements of the first phase. |
Review and comply with 01 00 00 General Requirements.
| 6.7 |
| Is the contractor responsible for costs associated with Submittal Exchange software? Will VA be providing an electronic submittal program, or is it expected that the general contractor provides this? Are there programs or software that is acceptable? |
| Review and comply with 01 33 23 Shop Drawings, Product Data, and Samples, and all submission requirements of all specifications. |
VA will not provide a web-based document management service, nor specifically require Submittal Exchange, however, whichever platform or method Contractor chooses to meet requirements, it cannot require government employees, or those of the AE, CxA, or other project team member to purchase or download software or applications. If the Government information security systems won’t allow VA staff to access the platform due to security issues (not uncommon), an alternative method of transmitting information is required.
Note that Procore is reportedly used successfully by contractors at Jesse Brown VAMC and Hines VAMC.
| 6.8 |
| Roof work is shown in the project drawing set; however, no roofing specification section is included. Please provide a specification section for the roof work required |
| The roofing is just patching of the existing roofing at new openings, which is covered in the roof flashing. We are not re-roofing any portion of the roof. Additionally, there is a request on the roofing warranty and who is performing that. That warranty will have instructions on anything that needs to be one. No roofing specification is required. |
| 6.9 |
| Will there be downtime anticipated between phases 1 and 2? If so, how long should the contractor assume work will be stopped between phases? |
| Work is programmed to be performed in sequence. Time between is a function of Contractor quality assurance and completing all requirements of the first phase. |
Review and comply with 01 00 00 General Requirements.
| 6.10 |
| If bid alternate 1 is chosen, will the project then be completed in one continuous phase? It appears that the work in phase 2 is entirely deducted in bid alternate 1 |
| Yes. If there are insufficient funds available for the entire project the VA will proceed only with Phase 1 (C-Wing) |
ALTERNATE NO.1: BASE BID except, delete all work in Wing A.
Phase I: All work in Wing C Phase II: All work in Wing A See GC101 and GC102
| 6.11 |
| Is an AISC Certification required for the structural steel fabricator and/or erector |
| Yes, an AISC Certification is required for the structural steel fabricator and/or erector. |
| 6.12 |
| Is an electrical source available in the work area for contractor use? Will the contractor be responsible for metering costs |
| Utilities requested for use by Contractor may be allowed by VA, however, any required modification, additional material, labor, engineering, etc. needed for contractor to make use of VA utilities are required to be performed and paid for by Contractor, and restored to their previous condition prior to project completion or acceptance. VA will not provide labor or material for temporary connections or use by Contractor. Contractor shall submit a detailed plan for use of any VA utility, and cooperate fully in following any conditions of their use communicated by VA. VA has no expectation of compensation for utilities used. |
| 6.13 |
| Please confirm that the testing, adjusting, balancing contractor is to be hired directly by the prime contractor, and cannot be a subcontractor of the mechanical contractor |
| Review and comply with 07 84 00 Firestopping. |
Submit products, installers, and independent inspector per 1.5 Quality Assurance, and 3.5 Inspections and Acceptance of Work.
Submit the qualified inspector’s standard report content/format for compliance with ASTM E699 (current edition).
| 6.14 |
| 01 00 00 Water Source: Is a water source available for contractor use? If so, is the contractor responsible for any associated costs |
| Utilities requested for use by Contractor may be allowed by VA, however, any required modification, additional material, labor, engineering, etc. needed for contractor to make use of VA utilities are required to be performed and paid for by Contractor, and restored to their previous condition prior to project completion or acceptance. VA will not provide labor or material for temporary connections or use by Contractor. Contractor shall submit a detailed plan for use of any VA utility, and cooperate fully in following any conditions of their use communicated by VA. VA has no expectation of compensation for utilities used. |
| 6.15 |
| 23 09 23 Controls Integration: Please confirm that the controls integration contractor is to be hired directly by the prime contractor, and cannot be a subcontractor of the mechanical contractor? |
| Review and comply with 07 84 00 Firestopping. |
Submit products, installers, and independent inspector per 1.5 Quality Assurance, and 3.5 Inspections and Acceptance of Work.
Submit the qualified inspector’s standard report content/format for compliance with ASTM E699 (current edition).
| 6.16 |
| 01 00 00 Elevator Use by Contractor: Please confirm per specifications that the contractor will not be allowed the use of existing elevators, and that outside type hoist shall be used by the contractor for transporting material and equipment. |
| Review and comply with Scope of Work. |
Review and comply with 01 00 00 General Requirements.
Use of freight elevators outside of normal hours, ensuring that material movement within the facility cannot harm people, VA property, or release dust, may be allowed by the COR (or revoked for failure to protect people and property). Also see note at GC101.
Use of passenger elevators is never allowed.
| 6.17 |
| 02 82 11 CPIH: Please confirm the prime contractor is responsible for directly hiring the CPIH to inspect and oversee abatement work |
| Review and comply with 02 82 11 Traditional Asbestos Abatement. |
Review and comply with 02 82 13.13 Glovebag Asbestos Abatement.
CPIH stands for Contractor's Professional Industrial Hygienist, which 02 82 11 and 02 82 13.13 states that CPIH is the asbestos abatement contractor’s industrial hygienist. Multiple occurrences within this specification describe requirements for CPIH/CIH.
| 6.18 |
| SF102: New Opening at Existing Slab: Where is Detail 4/SF102 labelled “New Opening In Existing Slab” located on the full plan? Is this detail referencing the 3rd floor slab opening shown on SF101? Or is this an additional slab opening at a different location? |
| 4/SF102 is for the new roof openings for the new AHU. See Mechanical Equipment Support Plan Notes, Note 3. |
| 6.19 |
| AD102 - 02 41 00: What is the existing ceiling layout within the project boundary? Is the demolition contractor to assume the existing ceiling is gypsum / act matching new ceiling plans |
| AD101, Note S: Remove ceiling assemblies in their entirety throughout project boundary unless notes otherwise. |
| 6.20 |
| AD102 - 02 41 00 Ceiling Demo: Are there any areas within the work project boundary that the existing ceiling system is to be removed and reinstalled for purposes of accessing above ceiling MEP work? Or is the entire ceiling within the project area to be removed and replaced with new? |
| AD101, Note S: Remove ceiling assemblies in their entirety throughout project boundary unless notes otherwise. |
| 6.21 |
| HA101 02 82 11 C-Wing Abatement: No Abatement is shown in the C-wing. Please confirm no ACM is anticipated in the C-wing to be abated as part of this contract. |
| Per the Environmental Report, Appendix A no ACM work is required in Wing C. |
| 6.22 |
| AE100 Second Floor Work - Off-Hours: Is work on the second floor to be completed on off-hours? |
| Wing A and B are occupied. Wing C is vacant. Work cannot disrupt facility operations. |
| 6.23 |
| AE100 Second Floor Work - Infection Controls: Is the contractor responsible for any infection control requirements when working on the second floor below the project area? |
Yes.
| 6.24 |
| AE100 Second Floor Work Is the second floor below the project area an occupied space? What is the second-floor space below the project area used for? |
Area is I-2 Healthcare Occupancy. See Q41.
| 6.25 |
| AE100 Second Floor Work: What is the existing ceiling layout of the second floor below the project boundary? When removing ceilings to access work on the second floor, should the contractor assume, these will be ACT ceilings? Can the second-floor ceilings remain open between shifts, or is the contractor to reinstall ceilings each day? |
In Wing A, it is lay-in type ceilings with drywall soffits around the main corridor perimeter.
| 6.26 |
| Penthouse Access: What are the dimensions of the doorway of the penthouse? |
| 33"W x 83"H. Contractor is responsible to verify existing conditions. |
| 6.27 |
| GC101 Elevator Size: What are the dimensions of the elevator for contractor use. |
| 53.5"W x 83.5"H x 85"D. Contractor is responsible to verify existing conditions. |
Also, review GC101.
| 6.28 |
| AE501: Masonry Specs: Masonry work is shown in the project drawing set; however, no masonry specification section is included. Please provide a specification section for the masonry work required. |
| Please provide location where new masonry work is shown. |
The drawings call for infilling a small opening with block. The detail and notes provide direction and do not warrant a specification.
| 6.29 |
| AI112 Epoxy Floor Specs: Please provide a specification section for the Resinous Epoxy Floor required. Epoxy floor work is shown in the project drawing set; however, no Resinous Epoxy Floor specification section is included. |
| AI601 shows epoxy flooring as Dur-A-Flex (brand) as basis of specification. |
VA to select from available products of submitted manufacturer which are suitable for electrical closet applications.
Finish/color: Microchip, Sahara.
Surface prep and product application are as required of the contract documents and manufacturer’s technical resources.
| 6.30 |
| QH101: Wall Hood: QH101 shows new wall hoods to be furnished and installed by the contractor. Please provide a detail or specification on the wall hoods to be provided. |
| This is a recirculating, commercial quality stainless steel hood equal to Proline PLJW 130.30. This is not a commercial hood. It is not ducted to the outdoors. |
| 6.31 |
| FP101 Fire Sprinklers: What is the current fire sprinkler system within the work area? Is there currently a fire sprinkler system to be rerouted to accommodate new room layout? Or is an entirely new system to be provided for the work area |
| Drawing General Notes call for existing wet pipe sprinkler system to be modified as noted. |
Note: Where heads are planned within the areas served by new Ceiling Mounted Patient Lifts, pendant heads become a collision risk/hazard. Where this occurs, (white) Flat Concealed Pendant, gasketed clean room spec, Quick Response heads/gaskets such as Reliable Model G5 series have been successfully employed.
Ceiling Mounted Patient Lift w/ H, H&J, or J Track are by Guldmann. See corrected 11 73 00 and associated docs of amendment.
| 6.32 |
| Is the contractor responsible for providing a temporary fire protection system in the project area during construction? Is the contractor responsible for fire watch? |
| Yes. |
Review and comply with Scope of Work.
Review and comply with 01 35 26 Safety Requirements.
Review and comply with 28 31 00 Fire Detection and Alarm.
| 6.33 |
| SF101 Structural Design Calcs: Please confirm if the contractor is responsible for providing engineered design calculations for all structural steel work. |
| Delegated design drawings and calculations, such as structural connections, member shape, size, material grade, welded connections, fasteners size, grade, quantity, etc. are required to be signed and sealed by an Illinois licensed structural engineer. Submit credentials. |
Note that this is NOT the work of the Guldmann structural engineer per 11 73 00 Ceiling Mounted Patient Lift System.
| 6.34 |
| 12 24 00 Window Shades: Window Shades is included in the spec book; however, no window shades are shown in the drawing set or the finish schedule. Are new window shades intended to be part of this project? If so, please clarify what the window shades scope is. |
Provide specified window treatments for all windows.
| 6.35 |
| SF102 Repair Concrete Columns: SF102 shows a note indicating to repair concrete columns as required. Please clarify the current condition of the concrete columns for bidding purposes. Will the repairs be structural or cosmetic? |
The repairs are cosmetic.
| 6.36 |
| Lead Times: Will an administrative NTP or an extended POP be issued to account for long lead times on equipment? If not, there is no realistic way to complete this project within the POP of 235 days. |
| 52.211-10 -- Commencement, Prosecution, and Completion of Work is included within this set of documents not only by reference, but verbatim at 01 45 00. |
Contractor is required to plan and execute the work completely and compliantly within the stated period of performance. To achieve this, contractor procurement efforts are required to adhere to a schedule which completes the work within the stated period of performance.
Where prior to bid day a contractor has found no source in the market capable of delivering materials or systems to meet the POP, a time extension may be considered by the Contracting Officer only after Contractor submits unaltered, unfiltered, unredacted documentation showing that multiple sources were solicited, and regardless of price none are capable of meeting requirements under any circumstances.
The inability to acquire some material or system doesn’t automatically justify or necessitate an atypical award or NTP scheme, nor a time extension. While planning the work is the responsibility of the contractor, so too is planning to contract requirements for time, cost, and quality.
Some material or systems lead times are longer than they used to be, however, VA commonly observes Contractor procurement efforts failing to begin until long after NTP, and consuming exceedingly more time than reasonable as a result of efforts to find subcontractors and material sources willing to fit into their bid budgets. This conflicts with requirements of bidding contractors to submit a listing of all subcontractors shortly after award.
| 6.37 |
| Nurse Call: Is there a basis of design for the new nurse call system. |
| Basis of design is Ascom Telligence 6 Nurse Call backbone with the Legacy EZCare System by JCI. This is the existing system at the medical that needs to be matched. |
| 6.38 |
| 01 00 00 Vibration & Noise: Specification section 01 00 00 read “Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied.” This will be required for the demolition scope on this project. Please confirm use of tools and equipment that may cause vibrations and noises will be permitted for the demolition scope of this job. |
Review and comply with Scope of Work.
Review and comply with 01 00 00 General Requirements.
No noise within the work area shall be allowed to leave it. Do not interfere with normal functioning of the medical center.
| 6.39 |
| AI601 Finish Schedule - Base PT 2: Wall Base PT 2 is listed in the Room Finish Schedule but is not referenced on the Finish Schedule on sheet AI601. Please clarify what is being referenced in the room finish schedule by Wall Base Type "PT2." |
PT 2 is the wall base tile that matches floor tile PT1 for manufacturer and color.
All final colors to be selected by VA. Submit manufacturer’s full line (typ.).
| 6.40 |
| No question submitted. |
No question submitted.
| 6.41 |
| No question submitted. |
No question submitted.
| 6.42 |
| AE102 Wall Infills: Are the walls to be infilled (per AE102 KN 3) to be infilled with a typical gypsum and nonstructural metal framing assembly as detailed on page AE002? Or are these walls to be infilled to match existing clay tile with plaster finish. |
6/AE501 Typical Interior Infill Detail @ Clay Block.
| 6.43 |
| 07 84 00 Fire Inspection: Please confirm that the firestopping inspector must be hired by the prime contractor. Please provide report requirements as they are missing from the specification. Will before and after photos be required. |
| Review and comply with 07 84 00 Firestopping. |
Submit products, installers, and independent inspector per 1.5 Quality Assurance, and 3.5 Inspections and Acceptance of Work.
Submit the qualified inspector’s standard report content/format for compliance with ASTM E699 (current edition).
| 6.44 |
| Shower Pans: Are the new shower pans to be prefabricated or ceramic tile? |
| See ceramic tile at room finish schedule AI601. |
| No. |
| Contractor Questions, July 22, 2022 |
| Response |
| 7.1 |
| Please issue a specification for the schedule for this project. |
| Review and comply with Scope of Work. |
Detailed requirements are presented under Kick-Off Meeting Documentation.
As always, CPM schedules and Schedules of Values must align and total the bid value.
Do not include costs associated with non-work administrative activities inherent in the listed work items. Examples include mobilization, preparation of submittals, development of schedules and progress reports, general and activity-specific safety compliance, attendance of meetings, and similar administrative activities which would not occur without the line-item listed work items. 52.246-12 Inspection of Construction defines Work as “…materials, workmanship, and manufacture and fabrication of components”. Inherent in these are planning, communicating, procuring, and quality assurance and quality control, among other inputs. The Government cannot pay for what it has not inspected and accepted as compliant, or for activities which add no value to VA facilities. Front-loading proposals, bids, schedules of values, and line-item costs of cost-loaded CPM schedules with all manner of non-work items puts the Contractor, the Government, and the Bonding Company at otherwise avoidable risk associated with paying out more than the value of work in place should the work stop prior to completion. Administrative and managerial activities associated with each Work line item are required to be prorated into each line item, along with prorated overhead and profit.
| 7.2 |
| Please clarify what spaces will be available for contractor use for onsite storage |
| Review and comply with Scope of Work. |
Review and comply with 01 00 00 General Requirements.
No on-site office or storage containers shall be allowed. Provide just-in-time delivery and removal. Only store materials, tools, equipment, within the work area. Coordinate site logistics with the assigned COR.
Also see 1.6 Operations and Storage Areas (FAR 52.236-10).
| 7.3 |
| Will space be provided for project dumpster in area of construction? Will a fence be required around the dumpster? |
| Review and comply with Scope of Work. |
Scope of Work specifically requires construction dumpsters to be secured within a locked security fence, along with requirements for Construction Waste Diversion Reports, and more.
Location to be determined by the COR.
| 7.4 |
| Will the VA be providing an electronic submittal program, or is it expected that the general contractor provides this? Are there programs or software that is acceptable? |
| Review and comply with 01 33 23 Shop Drawings, Product Data, and Samples, and all submission requirements of all specifications. |
VA will not provide a web-based document management service, nor specifically require Submittal Exchange, however, whichever platform or method Contractor chooses to meet requirements, it cannot require government employees, or those of the AE, CxA, or other project team member to purchase or download software or applications. If the Government information security systems won’t allow VA staff to access the platform due to security issues (not uncommon), an alternative method of transmitting information is required.
Note that Procore is reportedly used successfully by contractors at Jesse Brown VAMC and Hines VAMC.
| 7.5 |
| Will there be a third-party commissioning agent provided by VA? |
| VA intends to, however, VA engagement of a CxA does not relieve Contractor of quality or testing requirements of the several specifications, including 01 00 00, 1.19, referencing 23 05 93. |
Do not confuse CxA duties with that of 23 05 93 Contractor-provided testing, adjusting, and balancing requirements.
Review and comply with 01 91 00 General Commissioning Requirements.
Review and comply with 23 08 00 Commissioning of HVAC Systems.
Review and comply with 26 08 00 Commissioning of Electrical Systems.
Review and comply with 27 08 00 Commissioning of Communications Systems.
Review and comply with 28 08 00 Commissioning of Electronic Safety and Security Systems
| 7.6 |
| With current material procurement lead times, should there be any time built into the project for timeframe? |
| 52.211-10 -- Commencement, Prosecution, and Completion of Work is included within this set of documents not only by reference, but verbatim at 01 45 00. |
Contractor is required to plan and execute the work completely and compliantly within the stated period of performance. To achieve this, contractor procurement efforts are required to adhere to a schedule which completes the work within the stated period of performance.
Where prior to bid day a contractor has found no source in the market capable of delivering materials or systems to meet the POP, a time extension may be considered by the Contracting Officer only after Contractor submits unaltered, unfiltered, unredacted documentation showing that multiple sources were solicited, and regardless of price none are capable of meeting requirements under any circumstances.
The inability to acquire some material or system doesn’t automatically justify or necessitate an atypical award or NTP scheme, nor a time extension. While planning the work is the responsibility of the contractor, so too is planning to contract requirements for time, cost, and quality.
Some material or systems lead times are longer than they used to be, however, VA commonly observes Contractor procurement efforts failing to begin until long after NTP, and consuming exceedingly more time than reasonable as a result of efforts to find subcontractors and material sources willing to fit into their bid budgets. This conflicts with requirements of bidding contractors to submit a listing of all subcontractors immediately after award, just as with bonds and insurance.
| 7.7 |
| Are all crane lifts for the mechanical space/roof areas required to occur on weekends? |
| Review and comply with 01 35 26 Safety Requirements. |
| 7.8 |
| GC101 Elevator Size: What are the dimensions of the elevator for contractor use. |
| Elevator Size. What are the dimensions of the elevator for contractor use? |
Verify In Field (VIF). Also see note at GC101.
| 7.9 |
| Spec 013526 Safety Requirements, 1.7, A. – please confirm that the Superintendent will be allowed to perform duties as SSHO. |
Review and comply with 01 35 26 Safety Requirements.
| 7.10 |
| Spec 013526 Safety Requirements, 1.7, A. – please confirm that the Superintendent is required to be full time on this project and not allowed to split time between multiple projects, even if on same facility. |
Review and comply with 01 35 26 Safety Requirements.
| 7.11 |
| Spec 013526 Safety Requirements, 1.9, B. – please confirm that the CSP or CSHT inspector must be an independent contractor or can this individual be someone employed by the GC organization. |
Review and comply with 01 35 26 Safety Requirements.
| 7.12 |
| Spec 12013526 Safety Requirements, 1.13, B. – please confirm that the TB testing is required to be completed only 1 time within 90 days prior to assignment and will not be required every 90 days for the duration of the project. |
Review and comply with 01 35 26 Safety Requirements and 01 35 33 Infection Control Requirements.
| 7.13 |
| 014535 Special Inspections, 1.3, A – no “Schedule of Special Inspections” has been included as an attachment as listed. Please confirm there are no special inspections required, or issue schedule as stated. |
| All material and testing requirements are to be provided by the Contractor. Disregard instances stating VA will retain services for such requirements. VA does, however, retain the right to engage independent sources for quality assurance, and hold Contractor responsible for noncompliant results. |
Specification describes duties of both the AE (Designer of-Record) and the GC’s CQC, QCM, independent testing sources, and requirements for their collaboration and communication.
GC is required to develop a complete listing of all submittals required of this project and submit that list as their Submittal Log. Contractor must methodically review each part of the Project Manual, and prepare their complete submittal log for submission and acceptance prior to being released to mobilize. Where inspections are prescribed, list the resulting reports as submittals to be fulfilled.
Example: 01 45 35 Section 1.4 Definitions, Paragraph L indicates that Cold Rolled Steel and Fire-Resistant Penetrations and Joints are specific types of construction to be inspected. Contractor shall provide inspections and reports are identified in the specifications.
Review and comply with Scope of Work.
Review and comply with 01 00 00 General Requirements.
Review and comply with 01 40 00 Quality Requirements.
Review and comply with 01 45 00 Quality Control.
Review and comply with 01 45 35 Special Inspections Review and comply with 01 45 29 Testing Laboratory Services
| 7.14 |
| For Phase 2 Afterhours in the lobby area & elevator space, is afterhours only weekends or is that weekend and night? |
| Review and comply with Scope of Work. |
Normal work hours are clearly stated in the SOW, as are restrictions on certain activities and areas. The work hours indicated in the drawings which conflict with that of the SOW are erroneous.
All costs associated with planning and executing the work are borne by the contractor.
“Overtime” is not work outside of the described normal working hours unless performed by workers who have already performed their regularly scheduled eight-hour day, which can be avoided with attentive planning. Shift differential incentives and the like are common, but not overtime.
| 7.15 |
| Is Edge Guard or similar product acceptable for use as temporary wall and containment? |
| Temporary Construction Partitions: |
Review and comply with 01 35 26 Safety Requirements.
Containments at opening in rated wall assemblies shall be planned and constructed to comply with the rating of the wall.
Review and comply with 01 35 33 Infection Control Requirements.
Edge Guard is among the manufacturers listed.
Also see GC101.
| 7.16 |
| Is the VA requiring any downtime between Phase 1 and Phase 2? |
| Work is programmed to be performed in sequence. Time between is a function of Contractor quality assurance and completing all requirements of the first phase. |
Review and comply with 01 00 00 General Requirements.
| 7.17 |
| Drawings GC 101, Detail 6 & INFECTION CONTROL PLAN NOTES #2: will the VA be providing the card reader and programming, or is GC to provide the card reader and programming? |
| Provide means supply and install, complete. Coordinate with source indicated in SOW. Final programming to be coordinated with VA. |
| 7.18 |
| The Specification Book table of contents lists 015719 Temporary Environmental Controls but it was not found in the issued documents. Please issue this specification. |
| See attached specification. |
| 7.19 |
| The Specification Book table of contents lists “Appendix A” – Lovell Asbestos & Hazmat Testing Report” but it was not found in the issued documents. Please issue this Appendix. |
| See attached report. |
| 8.1 |
| 01 00 00 General Requirements |
3. Page 29: Please clarify the “Number of photographs” matrix listed there.
Requirements for Photographic Documentation of the work as it progresses is a function of construction cost. Contractor is also required as part of Daily Reports within the Scope of Work – and FAR/VAAR* to provide photos of the work as it progresses. The subject matrix was inadvertently retained in the specification.
*VA Form 10101 Contractor Production Report (VAAR 853.236-79; 826.7001(c)) available in fillable PDF form at https://www.va.gov/vaforms/va/pdf/VA10101.pdf is required to be submitted each day. On days with no activity, that is what is reported.
B. This solicitation includes NAICS 236220 General Construction with a Small Business Size Standard of $39.5M. In accordance with solicitation requirement VAAR 852.219-77(d) VA Notice of Limitations on Subcontracting – Certificate of Compliance for Services and Construction (SEP 2021)(Deviation), each offeror IS REQUIRED TO SUBMIT A CERTIFICATION WITH THEIR OFFER. Reference Solicitation Attachment 8. A copy is attached to this Amendment.
The bid opening date, time and in-person location has been extended from Friday, August 5, 2022 to Monday, August 8, 2022 at 13:00 CST. The location remains as follows: been changed from the details below.
Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S. 84th Street, Suite 101 Milwaukee WI 53214-1476
Attachment(s)
See attached document: S06 36C25222B0022 0003 Att1_Roof Warranties Bldg 134 B135 B187.
See attached document: S06 36C25222B0022 0003 Att2_Roof Warranty Bldg 134 Courtyard 3 season metal roof.
See attached document: S06 36C25222B0022 0003 Att3_SOL_Att08 556-20013 VAAR 852.219-77 Certification.
See attached document: S06 36C25222B0022 0003 Att4_Appx A - FHCC Asbestos _ Hazmat Testing Report.
See attached document: S06 36C25222B0022 0003 Att5_Spec 015719 - Temporary Environmental Controls.
36C25222B0022 0003 Page 18 of 18