S06 - Att 2 RFIs Repair Water Intrusion at B400 dated 5-2-22.pdf

PDF 3 MB Posted

Attached to
Z1DZ--REPAIR WATER INTRUSION B400 676-22-113
Solicitation number
36C25222B0017
Issued by

About this file

This document contains a solicitation for a federal construction project and related request for information responses. The solicitation is for repairs to Building 400 at the Tomah VA Medical Center in Tomah, Wisconsin, including seal and tuck-pointing of brick, roof replacement, exterior painting, heat tape replacement, gutter repair, and cupola restoration. The period of performance is 200 days with a bid opening scheduled for March 21, 2022. The project value is estimated between $2-5 million. The solicitation is set aside for verified Service-Disabled Veteran-Owned Small Businesses. The responses provide additional details on the scope of work requirements and material specifications in response to contractor questions.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

No. RFI From COMMENT Response 1 RHI In the scope of work, Tasks 2-2 line e in states to "Insulation on sloped roofs to be sprayed up to 4.5" of spray to achieve min of R-30" Is the intent to insulate the roof system from below or above? There is nothing in the roofing plans that can show this system, or is this a miss type for this section?

The rafters are currently open and exposed from the inside, allowing them to spray from the inside. Note some areas the contractor will need to walk through CLC areas to access

2 RHI How many layers of shingles are installed on the existing roof, by type? A single layer 3 RHI What is the composition of the existing roof deck? Asphalt 4 RHI What is the board foot approximate measurement for the spray foam to be applied? Spray foam drawing with locations added also attached pictures of existing formed areas 5 RHI The specifications call out for the roofing flashing be copper. At the site visit it was discussed that the existing flashing is aluminum.

Please confirm what material is preferred.

During the bid the COR said to the group that we maybe able to change to Aluminum. THIS IS NOT THE CASE Due to Historical Requirements and longevity of the copper WE WILL STAY WITH COPPER

6 RHI Is the spray foam insulation required to be fire proofed? Yes spray has to meet NFPA (national fire protection association) standards

7 Dennis Bedell Contracting All verbal items discussed during bid walk through such as round top window replacement, spray foam insulation, limestone repairs to include retaining walls and any other items not noted on the plans or specs how will those be addressed?

Refer to scope of work Memorandum

8 Dennis Bedell Contracting What will the payment schedule look like for the awarded bidder? Monthly depending on contractor progression 9 Dennis Bedell Contracting There is an electrical spec noted but nothing was discussed about this portion besides heat tape. Is there additional electrical work needed or required?

Will wire to junction boxes / controller

10 Dennis Bedell Contracting Power to job trailers who is responsible for this hook up and where can it be run from? Contractor TRAILER POWER 11 Dennis Bedell Contracting Building permits is the GC required to pull a building permit or is there a state agreement for VA projects that one is not required? And if one is needed can the cost be via change order as actual cost would not currently be known. Also if permit is required do plans need to be submitted to the state for review it has this been completed prior?

No building permit required the only permits required are for historical. The shingles are pre-approved so no pre-approval is needed from historical.

12 Dennis Bedell Contracting Lead and Asbestos testing were completed on areas to be renovated? And if so can a copy be provided for review and filing.

If not whom will be responsible for that testing?

No known hazardous material are known in the construction space. If hazardous materials are found, they will need to contact the COR. The shingles were replaced less than 10 years ago and nothing was found then. A preliminary Lead and Asbestos report is attached in the document.

13 Dennis Bedell Contracting If awarded the project can the project be started sooner that noted? Yes, the VA would like to start this project as soon as possible 14 Dennis Bedell Contracting Who is responsible for any landscaping that needs to be repaired or replaced from working being performed? PER SOW Additional requirements C: Contractor must protect buildings and grounds in contact and around from damage during their construction and or project.

I. If buildings or adjacent grounds are damaged, they will need to be repaired with like kind before project completion.

15 Dennis Bedell Contracting If there is roof decking that is damaged below roof surface can it be a change order or are we to assume replacement of all roof decking?

Yes a change order will be issued for bad roof decking

16 Dennis Bedell Contracting Brick repairs seem to be greater than 25% based on walk-thru. Do we just bid up to a 25% repair and change order at the time of overage and site verification during repairs?

Follow the SOW and change orders will be needed after the 25%

17 Dennis Bedell Contracting Lead times on certain materials are going to be a potential issue. For example EPDM rubber currently has a long lead time in excess of 6 months or more in some cases. With knowing this the 120 days to complete the project is going to be difficult because of this. Will there be an extension grated due to product availability delays on items that cannot be completed within the allotted time frame?

The Period of Performance will be extended to 200 Days. A stop work can be issued for materials and winter conditions so long as no cost to the government.

Tomah VAMC Repair Water Intrusion B400 - 676-22-113 36C25222B0017 Pre-Bid RFIs

36C25222B0017 RFIs ‐ Tomah VAMC Repair Water Intrusion B400 ‐ 676‐22‐113

18 Dennis Bedell Contracting Repair/replacement of limestone sills and parapet wall caps not being completely identified and will be more of an onsite verification on repair. Can an assumed allowance be bid and a change order to follow once actual extent of repairs are known based on field verification?

Contractor will estimate replacement of 10 of the worst limestone sills. And fix 30 cracked limestone sills by cutting and Caulking see pictures attached.

A change order will be needed for additional sills priced per sill. Wall caps the contractor was given opportunity to walk around building and portion of roof area to estimate

19 Dennis Bedell Contracting Are we to bid power washing all exterior brick and limestone? yes the whole building plus front steps and patio area 20 Dennis Bedell Contracting Do we need to provide bid for the temporary fencing and associated costs? all fencing must be covered by the contractor 21 Dennis Bedell Contracting Do we need to provide pricing for scaffolding around the building, is a scaffolding detail required? It is means and methods if you choose to use scaffolding a detail will need to be provided 22 Dennis Bedell Contracting Where do we allocate costs for logistical items; dumpster, job trailers, temporary toilets, etc.…..? Please consult the FAR. Most of the items you identify fall in the Division 01 -

GENERAL REQUIREMENTS

23 Dennis Bedell Contracting “Work needs to be compliant with ASHRAE 90.1-2019”, need further details regarding this requirement. Review the ASHRE specification for clarification 24 Dennis Bedell Contracting “Contractor shall provide labor, material, and equipment necessary to accomplish the following work on Building 400 in accordance with federal, state, and local authorities, VA master construction specifications and the requirements of the Wisconsin State Historic Preservation Office.” Need to know the specifics of this requirement for proposal alignment.

Completed work must meet the specifications & also there manufactures installation requirements

25 Dennis Bedell Contracting “Replace and Paint all attic windows match existing color,” does the VA have a detail and/count of the windows? How do we propose otherwise?

4 attic 1/2 moon windows, all windows will need to be individually measured as they are custom fit to opening, no details are available but a picture is provided in the sow. The approximate width is 44.5" and height is 24.5".

26 Dennis Bedell Contracting Cupola, “Paint all exterior trim as needed,” do we just propose to paint all wood trim, define as needed? refer to scope of work Memorandum task 6 27 Dennis Bedell Contracting Cupola, “Repair tower brick and surfaces as required,” is there a detail of requirements? Refer to seal and tuck opining task 1 as all brick tuck pointing will be considered that task. If exceeding the 25% additional quote will be needed as indicated in the SOW

28 Dennis Bedell Contracting Cupola, “Seal copper/lead clad roofing as required,” is there a detail of requirements? See Cupola drawing sealing estimated to be 90 linear feet 29 Dennis Bedell Contracting Cupola, “Replace boards as required,” is there a detail of requirements? See Cupola drawing estimated replacement of rotten and or weathered boards to be an estimated 100 linear feet.

30 Dennis Bedell Contracting Cupola, “Inspect tower exterior for additional damage and repairs,” is this a supplemental proposal additional to the awarded bid?

Estimate that 25% will need repair/replacement.

31 Dennis Bedell Contracting What happens in the event that our designated staging areas aren’t sufficient enough for our equipment, vehicles, materials, and other related items.

An off site location will need to source from the contractor

32 Dennis Bedell Contracting What is the wall square footages? Needed to properly propose exterior power washing. Refer to drawings elevation and perimeter dimensions were provided (see roof and tuck pointing drawings)

33 Melanie Frandsen Task #5, Item b) Replace all gutter liners.

Replace existing liners with what material?

What are the existing gutters lined with?

Install EPDM GUTTER LINING SYSTEM per manufactures installation requirements.

Not know what gutters are currently lined with as over 40 years old.

34 Melanie Frandsen Task #5, Item c) Downspouts’ connections are leaking between liner and downspout.

i. Fix by resealing between downspout and gutter

ii. Also fix by lining the gutter liner down the downspout to ensure water seal between gutter and downspouts.

The existing downspouts appear to be lined.

If so, what material are the lined with?

Will the gutter lining material adhere to the pipe lining?

The existing downspouts appear to be lined. Yes they are lined.

If so, what material are the lined with? Pipes are lined with biaxial weave fabric and silicate based epoxy.

Will the gutter lining material adhere to the pipe lining? I would think so but this would need to be verified with manufacture of epdm material

35 Zachary Blenkinsopp Task #2-4 Remove, clean, and replace all capstone joints.

a) Remove, clean, and replace all cap joints per specifications.

Does that imply all cap blocks need to be removed or just the sealant?

Implies to all capstone joints only as the capstone repair is called out on task #1-4 "Repair all limestone caps and window limestone.

a) Repair limestone by pining and patching with color matched epoxy

b) All limestone caps and window limestone surfaces to be sealed."

36 Zachary Blenkinsopp What are the specific scaffolding requirements for the project?

For example, is it required to have the entire building wrapped in scaffolding during the project or can we use scaffolding only during a phase of the building?

Scaffolding must meet osha and requirements, scaffolding can be phased without affecting patient safety

5‐2‐22 RFIs Repair Water Intrusion at B400 2 of 3

36C25222B0017 RFIs ‐ Tomah VAMC Repair Water Intrusion B400 ‐ 676‐22‐113

37 Zachary Blenkinsopp Ridge Vent for bldg. 400?

There seems to be ridge vent installed on the new addition but none of the main bldg. 400.

Is this something that needs to be installed with the new synthetic slate roofing system?

Yes per manufactures specifications, please see hip and ridge detail on product specifications instatllation sheet.

https://westlakeroyalroofing.com/wp-content/uploads/boral-resource/Classic- Slate-Installation-Guide-0820.pdf

38 Zachary Blenkinsopp - Would it be possible for an extension for construction time to one year after the Notice to Proceed (currently 120 days)? The EPDM that is in the SOW will likely take 3-6 just to order and would make finishing this project in a 120 day timeframe almost impossible.

The Period of Performance will be extended to 200 Days. A stop work can be issued for materials and winter conditions so long as no cost to the government.

5‐2‐22 RFIs Repair Water Intrusion at B400 3 of 3

Photo of existing areas that already have some spray foam.

S06 - Att 2 RFIs Repair Water Intrusion at B400 dated 5-2-22
S06 - Drawing B400 Roof Spray Foam Area 676-22-113 A106
S06 - Photo of area with existing spray foam
S06 - ACM Spreadsheet Inventory