S06 - Att 02 - Inspection Summary Report Bldg 48 - 2010.pdf

PDF 35 KB Posted

Attached to
Z1DA--578-21-028 Replace Building 48 Roof System (VA-21-00077419)
Solicitation number
36C25221B0025
Issued by

About this file

This document contains an inspection summary report for Building 48 at the Edward Hines Jr. VA Hospital and a pre-solicitation notice for replacing the roof system of Building 48.

The inspection summary report details the findings of an asbestos reinspection conducted in September 2010, which found asbestos-containing floor tile and pipe insulation throughout the building. The report recommends continuing operation and maintenance programs and preparing an asbestos removal design plan for any renovations that could impact asbestos-containing materials.

The pre-solicitation notice provides advance information for a forthcoming solicitation to replace the roof of Building 48, with objectives of removing existing roof units and assemblies, replacing scuppers, and installing a new roof system. The period of performance is 120 calendar days from notice to proceed. The solicitation will be set aside for service-disabled veteran-owned small businesses and issued on or about July 16, 2021, with bids due on or about August 17, 2021. The requirement value is estimated between $500,000 and $1,000,000.

View the file

Other files

File Type Posted
36C25221B0025 0003.docx DOCX document
S06 - Att 01 - Wage Determination 08_13_2021.pdf PDF
36C25221B0025 0002.docx DOCX document
S06 - Att 02 - 22 14 00.pdf PDF
S06 - Att 01 - Wage Determination 07_30_2021.pdf PDF
S06 - Att 01 - STC-028211.pdf PDF
S06 - Att 03 - BLDG 48 REEVALUATION 2010.pdf PDF
36C25221B0025 0001.docx DOCX document
14) No Smoking Policy 10-1-19.pdf PDF
16) Hines COVID-19 Guidelines.pdf PDF
1) Hines VA Campus Site Plan.pdf PDF
SOW 578-21-028 Replace Building 48 Roof System.pdf PDF
17) Drawing Specifications 578-21-028.pdf PDF
11) Contractor Parking.pdf PDF
4) Safety and Health During Construction Activities.pdf PDF
10) Contractor PIV Instructions and Form.pdf PDF
6) Above Ceiling Entry and Wall Construction Permits.pdf PDF
15) Infection Control Barrier Sample.pdf PDF
P07 Wage Determination.txt TXT text file
Wage Determination 7-14-2021.pdf PDF
12) OIT Horizontal Cable Requirements.pdf PDF
36C25221B0025.docx DOCX document
3) Pre-Construction Checklist.pdf PDF
2) Hines Underground Utility Plan.pdf PDF
13) Specifications Book.pdf PDF
18) Pre-Existing Site Photos.pdf PDF
8) Interim Life Safety Measures (ILSM).pdf PDF
5) Cutting Welding and Other Hot Work.pdf PDF
7) Pre-Construction Risk Assessment (PCRA).pdf PDF
9) Infection Control Risk Assessment (ICRA).pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

48-1

BUILDING 48

INSPECTION SUMMARY

In September 2010, an asbestos re-inspection of Building 48 was conducted by MC Consulting Inc. (MC2).

The asbestos re-inspection was conducted by an Illinois Department of Public Health (IDPH) Licensed

Asbestos Building Inspector, Roberto Rivera (IDPH License No. 100-06327). A copy of the inspector’s license is provided in the Appendix.

Prior to the field inspection, the following document was reviewed.

* 2006 asbestos re-inspection for Building 48

The 2010 asbestos re-inspection was performed on the basis of the 2006 re-inspection information. The following activities were observed and performed.

* Building 48 houses the Hines VA laundry distribution system, and several rooms are used for storage by the Jesse Brown VA.

* Overall suspect asbestos-containing materials (ACM) were found in good condition at the time of the inspection.

* Asbestos pipe insulation is likely to be concealed behind walls, within suspended or plaster ceilings, or in other inconspicuous locations throughout the building.

* The findings of the 2010 re-inspection are summarized in the 2010 reevaluation tables.

Abatement History:

* Based on the 2006 asbestos re-inspection findings, no information was found regarding any asbestos abatement for Building 48.

48-2

BUILDING 48

RECOMMENDATIONS

Floor Tile

The 12” x 12” white with green and gray streaks tile and the 9” x 9” floor tile and mastic were in good condition at the time of the inspection. These materials were found to contain asbestos according to previous reports. These materials may be accessible to building occupants and maintenance personnel. It is recommended that the Hines VA continue to monitor the condition of this material under an Operation and Maintenance (O&M) Program. These materials can remain in place until major renovation or demolition requires their removal.

Pipe Insulation

Asbestos pipe insulation and associated fittings were in good condition at the time of the inspection. These materials were found to contain asbestos according to previous reports. These materials may be accessible to building occupants and maintenance personnel. Suspect ACMs are likely to be concealed behind walls, within suspended or plaster ceilings, or in other inconspicuous locations throughout the building. These materials can remain in place until major renovation or demolition requires their removal.

General Recommendations

The Hines VA should continue to follow its Asbestos Management Plan’s (O&M) Program. It is also recommended that Hines VA prepare an Asbestos Removal Project Design prior to initiating any renovation activities in which ACM may be impacted. The asbestos design plan and specifications should be prepared and signed by an IDPH-licensed Asbestos Project Designer in accordance with IDPH and federal regulations. Asbestos abatement work should be conducted by a licensed abatement contractor under the supervision of a licensed Asbestos Project Manager, in accordance with all applicable federal, state, and local regulations.

File details come from the government source that posted it. Updated .