Revised and Final Specs.pdf
PDF 12 MB Posted
- Attached to
- Z2NB--Project No. 539-20-101 - Replace Fort Thomas Boilers. Federal contract opportunity
- Solicitation number
- 36C25024B0075
About this file
This summary cannot be generated as the provided file appears to be a reference only to "Revised and Final Specs.pdf" without containing the actual content of the document. While we know this file relates to a VA contracting opportunity for replacing boilers at Fort Thomas (Project No. 539-20-101), the actual specifications document is not provided for review and summary.
View the file
Other files for this federal contract opportunity
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VAMC Project # 539-20-101 LPA Project No. 202125.00 Construction Documents Levin Porter Associates Inc.
REPLACE FTD BOILERS WITH HOT WATER SYSTEM
AT
FT THOMAS DOMICILIARY BUILDING 64
539-20-101
TECHNICAL SPECIFICATIONS
Prepared By:
November 2024
VA CINCINNATI PROJECT # 539-20-101
10-01-22
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 01-24
01 33 23 Shop Drawings, Product Data, and Samples 11-23
01 35 26 Safety Requirements 05-24
01 42 19 Reference Standards 11-20
01 45 29 Testing Laboratory Services 11-18
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 04-22
01 81 13 Sustainable Construction Requirements 10-17
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 11 Asbestos Abatement 01-21
02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 01-21
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18
05 31 00 Steel Decking 01-21
05 40 00 Cold-Formed Metal Framing 01-21
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 Thermal Insulation 01-21
07 22 00 Roof and Deck Insulation 01-21
00 01 10-2
07 24 00 Exterior Insulation and Finish Systems 01-21
07 51 13.13 Cold Applied Built-Up Bituminous Roofing 12-21
07 60 00 Flashing and Sheet Metal 01-21
07 71 00 Roof Specialties 01-21
07 72 00 Roof Accessories 01-21
07 81 00 Applied Fireproofing 10-17
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
DIVISION 08 - OPENINGS
08 51 13 Aluminum Windows 01-21
08 80 00 Glazing 01-21
08 90 00 Louvers and Vents 01-21
DIVISION 09 – FINISHES
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 51 00 Acoustical Ceilings 12-18
09 67 23.60 Resinous Urethane and Epoxy Mortar Flooring (RES-6A and RES 6B) 01-21
09 91 00 Painting 01-21
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
21 13 16 Dry-Pipe Sprinkler Systems 01-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 09-20
22 05 12 General Motor Requirements for Plumbing Equipment 09-20
22 05 19 Meters and Gages for Plumbing Piping 09-20
22 05 23 General-Duty Valves for Plumbing Piping 09-20
22 05 33 Heat Tracing for Plumbing Piping 09-20
22 07 11 Plumbing Insulation 09-19
22 08 00 Commissioning of Plumbing Systems 11-16
22 11 00 Facility Water Distribution 05-21
22 13 00 Facility Sanitary and Vent Piping 09-20
22 14 29 Sump Pumps 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
(HVAC)
23 05 10 Common Work Results for Boiler Plant and Steam Generation 04-20
23 05 11 Common Work Results for HVAC 04-22
23 05 12 General Motor Requirements for HVAC and Steam Generation Equipment 02-20
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 02-20
00 01 10-3
23 05 51 Noise and Vibration Control for Boiler Plant 03-22
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20
23 07 11 HVAC and Boiler Plant Insulation 02-20
23 08 00 Commissioning of HVAC Systems 04-22
23 08 11 Demonstrations and Tests for Boiler Plant 04-20
23 09 11 Instrumentation and Control for Boiler Plant 03-22
23 09 23 Direct-Digital Control System for HVAC 09-11
23 21 11 Boiler Plant Piping Systems 09-22
23 21 13 Hydronic Piping 02-20
23 21 23 Hydronic Pumps 02-20
23 23 00 Refrigerant Piping 02-20
23 25 00 HVAC Water Treatment 02-20
23 31 00 HVAC Ducts and Casings 02-20
23 34 00 HVAC Fans 02-20
23 37 00 Air Outlets and Inlets 02-20
23 50 11 Boiler Plant Mechanical Equipment 03-22
23 51 00 Breechings, Chimneys, and Stacks 04-20
23 52 33 Water Tube Boilers 03-22
23 64 00 Packaged Water Chillers 03-20
23 81 00 Decentralized Unitary HVAC Equipment 03-20
23 81 43 Air-source Unitary Heat Pumps 03-20
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 05 73 Overcurrent Protective Device Coordination Study 01-18
26 08 00 Commissioning of Electrical Systems 11-16
26 09 23 Lighting Controls 01-18
26 24 16 Panelboards 01-18
26 27 26 Wiring Devices 01-18
26 29 11 Motor Controllers 01-18
26 29 21 Enclosed Switches and Circuit Breakers 01-17
26 41 00 Facility Lightning Protection 01-17
26 43 13 Surge Protective Devices 01-17
26 51 00 Interior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS 09-19
27 10 00 Structured Cabling 12-22
27 13 13 Communications Copper Backbone Cabling 12-22
27 13 13.13 Communications Copper Cable Splicing and Terminations 12-22
27 13 23 Communications Optical Fiber Backbone Cabling 12-22
27 13 23.13 Communications Optical Fiber Splicing and Terminations 12-22
27 15 13 Communications Copper Horizontal Cabling 12-22
00 01 10-4
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 31 00 Fire Detection and Alarm 10-11
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 31 13 Chain Link Fences and Gates 06-18
32 90 00 Planting 08-16
VA CINCINNATI PROJECT NO. 539-20-101
05-01-20
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Sheet List Sheet Number Sheet Name
G001 TITLE SHEET
G002 GENERAL NOTES AND SITE LOGISTICS
G003 LIFE SAFETY PLANS
AD100 BASEMENT DEMOLITION PLAN
AD104 PENTHOUSE PLAN DEMOLITION
A100 BASEMENT PLANS
A101 TEMPORARY BOILER AND FENCE
A104 PENTHOUSE PLAN
A105 PENTHOUSE ENLARGED PLAN WITH DETAILS
S001 GENERAL STRUCTURAL NOTES
S104 ROOF FRAMING PLAN
S201 DETAILS
S202 SLAB PLAN, DETAILS, AND ELEVATIONS
F001 ABBREVIATIONS, SYMBOLS & INDEX OF DRAWINGS
FX100 MECHANICAL ROOM PLAN - FIRE SUPPRESSION
FX104 PARTIAL PENTHOUSE PLAN - FIRE SUPPRESSION
P001 ABBREVIATIONS, SYMBOLS & INDEX OF DRAWINGS
PS100 SITE PLAN
PD100.1A MECHANICAL ROOM PLANS - TEMPORARY PLAN
PD100.2A MECHANICAL ROOM PLANS - REMOVALS
PL100 MECHANICAL ROOM PLANS - DRAINAGE
PP100 MECHANICAL ROOM PLAN - DISTRIBUTION
P501 DETAILS & SCHEDULES
P701 DIAGRAMS
M001 ABBREVIATIONS, SYMBOLS, INDEX AND GENERAL NOTES
MD100 PARTIAL BASEMENT FLOOR PLAN - TEMPORARY PLAN REMOVALS
MD100.1 PARTIAL BASEMENT FLOOR PLAN - TEMPORARY WORK
00 01 15 - 2
MD400 ENLARGED BASEMENT FLOOR PLAN- REMOVALS
MD403 ENLARGED THIRD FLOOR PLAN - REMOVALS
MD404 ENLARGED ROOF AND PENTHOUSE PLAN - REMOVALS
MH400 ENLARGED BOILER ROOM - NEW WORK
MH400.1 PARTIAL BASEMENT FLOOR PLAN CONTROLS - NEW WORK
MH402 ENLARGED SECOND FLOOR PLAN - NEW WORK
MH403 ENLARGED THIRD FLOOR PLAN -NEW WORK
MH404 ENLARGED PENTHOUSE PLAN - NEW WORK
M201 STEAM BOILER PLANT ELEVATIONS
M501 DETAILS
M502 DETAILS
M503 DETAILS
M504 DETAILS
M505 DETAILS
M506 DETAILS
M507 CHILLED WALTER PIPING SCHEMATIC
M508 STEAM BOILER SCHEMATIC - REMOVALS
M509 STEAM BOILER SCHEMATIC - NEW
M601 SCHEDULES
M602 SCHEDULES
M603 SCHEDULES
M604 PIPING SUPPORT SYSTEMS
M701 CONTROL DIAGRAMS AND SEQUENCES
M702 CONTROL DIAGRAMS AND SEQUENCES
M703 CONTROL DIAGRAMS AND SEQUENCES
M704 CONTROLS DIAGRAMS AND SEQUENCES
M901 STEAM BOILER PLANT ISOMETRIC
E001 ABBREVIATIONS, SYMBOLS & INDEX OF DRAWINGS
ED100A PARTIAL BASEMENT PLAN - REMOVALS
ED104B PARTIAL ROOF PLAN - REMOVALS
EL100A PARTIAL BASEMENT PLAN - LIGHTING
EL104B PARTIAL ROOF PLAN - LIGHTING
00 01 15 - 3
EP100.1A PARTIAL BASEMENT PLAN - TEMPORARY BOILER
EP100A PARTIAL BASEMENT PLANS - POWER
EP104 PARTIAL ROOF PLAN - POWER
E501 DETAILS
E601 ELECTRICAL SINGLE LINE - NORMAL POWER
E602 ELECTRICAL SINGLE LINE - EMERGENCY POWER
E701 PANEL SCHEDULES
- - - END - - -
01-01-21
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for VA PROJECT # 539-
20-101 REPLACE FTD BOILERS WITH HOT WATER SYSTEM as required by drawings and specifications.
B. A bid walk through shall be scheduled by COR.
C. Offices of Levin Porter Associates, Heapy Engineers as Architect-Engineers, as
Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by
Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
F. Prior to commencing work, general contractor shall provide proof that an OSHA designated
“competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
G. Training:
1. All employees of general contractor or subcontractors shall have the 10-hour or 30-hour
OSHA Construction Safety course and other relevant competency training, as determined by
01 00 00 -2
COR acting as the Construction Safety Officer with input from the facility Construction Safety
Committee.
2. Submit training records of all such employees for approval before the start of work.
H. Photo ID:
1. During the performance of this contract, the contractor’s personnel shall conduct themselves in a professional manner, wear clean, neat clothing, and be identified by displaying a photo identification furnished by the VA. The contractor is responsible for coordinating with the VA
Police Service to obtain these ID badges for all personnel working on the project. All personnel working on this project must submit a REQUEST FOR PERSONAL IDENTITY
VERFICATION CARD form 0711, be fingerprinted, and read and sign the Cincinnati
Contractors Summary Construction Training Pamphlet at least 2 weeks prior to starting work on the premises. All badges must be turned back into the VA at project completion.
2. The general contractor is required to obtain an “Above Ceiling Work Permit” from the project engineer for this project and must be responsible for all that it requires. A copy of the permit and policy is attached at the end of this specification section
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION:BASE BID:
Work will include all labor, materials, equipment and supervision required to complete the project
REPLACE FTD BOILERS WITH HOT WATER SYSTEM in the Hospital, at the Department of
Veterans Affairs Medical Center, FORT THOMAS, KENTUCKY.
1. Work includes the replacement of the existing steam boilers, boiler room equipment, boiler room system piping, breeching, controls, electrical and technology work. Existing steam boilers will be replaced with field erected low pressure watertube steam boilers. The existing condensate receiver, transfer pumps, deaerator, and feedwater pumps will be replaced with an atmospheric feedwater system. Work includes upgrades and replacement to plumbing system required for the replacement boilers, including underground sanitary system, modifications to the existing natural gas, propane, fuel system and vents, water piping, and other systems required for the boiler system.
2. Scope also includes the replacement of the existing chillers, and chiller room equipment, and chiller room piping, chiller room refrigerant exhaust system, controls, electrical and technology work. Work includes the enlargement and expansion of the existing chiller room.
01 00 00 -3
It also includes modification of the chilled water system from constant volume to variable primary, with replacement of existing 3-way controls valves. Chilled water scope also includes modification to air handler AH-2 ductwork, rebalancing, and exhaust system.
3. Work shall include a temporary boiler system and shall be phased to minimize outages and disruptions to the facility heating and cooling system as described on the technical specifications and drawings.
4. All phases of work including close out documents shall be complete within 913 calendar days after receipt of Notice to Proceed.
B. ITEM II, (DEDUCT ALTERNATE NO.1): BASE BID except delete the work listed below:
1. All equipment list in Specification Section 23 81 43, Air Source Unitary Heat Pumps.
2. All phases of work including close out documents shall be complete within 913 calendar days after receipt of Notice to Proceed.
C. ITEM III, (DEDUCT ALTERNATE NO.2): Bid Item 2 except delete the work listed below:
1. Entirety of the steam boiler and heating system replacement including, but not limited to, boilers, deaerator, blow down, controls, steam piping, electrical, plumbing, fire suppression and technology systems associated with the work in Room 029 (and associated services).
2. Work associated with modifications to the chimney for boiler flue and piping to the roof for venting.
3. Replacement of windows, fencing, piping, site prep, concrete pad, utilities and procurement/rental of temporary boiler.
4. All phases of work including close out documents shall be complete within 609 calendar days after receipt of Notice to Proceed.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
01 00 00 -4
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge.
They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting
Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting
Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General
Contractor’s employees off the premises in the event of a national emergency. The General
Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
01 00 00 -5
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law
Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Fire Safety
1. Smoking : Tobacco products are prohibited on VA campus.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. There will be no parking by any Contractors on the Cincinnati VA Campus
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the
Contractor only with the approval of the Contracting Officer and shall be built with labor and
01 00 00 -6 materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the
Contractor at its expense upon completion of the work. With the written consent of the
Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:
01 00 00 -7
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the
Contractor.
H. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR and Contractor, as follows:
I. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment.
In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
J. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems
(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
01 00 00 -8
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR
ELECTRICAL INSTALLATIONS, for additional requirements.
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 28 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center.
Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 28 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR.
Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the
Contractor.
K. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
L. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. All
01 00 00 -9 potential tripping hazards present from the fence shall be removed or protected as directed by the COR.
M. Contractor shall submit a request to interrupt any such services to COR, in writing, 21 days in advance of proposed interruption. Major interruptions of any system must be requested, in writing, at least 28 calendar days prior to the desired time.
N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the
Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and
COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-
4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a
01 00 00 -10 report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
01 00 00 -11
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
1.10 RESTORATION
. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work.
Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR.
Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
A. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.)
disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
B. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of
01 00 00 -12 utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
C. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version
(scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term
“status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work.
The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
01 00 00 -13
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
01 00 00 -14
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the
Contractor shall respond in a timely manner. Written verification will follow oral instructions.
Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the
Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service Requirements:
E. Following oral or written notification by the Contracting Officer, the Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty
Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the
01 00 00 -15 cause of the problem, date reported, corrective action taken, and when the repair was completed.
If the Contractor does not perform the construction warranty within the timeframe specified, the
Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
1. The “Construction Warranty Service Priority List” is as follows:
a) Code 1-Life Safety Systems
Fire suppression systems.
Fire alarm system(s).
b) Code 1-Electrical
Power failure (entire area or any building operational after 1600 hours).
Security lights.
Smoke detectors.
c) Code 2-Electrical
Power failure (no power to a room or part of building). Receptacle and lights not operational (in a room or part of building).
d) Code 3-Electrical
Exterior lights not operational.
e) Code 3-Interior
Floors damaged.
Paint chipping or peeling.
01 00 00 -16
Casework damaged.
f) Code 3
All work not listed above.
F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
Warranty Tags
Type of product/material
Model number
Serial number
Contract number
Warranty period from/to
Inspector’s signature
Construction Contractor
Address
Telephone number
Warranty Contact
Address
Telephone number
Warranty response time priority code
SPEC WRITER NOTE: Determine necessary paragraphs from below and delete non-applicable portions.
1.13 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor
01 00 00 -17 at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.14 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National
Electrical Code, (2014 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use;
maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government. Boilers, pumps, feedwater heaters and auxiliary equipment must be operated as a complete system and be fully maintained by operating personnel. Boiler water must be given complete and continuous chemical treatment.
01 00 00 -18
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
1.15 TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing elevators for handling building materials and Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the COR for use of elevators. The COR will ascertain that elevators are in proper condition. Contractor may use elevators in Building
Nos. 1 for for special nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of Veterans Affairs.
2. Contractor covers and provides maximum protection of following elevator components:
a) Entrance jambs, heads soffits and threshold plates.
b) Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c) Finish flooring.
3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractors expense.
1.16 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
01 00 00 -19
1.17 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the
Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the
Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the
Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1. Obtain heat by connecting to Medical Center heating distribution system.
a. Steam is available at no cost to Contractor.
D. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The
Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat.
Electricity for all other uses is available at no cost to the Contractor.
E. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted.
Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of…