S06 36C25024B0066 0003 - 515-22-101.pdf
PDF 236 KB Posted
- Attached to
- Z1DA--Renovate Restrooms 515-22-101
- Solicitation number
- 36C25024B0066
About this file
This document is an amendment to Solicitation 36C25024B0066 for a contract to Renovate Restrooms at the VA Medical Center in Battle Creek, Michigan (Project 515-22-101). The amendment provides answers to questions from potential offerors regarding the project requirements.
The key details are:
- The project involves renovating restrooms at the VAMC Battle Creek, including demolition, new construction, and abatement of suspected lead-based paint and asbestos-containing materials.
- The contract will be a firm-fixed price awarded to a Service-Disabled Veteran-Owned Small Business (SDVOSB). The estimated project cost is between $2-5 million.
- The period of performance is 380 calendar days. Contractors will be given access to one restroom per building at a time, with the ability to proceed to the next area once the initial work is accepted. Coordination with the COR will be required for phasing.
- The contractor is responsible for tasks such as hazardous materials testing and abatement, providing a document management platform, and hiring a commissioning agent.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25024B0066 0003 – Renovate Restrooms – 515-22-101 – VAMC Battle Creek, MI
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 11
0003 10-31-2024
515-22-101
Department of Veterans Affairs
Network Contracting Office (NCO) 10
5500 Armstrong Rd.
Battle Creek MI 49037
Same as Block 6
To all Offerors/Bidders
36C25024B0066
10-31-2024
X
X X
The Purpose of this Amendment is to provide answers to RFI Questions.
SCOTT D. BRENNAN
Senior Contract Specialist
NCO1015L3-0962
SF 30 CONTINUATION PAGE 36C25024B0066
AMENDMENT 0003
THE FOLLOWING ANSWERS TO REQUESTS FOR INFORMATION QUESTIONS ARE
HEREBY PROVIDED TO CLARIFY, UPDATE, REVISE, OR CORRECT CONTRACT
SPECIFICATIONS AND/OR DRAWINGS.
QUESTIONS AND ANSWERS
RFI Question 1: The phasing notes on GI003 says, maintain one (1) egress exit at all times and limit disruptions to daily operations. Other notes say the contractor is to coordinate with the COR regarding new construction vs. demolition/progress phasing. Will there be a limit to the number of restrooms we are given at once? Will there be a limit to the number of restrooms we are given per building/floor? Will there be a specific order in which we are expected to complete the restrooms?
Answer 1: One restroom, per building at first with re-evaluation after or before 1st completed restroom. Reference GI003 General Construction & Phasing Notes note #6, #7, #15. Notes indicate that ‘the Contractor shall not continue with construction until the demo scope of work and new construction scope of work at the turned over restroom, in the same building, is accepted by the VA / COR’. Coordinate new construction vs. demolition progress phasing with the COR / VA. Additionally see note #5, #12 regarding Exits and notes #8, #9, #10, #11 regarding MEPFP systems; as the building will be fully occupied during construction.
RFI Question 2: There plumbing plans do show new valves being installed to isolate the restrooms associated with this project. Are there existing valves that can be used to isolate the restrooms during construction, or will new valves be needed?
Answer 2: New shut-off valves will be needed and quoted. If any existing valves are readily available and in good working conditions, submit an in construction RFI and contact COR for determination, if new valves are needed and descoped from scope of work with a pending contract modification, case by case basis.
RFI Question 3: A note on GI003 states, lead containing paint suspected in all buildings.
contractor is responsible for all testing and abatement of lead paint. Will the amount of lead be quantified? Is it acceptable to encapsulate the lead?
The documents indicate that the contractor is responsible for testing and abatement of lead-based paint, as is suspected to be present in all buildings. Please confirm, for bidding purposes is the contractor to assume all paint within all work areas is lead-based paint to be abated and removed in the present of a certified industrial hygienist. If so, please provide a means of quantifying the amount of lead paint anticipated in the work areas, to ensure all bidders are basing their proposals on the same assumptions.
Or is the contractor to bid assuming only lead-based paint testing will be required as part of the base contract, and any LBP abatement required as a result of the tests will be addressed as a change order?
Answer 3: All existing walls that are to be disturbed within project scope of work are to be all assumed to contain lead-based paint and to be abated, per specification 02 83 33.13.
RFI Question 4: Note 3 on the AD drawings states, wall finishes - remove and dispose of existing wall finishes including base in its entirety. contractor shall prepare wall surfaces to receive new finishes as scheduled. Are the existing walls all suitable for new finishes? Will any walls need to be demoed in their entirety and replaced?
Answer 4: Contractor is to provide quote per bid drawing and specifications. Is any existing walls are found to be not suitable for new required finishes, contractor is to submit a in construction RFI and contact COR for determination with a pending contract modification, case by case basis.
RFI Question 5: Regarding the required on-site personnel roles of Superintendent, SSHO, and QCM, can a single individual occupy 2 or all 3 of these roles simultaneously, or must each of these roles be filled by separate individuals?
Answer 5: General contractor (GC) site superintendent may fill SSHO and QCM roles simultaneously.
RFI Question 6: Please confirm, is it required that the control systems integrator be hired directly by the prime contractor as opposed to being hired by the mechanical contractor?
Answer 6: Control systems integrator maybe hired by prime contractor or mechanical contractor.
RFI Question 7: Please confirm work hours for this project. Are there any specific tasks or trade divisions that must be on overtime? Are there any areas of work that must be on overtime?
Answer 7: Documents do not call for work to be performed outside of regular work hours;
however any whole building water shutdown will be required during off-hours, if isolation valves are not present.
RFI Question 8: Please confirm order of precedence for the contract documents. If discrepancies are found between the drawings and specifications, is the contractor to assume the specifications take precedence over the drawings?
Answer 8: If there are discrepancies between the documents and specifications the contractor shall follow the most stringent requirement.
RFI Question 9: For bidding purposes, how many separate work areas is the contractor to have access to at a time?
Answer 9: One restroom, per building at first with re-evaluation after or before 1st completed restroom. Reference GI003 General Construction & Phasing Notes note #6, #7, #15. Notes indicate that ‘the Contractor shall not continue with construction until the demo scope of work and new construction scope of work at the turned over restroom, in the same building, is accepted by the VA / COR’. Coordinate new construction vs. demolition progress phasing with the COR / VA. Additionally see note #5, #12 regarding Exits and notes #8, #9, #10, #11 regarding MEPFP systems; as the building will be fully occupied during construction.
RFI Question 10: Is the contractor responsible for costs associated with an electronic document management platform such as Submittal Exchange?
Answer 10: Yes, the Contractor is responsible for costs associated with electronic document management. The platform shall provide access for the VA (minimum of 6 users, number of users to be confirmed by VA) Architect (2 users), MEP Engineer (2 users).
RFI Question 11: Will the contractor be required to complete each work area or group of work areas before moving onto the next?
Answer 11: One restroom, per building at first with re-evaluation after or before 1st completed restroom. Reference GI003 General Construction & Phasing Notes note #6, #7, #15. Notes indicate that ‘the Contractor shall not continue with construction until the demo scope of work and new construction scope of work at the turned over restroom, in the same building, is accepted by the VA / COR’. Coordinate new construction vs. demolition progress phasing with the COR / VA. Additionally see note #5, #12 regarding Exits and notes #8, #9, #10, #11 regarding MEPFP systems; as the building will be fully occupied during construction.
RFI Question 12: Or will the contractor have access to all work areas throughout the project duration, with work ongoing in many rooms simultaneously?
Answer 12: One restroom, per building at first with re-evaluation after or before 1st completed restroom. Reference GI003 General Construction & Phasing Notes note #6, #7, #15. Notes indicate that ‘the Contractor shall not continue with construction until the demo scope of work and new construction scope of work at the turned over restroom, in the same building, is accepted by the VA / COR’. Coordinate new construction vs. demolition progress phasing with the COR / VA. Additionally see note #5, #12 regarding Exits and notes #8, #9, #10, #11 regarding MEPFP systems; as the building will be fully occupied during construction.
RFI Question 13: Please confirm, will space adjacent to work areas be occupied during construction?
Answer 13: Additionally see note #5, #12 regarding Exits and notes #8, #9, #10, #11 regarding MEPFP systems; as the building will be fully occupied during construction.
RFI Question 14: For any above-ceiling work in corridors, would HEPA carts suffice as an adequate means of infection control?
Answer 14: HEPA carts are allowable, as long as, they achieve infection control parameters.
RFI Question 15: Please confirm, will the contractors have access to elevators in each of the buildings?
Answer 15: Elevator use will be allowed. Contractors will be required to restore damages and properly house-keep any construction debris or mess.
RFI Question 16: The solicitation lists the period of performance as 380 days, however specification section 01 00 00 states that the estimated project duration is 546 days. Please confirm what the period of performance is on this project.
Answer 16: The original scope of work included additional bathrooms that have been removed from the project. 380 Calendar Days is correct under the current scope of work.
RFI Question 17: On drawing page GI003, asbestos quantities are listed, however it is stated that these drawings do not claim to identify all asbestos containing material present, and that the contractor is responsible for confirmation testing for hazardous materials.
Please confirm, is the contractor to assume all ACM quantities listed on this page are accurate for bidding purposes?
Answer 17: Bidding purposes, contractor is to provide bid for quantities found in specification totals in extent of work from both Traditional Asbestos Abatement 02 82 11 and
Glovebag Asbestos Abatement 02 82 13.13. See attached 515-22-101 BCVA_Asbestos
Survey - Rev 8-2022 and Bulk Sampling Report.
RFI Question 18: If additional ACM is discovered during the contractor-provided hazardous material confirmation testing, will this additional abatement work be handled through a change order to the original contract?
Answer 18: If any ACM differing site conditions are discovered, general contractor is to alert/notify contracting officer of differing site condition and contact COR for determination and a pending contract modification, case by case basis.
RFI Question 19: The asbestos abatement specifications state that the extent of work includes only a small amount of asbestos containing pipe insulation to be abated, however drawing page GI003 shows many various asbestos containing materials that will require abatement as part of this contract. Please confirm whether the extent of the asbestos abatement work on this project is limited the items and quantities shown in the specs, drawings, or both?
Answer 19: Bidding purposes, contractor is to provide bid for quantities found in specification totals in extent of work from both Traditional Asbestos Abatement 02 82 11 and
Glovebag Asbestos Abatement 02 82 13.13.
RFI Question 20: If the quantities listed for ACM pipe insulation in specification section 02
82 11 are to be abated as part of this contract, please provide indication of which buildings / rooms the ACM insulation is located.
Answer 20: See the Abatement report.
RFI Question 21: Please confirm, if unsatisfactory moisture / pH conditions are encountered in existing floor slabs, will the required remedial floor coating be added to the contract as a change order?
Answer 21: If any existing floor slabs are found to be unsatisfactory for moisture/pH conditions, general contractor is to submit an in construction RFI and contact COR for determination and a pending contact modification, case by case basis.
RFI Question 22: If it is the responsibility of the contractor to anticipate unsatisfactory moisture / pH conditions ahead of testing, and therefore include remedial floor coating in their base bid, please provide a means quantifying the extent of remedial floor coating to be assumed for bidding purposes.
Answer 22: If any existing floor slabs are found to be unsatisfactory for moisture/pH conditions, general contractor is to submit an in construction RFI and contact COR for determination and a pending contract modification, case by case basis. For bidding purposes, provide a bid per drawing and specification requirements.
RFI Question 23: Drawing page MD100 calls for new glazing. Please provide a glazing specification section.
Answer 23: The building has new station standard windows provided by Quaker Windows.
The style of window is the T500 single hung. As noted in note 2. VA/ COR will provide additional details.
RFI Question 24: Is the contractor responsible for hiring a commissioning agent?
Answer 24: Refer to project specification for commissioning requirements.
RFI Question 25: A section for signage is included in the specs, but none are shown on the drawings. Please confirm, is the contractor responsible for providing new room signage at all renovated bathrooms?
Answer 25: Contractor shall provide new signage which meets the Station standard and
VA Signage Guidelines. Signage type IN-09.01 - .06 Interior Signage Drawings Restroom
Identification. Signage shall include Room Number, Room Name, Pictogram and Braille.
See attached documentation from Signage Manual. Coordinate final mounting locations
(door or wall) with COR. Submit Signage schedule with room names, numbers, pictogram, etc. for review by VA / COR.
Building 2
004 MEN
003 WOMEN
082 WOMEN
083 MEN
1150 MEN
1189 WOMEN
1190 MEN
2206 WOMEN
2208 MEN
2258 MEN
2260 WOMEN
Building 7
010 RESTROOM
010A (this is a chase – room number only)
016A RESTROOM
029 RESTROOM
Building 9
116 MEN
116A (this is a chase – room number only)
119 WOMEN
119E (this is a chase – room number only)
121 RESTROOM
208 WOMEN
208E (this is a chase – room number only)
211 MEN
211E (this is a chase – room number only)
Building 10
112 WOMEN
112E (this is a chase – room number only)
115 MEN
115E (this is a chase – room number only)
117 RESTROOM
211 MEN
211E (this is a chase – room number only)
214 WOMEN
214E (this is a chase – room number only)
Building 11
111 WOMEN
111E (this is a chase – room number only)
114 MEN
114E (this is a chase – room number only)
117 RESTROOM
208 WOMEN
208E (this is a chase – room number only)
Building 12
115 WOMEN
115E (this is a chase – room number only)
117 RESTROOM
118 MEN
Building 14
118 MEN
134 RESTROOM
144 MEN
218 MEN
234 RESTROOM
244 MEN
Building 82
002 MEN
014 WOMEN
114 RESTROOM
007G RESTROOM
007K
146 MEN
214A MEN
246 WOMEN
Building 84
016 RESTROOM
Building 136
125 MEN
126 WOMEN
RFI Question 26: Specifications for high impact wall coverings are included in the documents, but none appear to be shown on the drawings. Please clarify, is the contractor responsible for providing new high impact wall coverings as part of this contract?
Answer 26: High impact wall coverings are not required for this project.
RFI Question 27: It is noted that the contractor is responsible for providing new anchors / supports for reinstallation of the existing Patient Lift System. Please provide an elevation detail depicting how the patient lift system is to be supported.
Answer 27: Patient lifts shall be removed in their entirety; including all electrical wiring, devices, and anchors. Verify with COR if lifts shall be salvaged and returned to the VA.
RFI Question 28: Is the contractor responsible for hiring a 3rd party inspector to inspect all new firestopping?
Answer 28: Yes
RFI Question 29: Please confirm - Since EF-24-206 and EF-24-208 listed in the Exhaust
Fan Schedule on page MPG001 are shown in rooms 206 and 208, are these not to be included in the bid?
Answer 29: Building 24 has been removed from the project in its entirety. Exhaust Fans shall not be included in bid. Noted on Cover Sheet of drawings.
RFI Question 30: Wall tile is shown in all architectural elevation details, however the only walls shown in elevation details are those that contain new fixtures. Are all restroom walls to receive new wall tile? Or only those specifically shown in elevation details?
Answer 30: See Room Finish Schedule on sheet AS103; all walls shall receive new finishes unless noted otherwise. Note Room B9-211 was not on finish schedule, prints indicate demolition in that room. Scope provided below.
RFI Question 31: If wall tile is only to be installed on walls as shown in elevation details, is the contractor to assume all other walls that are not shown in elevation details are to receive full height drywall finish?
Answer 31: See Room Finish Schedule on sheet AS103; all walls shall receive new finishes unless noted otherwise.
RFI Question 32: Please clarify what the existing partition wall assemblies are constructed of? Is the contractor to assume existing finishes are 1-layer drywall, 1-layer plaster, 2-layer plaster, etc.?
Answer 32: Pre-bid site-visit was available to all general contractors on 10/1/2024.
RFI Question 33: Where walls are to be demolished and patched / repaired for renovation purposes, are these walls to be replaced with plaster or drywall finish?
Answer 33: Drywall finish at a level of finish, per specification.
RFI Question 34: Please confirm, is the intent to reuse existing partition wall framing where possible, and only to patch and repair the drywall / plaster as needed? Or is the intent to replace partition wall assemblies with new framing and finishes?
Answer 34: If newly framed wall and finishes are indicated and required by bid documents, contractor is to provide. If not indicated or noted, contractor is to patch and repair drywall or plaster, as necessary.
RFI Question 35: Will the VA allow for stored material so that we can procure and lay down long lead items and/or critical path material/equipment?
Answer 35: General contractor (GC) is responsible for material storage. VA will allow storage container on campus at GC cost and responsibly.
RFI Question 36: The drawings indicate the contractor is responsible for infilling / repairing the concrete floor slab where needed. For bid levelling purposes, please provide a means of quantifying the extent of concrete floor patching anticipated to be required.
Answer 36: See, Plan Demolition Note #4, contractor is required to level floor to prepare for new finishes. Infilling will be required for existing penetration are removed.
A.1 ADDITIONAL ATTACHMENTS
See attached document: 515-22-101 BCVA_Asbestos Survey - Rev 8-2022.
See attached document: Battle Creek VA Bulk Sampling Report with attachments
20161216.
File details come from the government source that posted it. Updated .