Z1DA--Replace Boiler Control System 553-19-103 Federal contract opportunity
Solicitation number
36C25023B0068
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10

About this file

This document provides an amendment to a federal solicitation for replacing a boiler control system. The amendment provides responses to seven bidder questions, including clarifying that supplemental steel framing details and original equipment manufacturer shop drawings for the existing breeching system will be provided. It also attaches sign-in sheets from a pre-bid site visit and the agenda for that visit. The solicitation number is 36C25023B0068 and is seeking to replace the boiler control system at the Veterans Affairs Medical Center in Detroit, Michigan under the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10. The response due date is not specified.

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25023B0068 – Replace Boiler Control System – 553-19-103 – VAMC Detroit

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 3

553-23-1-3508-0002

553-19-103

Department of Veterans Affairs

Network Contracting Office (NCO) 10

24 Frank Lloyd Wright Drive

Ann Arbor MI 48105

Department of Veterans Affairs

Network Contracting Office (NCO) 10

24 Frank Lloyd Wright Drive

Ann Arbor MI 48105

To all Offerors/Bidders

36C25023B0068

04-03-2023

X

X X

The purpose of this Amendment is:

1. To provide Responses to all Request for Information (RFI's).

2. To provide the Pre-Bid Site Visit Attendance Log and Agenda (see continuation page).

End of Amendment 0001.

RICHMOND MCCLOUD

Contract Specialist

PAGE NO.

CONTRACT NO. ORDER NO. MODIFICATION NO.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (CONTINUED)

STANDARD FORM 30 (CONTINUATION)

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

CONTINUATION PAGE

RFI 01

Question 1: Please confirm that the project engineer will provide the MAU curb support steel detail.

Answer 1 - AE Reply: A detail indicating any required supplemental steel framing will be provided via Addendum.

Question 2: Draft damper will not fit as shown on the drawing (referencing the attached IMG_3010.JPG, cannot confirm that all are the same condition without site visit). Potential solution:

Move damper closer to wye (pending there is enough clearance). Please advise.

Answer 2 - AE Reply: Please refer to the original equipment manufacturer's (OEM) shop drawing of the breeching system which is included with this RFI response. Coordinate the available space and reconfiguration of sections to accommodate the damper. The damper may be placed in front or or behind the existing FM economizer.

Question 3: Please provide manufacturer, or tag, for current boiler breeching.

Answer 3 - AE Reply: Refer to response to RFI-01-02

Question 4: Who is responsible for the roofing?

Answer 4 - AE Reply: The Contractor is responsible for providing labor and material for flashing and weatherproofing the installation of the roof curbs, vents, and any other roof penetrations shown on the drawings.

Question 5: Is the current roof under warranty? If so, who holds the warranty?

Answer 5 - AE Reply: The existing roof was installed in 1995 and no longer has a warranty.

Question 6: The “Instrument Description Table” on M-001 is incomplete. Please provide a complete table that identifies the devices shown on MD-703 and MI-703.

Answer 6 - AE Reply : The "Instrument Description Table" is complete and is the standard International Society of

Automation (ISA) instrument table available in ISA S5.1 "Instrument Symbols and Identification" .

The device call-outs are represented by the different columns of the table. For example, FSV is Flow Safety Valve, ZSC is Position Switch Closed, and GG is Gauge Glass. The first and second letters are generally the first two columns and the remaining letters are the following columns.

Question 7: Are all the instrumentation devices shown on drawing MD-703 with note “Demolish to Point Indicated” to be completely demolished and discarded? Are all the instrumentation devices on MI-703 with “Connect to Existing” symbols next to them to be with new devices?

Answer 7 - AE Reply: The diamond symbol with the B designator is a Burner Management System (BMS) interlock/connection.

Refer to the "Controls Legend" table on M-001. The scope of work this is defining is removal of the connection to a device (MD-703) and reconnection/new connection to a device (MI-703) with the BMS. The project includes demolishing of the existing BMS and provision of a new BMS. Each and every device, new or existing, will require reconnection to the

BMS as indicated. The new devices are represented by the bold and dark device symbol and the existing devices are represented by the light device symbols.

End of RFI Questions and Answers for Amendment 0001

LIST OF ATTACHMENTS:

See attached document: 553-19-103 Pre-bid Site Visit Sign-in Sheet.

See attached document: 553-19-103 Pre-Bid Site Visit Agenda

See attached document: 553-19-103 Addendum No. 1 Narrative

See attached document: 553-19-103 Addendum No. 1 Drawings

See attached document: 553-19-103 Breeching Drawing

See attached document: 553-19-103 Breeching Photo

File details come from the government source that posted it. Updated .