2022-0427_Correct Water Infiltration AMEND 00001 DWGs_Part3.pdf
PDF 4 MB Posted
- Attached to
- Z1DA--Correct Water Infiltration 610-20-102
- Solicitation number
- 36C25022B0009
About this file
This document package includes construction drawings and a federal contract opportunity related to a water infiltration corrective project at a Department of Veterans Affairs medical center. The drawings depict proposed repairs and replacements to rooftops, gutters, downspouts, and masonry on multiple buildings. Work includes removing and replacing asphalt shingles with new stone-coated steel shingles, repairing box gutters and cornices, cleaning and repointing brick, and installing new roofing materials on some sections. The related solicitation seeks bids for all labor, materials, tools and equipment to complete the Correct Water Infiltration project numbered 610-20-102 at the Northern IN VA Medical Center in Marion, Indiana, as outlined in the attachments, drawings, specifications and statement of work. The Veterans Health Administration and Veterans Integrated Service Network 10 are the agencies involved.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AE208
AE2083
AE208
AE208 4
AE501
BUILDING 15
BUILDING 17
BUILDING 174
:1
:1
4:12 4:12
:1
:1
:1
:1
:1
2 2:122:12
6:126:12
:1
:1
4:124:12
:1
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
13 13
AE501
Sim
AE501
Sim
AE501
Sim
AE501
Sim
AE501
Sim
AE501
Sim
AE501
TYP.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
DRAWING OF 24
C U s e rs
\n a te m \O n e
D ri v e
\D o c u m e n ts \F
F E
M a ri o n
W a te r In fi lt ra ti o n
B n a te
.m o u ld s .r v t
/2
/2
:2
:4
P
M
AE108
BUILDING 16 - ROOF PLAN
03/11/2021 PQ BL
MARION, INDIANA
#610-20-102CONSTRUCTION
DOCUMENTS
CORRECT WATER
INFILTRATION
SCALE: 1/8" = 1'-0"
BUILDING 16 - ROOF PLAN
1 REMOVE EXISTING ASPHALT SHINGLES AND UNDERLAYMENT - REPLACE
WITH NEW STONE COATED STEEL SHINGLES OVER #30 FELT
UNDERLAYMENT OVER EXISTING SHEATHING. REPLACE SHEATHING AND
INSULATION WHERE DAMAGED - ASSUME 10% SHEATHING AND
INSULATION REPLACEMENT AT RAFTERS - SEE SECTIONS AND DETAILS ON
AE501 AND AE502.
2 EXISTING METAL ROOF TO REMAIN - PREPARE SURFACE AND APPLY 3-PLY
SELF-ADHERED SBS MODIFIED BITUMIN MEMBRANE TO EXTENT OF METAL
ROOF AND EXTEND 24" UP ADJACENT ROOF SLOPE. INSTALL NEW
BLOCKING WHERE REQUIRED. SEE DETAIL 9/AE501.
3 REPLACE EXISTING BOX GUTTER - INSTALL NEW METAL GUTTER BOX,
PEEL & SEAL LINER, AND METAL CORNICE PROFILE AND ASSOCIATED
BLOCKING, TYPICAL UNLESS NOTED OTHERWISE - SEE DETAILS ON AE501
AND AE502.
4 SEE SHEETS AE107 AND AE207 FOR DEMOLITION AND NEW WORK AT
BUILDING 15.
5 SEE SHEETS AE109 AND AE209 FOR DEMOLITION AND NEW WORK AT
BUILDING 17.
6 NO WORK IN THIS AREA.
7 EXISTING ROOF HATCH TO REMAIN.
8 REMOVE EXISTING MECHANICAL DUCTWORK TO BELOW ROOF SURFACE -
SUPPORT EXISTING WITHIN ATTIC SPACE - VERIFY EXHAUST IS INACTIVE
PRIOR TO CONSTRUCTION - PATCH OPENING WITH WOOF FRAMING AND
SHEATHING - PREPARE TO RECEIVE NEW SHINGLES
9 EXISTING METAL CAP TO REMAIN - PREPARE SURFACE AND APPLY
SELF-ADHERED SBS.
10 RIDGE CAP BY SHINGLE MANUFACTURER TO MATCH ADJACENT SHINGLES
- TYPICAL.
11 VALLEY FLASHING BY SHINGLE MANUFACTURER.
12 PROVIDE NEW STEP FLASHING AT INTERSECTION WITH WALL.
13 PROTECT EXISTING DOWNSPOUT DURING ALL PHASES OF
CONSTRUCTION.
14 EXISTING ALUMINUM GUTTER TO REMAIN.
15 ALTERNATE #1: FALL PROTECTION ROOF ANCHOR SPACED AT 20’ O.C., NO
MORE THAN 24” FROM ROOF PEAK. INSTALL INTO STRUCTURAL FRAMING
AND COORDINATE WITH SHINGLE INSTALLATION.
16 CRICKET BY SHINGLE MANUFACTURER TO MATCH ADJACENT SHINGLES.
D R A W I N G N O T E S
G E N E R A L N O T E S
KEY PLAN
A. THE ROOFING SYSTEM SHALL BE COMPLETELY WATERTIGHT AT THE END OF EACH DAY’S
CONSTRUCTION ACTIVITY. IF TEMPORARY ROOFING STRATEGIES ARE USED, MATERIALS
INSTALLED SHALL SERVE THE SAME FUNCTION AS EXISTING MATERIALS AND WILL BE
COMPATIBLE WITH EXISTING ROOF SYSTEM.
B. CONTRACTOR SHALL RELOCATE EXISTING SURFACE-MOUNTED LIGHTNING PROTECTION
SYSTEM AS NEEDED. REINSTALL SYSTEM AT COMPLETION OF ROOF WORK IN EACH ROOF
AREA. CONTRACTOR SHALL RECERTIFY ENTIRE LIGHTNING PROTECTION SYSTEM AT
CONCLUSION OF PROJECT.
C. NOTE REMOVED.
D. EXISTING PLUMBING VENTS ARE NOT SHOWN ON ROOF PLAN BUT SHALL BE INCLUDED IN THE
PROJECT BID AND COMPLETED ACCORDING TO DETAILS AND/OR ROOFING SYSTEM
REQUIREMENTS.
E. MISCELLANEOUS MECHANICAL, PLUMBING, OR ELECTRICAL PENETRATIONS THRU ROOF MAY
NOT BUT SHOWN BUT SHALL BE INCLUDED IN THE PROJECT BID AND COMPLETED
ACCORDING TO ROOFING SYSTEM REQUIREMENTS. COORDINATE REMOVAL WITH NEW
WORK PLANS AND SECTIONS. ALL PENETRATIONS SHALL BE FLASHED AND MAINTAIN
WATERTIGHTNESS THROUGHOUT COMPLETION OF CONSTRUCTION.
F. EXISTING STRUCTURAL AND FRAMING MEMBERS TO REMAIN UNLESS NOTED OTHERWISE.
No. Revisions: Date:
1 ADDENDUM 001 04/27/2022
AE209
AE2092
AE209
AE209 3
AE501
BUILDING 16
4:
4:
4:12 4:12
4:
4:
4:
4:
4:12 4:12
4:
4:
4:124:12
4:12
4:
4:12
4:
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
AE501
Sim4
AE501
Sim
AE501
Sim
AE501
Sim
AE501
Sim
AE501
Sim
TYP.
TYP.
TYP.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
DRAWING OF 24
C :\U se rs
\q ui nn \D oc um en ts
\F
FE
_M ar io n
- W at er In fil tra tio n_
B1
(2
0) _p at ric k.
qu in nF
BN
EU
.rv t
4/
/2
8:
:2
PM
AE109
BUILDING 17 - ROOF PLAN
03/11/2021 PQ BL
MARION, INDIANA
#610-20-102CONSTRUCTION
DOCUMENTS
CORRECT WATER
INFILTRATION
SCALE: 1/8" = 1'-0"
BUILDING 17 - ROOF PLAN1
1 REMOVE EXISTING ASPHALT SHINGLES AND UNDERLAYMENT - REPLACE WITH NEW
STONE COATED STEEL SHINGLES OVER #30 FELT UNDERLAYMENT OVER EXISTING
SHEATHING. REPLACE SHEATHING AND INSULATION WHERE DAMAGED - ASSUME
10% SHEATHING AND INSULATION REPLACEMENT AT RAFTERS - SEE SECTIONS AND
DETAILS ON AE501 AND AE502.
2 EXISTING METAL ROOF TO REMAIN - PREPARE SURFACE AND APPLY 3-PLY
SELF-ADHERED SBS MODIFIED BITUMIN MEMBRANE TO EXTENT OF METAL ROOF AND
EXTEND 24" UP ADJACENT ROOF SLOPE. INSTALL NEW BLOCKING WHERE REQUIRED.
SEE DETAIL 9/AE501.
3 SEE SHEETS AE108 AND AE208 FOR DEMOLITION AND NEW WORK AT BUILDING 16.
4 NO WORK IN THIS AREA.
5 EXISTING ROOF HATCH TO REMAIN.
6 EXISTING METAL CAP TO REMAIN - PREPARE SURFACE AND APPLY SELF-ADHERED
SBS.
7 RIDGE CAP BY SHINGLE MANUFACTURER TO MATCH ADJACENT SHINGLES - TYPICAL.
8 VALLEY FLASHING BY SHINGLE MANUFACTURER.
9 PROVIDE NEW STEP FLASHING AT INTERSECTION WITH WALL.
10 PROTECT EXISTING DOWNSPOUT DURING ALL PHASES OF CONSTRUCTION.
11 EXISTING ALUMINUM GUTTER TO REMAIN.
12 ALTERNATE #1: FALL PROTECTION ROOF ANCHOR SPACED AT 20’ O.C., NO MORE
THAN 24” FROM ROOF PEAK. INSTALL INTO STRUCTURAL FRAMING AND COORDINATE
WITH SHINGLE INSTALLATION.
13 CRICKET BY SHINGLE MANUFACTURER TO MATCH ADJACENT SHINGLES.
14 REPLACE EXISTING BOX GUTTER - INSTALL NEW METAL GUTTER BOX, PEEL & SEAL
LINER, AND METAL CORNICE PROFILE AND ASSOCIATED BLOCKING, TYPICAL UNLESS
NOTED OTHERWISE - SEE DETAILS ON AE501 AND AE502.
D R A W I N G N O T E S
G E N E R A L N O T E S
KEY PLAN
A. THE ROOFING SYSTEM SHALL BE COMPLETELY WATERTIGHT AT THE END OF EACH DAY’S
CONSTRUCTION ACTIVITY. IF TEMPORARY ROOFING STRATEGIES ARE USED, MATERIALS
INSTALLED SHALL SERVE THE SAME FUNCTION AS EXISTING MATERIALS AND WILL BE
COMPATIBLE WITH EXISTING ROOF SYSTEM.
B. CONTRACTOR SHALL RELOCATE EXISTING SURFACE-MOUNTED LIGHTNING PROTECTION
SYSTEM AS NEEDED. REINSTALL SYSTEM AT COMPLETION OF ROOF WORK IN EACH ROOF
AREA. CONTRACTOR SHALL RECERTIFY ENTIRE LIGHTNING PROTECTION SYSTEM AT
CONCLUSION OF PROJECT.
C. NOTE REMOVED.
D. EXISTING PLUMBING VENTS ARE NOT SHOWN ON ROOF PLAN BUT SHALL BE INCLUDED IN THE
PROJECT BID AND COMPLETED ACCORDING TO DETAILS AND/OR ROOFING SYSTEM
REQUIREMENTS.
E. MISCELLANEOUS MECHANICAL, PLUMBING, OR ELECTRICAL PENETRATIONS THRU ROOF MAY
NOT BUT SHOWN BUT SHALL BE INCLUDED IN THE PROJECT BID AND COMPLETED
ACCORDING TO ROOFING SYSTEM REQUIREMENTS. COORDINATE REMOVAL WITH NEW
WORK PLANS AND SECTIONS. ALL PENETRATIONS SHALL BE FLASHED AND MAINTAIN
WATERTIGHTNESS THROUGHOUT COMPLETION OF CONSTRUCTION.
F. EXISTING STRUCTURAL AND FRAMING MEMBERS TO REMAIN UNLESS NOTED OTHERWISE.
No. Revisions: Date:
1 ADDENDUM 001 04/27/2022
AE2101
AE210
AE502
TYP.
TYP.
TYP.
TYP.
TYP.
AE210
AE210 4
BUILDING 172
6:
6:
6:12
6:
6:12
4:
4:
6:12
6:
6:
6:
6:12
6:12
6:12
TYP.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
DRAWING OF 24
C :\U se rs
\q ui nn \D oc um en ts
\F
FE
_M ar io n
- W at er In fil tra tio n_
B1
(2
0) _p at ric k.
qu in nF
BN
EU
.rv t
4/
/2
8:
:0
PM
AE110
BUILDING 124 - ROOF PLAN
03/11/2021 PQ BL
MARION, INDIANA
#610-20-102CONSTRUCTION
DOCUMENTS
CORRECT WATER
INFILTRATION
SCALE: 1/8" = 1'-0"
BUILDING 124 - ROOF PLAN
1 REMOVE EXISTING ASPHALT SHINGLES AND UNDERLAYMENT - REPLACE
WITH NEW STONE COATED STEEL SHINGLES OVER #30 FELT
UNDERLAYMENT OVER EXISTING SHEATHING. REPLACE SHEATHING AND
INSULATION WHERE DAMAGED - ASSUME 10% SHEATHING AND
INSULATION REPLACEMENT AT RAFTERS - SEE SECTIONS AND DETAILS ON
AE501 AND AE502.
2 EXISTING METAL ROOF TO REMAIN - PREPARE SURFACE AND APPLY 3-PLY
SELF-ADHERED SBS MODIFIED BITUMIN MEMBRANE TO EXTENT OF METAL
ROOF AND EXTEND 24" UP ADJACENT ROOF SLOPE. INSTALL NEW
BLOCKING WHERE REQUIRED. SEE DETAIL 9/AE501.
3 NO WORK IN THIS AREA.
4 REMOVE EXISTING MECHANICAL DUCTWORK TO BELOW ROOF SURFACE -
SUPPORT EXISTING WITHIN ATTIC SPACE - VERIFY EXHAUST IS INACTIVE
PRIOR TO CONSTRUCTION - PATCH OPENING WITH WOOF FRAMING AND
SHEATHING - PREPARE TO RECEIVE NEW SHINGLES
5 RIDGE CAP BY SHINGLE MANUFACTURER TO MATCH ADJACENT SHINGLES -
TYPICAL.
6 PROTECT EXISTING DOWNSPOUT DURING ALL PHASES OF
CONSTRUCTION.
7 EXISTING STONE CORNICE AND BOX GUTTER FRAMING TO REMAIN -
REPLACE EXISTING SHEET METAL LINER AND APPLY NEW PEEL AND SEAL
OVER METAL LINER.
D R A W I N G N O T E S
G E N E R A L N O T E S
KEY PLAN
A. THE ROOFING SYSTEM SHALL BE COMPLETELY WATERTIGHT AT THE END OF EACH DAY’S
CONSTRUCTION ACTIVITY. IF TEMPORARY ROOFING STRATEGIES ARE USED, MATERIALS
INSTALLED SHALL SERVE THE SAME FUNCTION AS EXISTING MATERIALS AND WILL BE
COMPATIBLE WITH EXISTING ROOF SYSTEM.
B. CONTRACTOR SHALL RELOCATE EXISTING SURFACE-MOUNTED LIGHTNING PROTECTION
SYSTEM AS NEEDED. REINSTALL SYSTEM AT COMPLETION OF ROOF WORK IN EACH ROOF
AREA. CONTRACTOR SHALL RECERTIFY ENTIRE LIGHTNING PROTECTION SYSTEM AT
CONCLUSION OF PROJECT.
C. NOTE REMOVED.
D. EXISTING PLUMBING VENTS - COLOR: COPPER. INCLUDED IN THE PROJECT BID AND
COMPLETED ACCORDING TO DETAILS AND/OR ROOFING SYSTEM REQUIREMENTS.
E. MISCELLANEOUS MECHANICAL, PLUMBING, OR ELECTRICAL PENETRATIONS THRU ROOF MAY
NOT BUT SHOWN BUT SHALL BE INCLUDED IN THE PROJECT BID AND COMPLETED
ACCORDING TO ROOFING SYSTEM REQUIREMENTS. COORDINATE REMOVAL WITH NEW
WORK PLANS AND SECTIONS. ALL PENETRATIONS SHALL BE FLASHED AND MAINTAIN
WATERTIGHTNESS THROUGHOUT COMPLETION OF CONSTRUCTION.
F. EXISTING STRUCTURAL AND FRAMING MEMBERS TO REMAIN UNLESS NOTED OTHERWISE.
No. Revisions: Date:
1 ADDENDUM 001 04/27/2022
TYP.
TYP.
9 9
TYP. TYP.
TYP.
14 14
TYP.
TYP.
TYP.
TYP.
TYP.
3 14 14 14
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
14 3
14 14
:7 AE201
:7 AE201
:5 AE201
:5 AE201
3 3
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
14 3
12 121212
BRICK TO BE CLEANED AND TUCK-POINTED - 530 SF - BUILDING 1
BRICK TO BE REMOVED AND REPLACED - 140 SF - BUILDING 1
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
DRAWING OF 24
C U s e rs
\n a te m
\O n e
D ri v e \D o c u m e n ts
\F F
E
M a ri o n
W a te r
In fi lt ra ti o n
B n a te
.m o u ld s .r v t
/2
/2
:3
:5
P
M
AE201
BUILDING 1 - ELEVATIONS
03/11/2021 PQ BL
MARION, INDIANA
#610-20-102CONSTRUCTION
DOCUMENTS
CORRECT WATER
INFILTRATION
1/8" = 1'-0"
B1 - EAST ELEVATION
1/8" = 1'-0"
B1 - WEST ELEVATION
1/8" = 1'-0"
B1 - NORTH ELEVATION
1/8" = 1'-0"
B1 - SOUTH ELEVATION
1 REMOVE EXISTING ASPHALT SHINGLES AND UNDERLAYMENT - REPLACE WITH
NEW STONE COATED STEEL SHINGLES OVER #30 FELT UNDERLAYMENT OVER
EXISTING SHEATHING. REPLACE SHEATHING AND INSULATION WHERE
DAMAGED - ASSUME 10% SHEATHING AND INSULATION REPLACEMENT AT
RAFTERS - SEE SECTIONS AND DETAILS ON AE501 AND AE502.
2 REPLACE EXISTING BOX GUTTER - INSTALL NEW METAL GUTTER BOX, PEEL &
SEAL LINER, AND METAL CORNICE PROFILE AND ASSOCIATED BLOCKING,
TYPICAL UNLESS NOTED OTHERWISE - SEE DETAILS ON AE501 AND AE502.
3 REMOVE EXISTING LOOSE OR RECEDING MORTAR FROM JOINT - TUCKPOINT
WITH NEW MORTAR - STAIN ALL NEW MORTAR TO MATCH EXISTING COLOR.
4 REMOVE EXISTING ROOF HATCH - PATCH OPENING WITH WOOD FRAMING AND
SHEATHING - PREPARE TO RECEIVE NEW SHINGLES.
5 REMOVE AND REPLACE EXISTING METAL ROOF WITH NEW STANDING SEAM
METAL ROOF - COLOR: COPPER.
6 CLEAN AND TUCK-POINT BRICK NEAR DOWNSPOUT.
7 NEW 3"X4" COPPER COLOR DOWNSPOUT TO EXISTING BOOT.
8 NEW 3"X4" COPPER COLOR DOWNSPOUT TO EXISTING BOOT.
9 EXISTING DOWNSPOUT BOOT TO REMAIN.
10 EXISTING CORNICE WORK TO REMAIN - PAINT TO MATCH NEW CORNICE WORK.
11 NEW STEP FLASHING AT ROOF AND WALL INTERSECTION
12 NEW BASE FLASHING
13 RIDGE CAP BY SHINGLE MANUFACTURER TO MATCH ADJACENT SHINGLES -
TYPICAL.
14 REMOVE EXISTING DAMAGED BRICK - REPLACE WITH NEW BRICK TO MATCH
EXISTING IN SIZE, COLOR, AND SURFACE - STAIN ALL NEW MORTAR TO MATCH
EXISTING COLOR.
15 EXISTING PORCH ROOF TO REMAIN.
16 REMOVE LOOSE FACE OF LIMESTONE SILL - SEAL AND STAIN TO MATCH
ADJACENT LIMESTONE SILL IN COLOR.
17 NEW GUTTER FORMED FROM SAME MATERIAL AS ROOF PANELS - COLOR:
COPPER.
18 INSTALL CLAMP-TO-SEAM SNOW GUARDS AT 24" AND 36" FROM FASCIA BOARD -
16" O.C. - COLOR: COPPER TO MATCH ROOFING MATERIAL.
A. THE ROOFING SYSTEM SHALL BE COMPLETELY WATERTIGHT AT THE END OF EACH DAY’S
CONSTRUCTION ACTIVITY. IF TEMPORARY ROOFING STRATEGIES ARE USED, MATERIALS
INSTALLED SHALL SERVE THE SAME FUNCTION AS EXISTING MATERIALS AND WILL BE
COMPATIBLE WITH EXISTING ROOF SYSTEM.
B. CONTRACTOR SHALL RELOCATE EXISTING SURFACE-MOUNTED LIGHTNING PROTECTION
SYSTEM AS NEEDED. REINSTALL SYSTEM AT COMPLETION OF ROOF WORK IN EACH ROOF
AREA. CONTRACTOR SHALL RECERTIFY ENTIRE LIGHTNING PROTECTION SYSTEM AT
CONCLUSION OF PROJECT.
C. NOTE REMOVED.
D. EXISTING PLUMBING VENTS - COLOR: COPPER. INCLUDED IN THE PROJECT BID AND
COMPLETED ACCORDING TO DETAILS AND/OR ROOFING SYSTEM REQUIREMENTS.
E. ALL DOORS AND WINDOWS ARE EXISTING TO REMAIN UNLESS NOTED OTHERWISE.
D R A W I N G N O T E S
G E N E R A L N O T E S
1/8" = 1'-0"
Elevation 2 - a 1/8" = 1'-0"
Elevation 1 - a
No. Revisions: Date:
1 ADDENDUM 001 04/27/22
| 07.10_AE108 - BUILDING 16 - ROOF PLAN |
| AE108 - BUILDING 16 - ROOF PLAN |
| AE101 - BUILDING 1 - ROOF PLAN |
| AE101 - BUILDING 1 - ROOF PLAN |
File details come from the government source that posted it. Updated .