Amendment A00006 Rev DWGs_Part2.pdf
PDF 3 MB Posted
- Attached to
- Z1DA--Correct Water Infiltration 610-20-102 Federal contract opportunity
- Solicitation number
- 36C25022B0009
About this file
This document package includes construction drawings and a federal contract opportunity solicitation. The drawings show plans for correcting water infiltration issues on the roofs of six buildings at the Northern Indiana VA Medical Center in Marion, Indiana. Work includes removing and replacing asphalt shingles and underlayment with new stone-coated steel shingles, removing and replacing various metal roof sections with new standing seam metal roofing, replacing box gutters and downspouts, and installing snow guards. The solicitation seeks bids for the correct water infiltration project numbered 610-20-102 per the attached drawings and specifications. The work will be awarded through the Department of Veterans Affairs Veterans Health Administration VISN 10 to provide all labor, materials, tools and supervision to complete the project. The response due date is not stated.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AE2012
AE201
AE201
AE201 3
:1
:1
12:1212:12
:1
12:12
:1
:1
:1
13:1213:12
:1
:1
:1
:1
:1
14:1214:12
:1
12:12
12:12 12:12
12:12
:1
:1
12:12
:1
12:1212:12
:1
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP. TYP.
TYP.
TYP.2
AE501
Sim6
AE501
Sim
AE501
Sim
AE501
Sim
AE2017
AE201 5
11 122
9 9
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
DRAWING OF 24
C U s e rs
\n a te m
\O n e
D ri v e \D o c u m e n ts
\F F
E
M a ri o n
W a te r
In fi lt ra ti o n
B n a te
.m o u ld s .r v t
/1
/2
:4
:5
A
M
AE101
BUILDING 1 - ROOF PLAN
03/11/2021 PQ BL
MARION, INDIANA
#610-20-102CONSTRUCTION
DOCUMENTS
CORRECT WATER
INFILTRATION
KEY PLAN
SCALE: 1/8" = 1'-0"
BUILDING 1 - ROOF PLAN
1 REMOVE EXISTING ASPHALT SHINGLES AND UNDERLAYMENT - REPLACE
WITH NEW STONE COATED STEEL SHINGLES OVER #30 FELT
UNDERLAYMENT OVER EXISTING SHEATHING. REPLACE SHEATHING AND
INSULATION WHERE DAMAGED - ASSUME 10% SHEATHING AND
INSULATION REPLACEMENT AT RAFTERS - SEE SECTIONS AND DETAILS ON
AE501 AND AE502.
2 VALLEY FLASHING BY SHINGLE MANUFACTURER.
3 RIDGE CAP BY SHINGLE MANUFACTURER TO MATCH ADJACENT SHINGLES
- TYPICAL.
4 REMOVE EXISTING ROOF HATCH - PATCH OPENING WITH WOOD FRAMING
AND SHEATHING - PREPARE TO RECEIVE NEW SHINGLES.
5 NEW 3"X4" COPPER COLOR DOWNSPOUT TO EXISTING BOOT.
6 PROVIDE NEW STEP FLASHING AT INTERSECTION WITH WALL.
7 REMOVE AND REPLACE EXISTING METAL ROOF WITH NEW STANDING
SEAM METAL ROOF - COLOR: COPPER.
8 PROTECT EXISTING DOWNSPOUT DURING ALL PHASES OF
CONSTRUCTION.
9 REPLACE EXISTING BOX GUTTER - INSTALL NEW METAL GUTTER BOX,
PEEL & SEAL LINER, AND METAL CORNICE PROFILE AND ASSOCIATED
BLOCKING, TYPICAL UNLESS NOTED OTHERWISE - SEE DETAILS ON AE501
AND AE502.
10 EXISTING COPPER ROOF TO REMAIN. EXISTING COPPER GUTTERS AND
DOWNSPOUTS TO REMAIN.
11 NEW GUTTER FORMED FROM SAME MATERIAL AS ROOF PANELS - COLOR:
COPPER.
12 INSTALL CLAMP-TO-SEAM SNOW GUARDS AT 24" AND 36" FROM FASCIA
BOARD - 16" O.C. - COLOR: COPPER TO MATCH ROOFING MATERIAL.
A. THE ROOFING SYSTEM SHALL BE COMPLETELY WATERTIGHT AT THE END OF EACH DAY’S
CONSTRUCTION ACTIVITY. IF TEMPORARY ROOFING STRATEGIES ARE USED, MATERIALS
INSTALLED SHALL SERVE THE SAME FUNCTION AS EXISTING MATERIALS AND WILL BE
COMPATIBLE WITH EXISTING ROOF SYSTEM.
B. CONTRACTOR SHALL RELOCATE EXISTING SURFACE-MOUNTED LIGHTNING PROTECTION
SYSTEM AS NEEDED. REINSTALL SYSTEM AT COMPLETION OF ROOF WORK IN EACH ROOF
AREA. CONTRACTOR SHALL RECERTIFY ENTIRE LIGHTNING PROTECTION SYSTEM AT
CONCLUSION OF PROJECT.
C. NOTE REMOVED.
D. EXISTING PLUMBING VENTS ARE NOT SHOWN ON ROOF PLAN BUT SHALL BE INCLUDED IN THE
PROJECT BID AND COMPLETED ACCORDING TO DETAILS AND/OR ROOFING SYSTEM
REQUIREMENTS.
E. ALL DOORS AND WINDOWS ARE EXISTING TO REMAIN UNLESS NOTED OTHERWISE.
D R A W I N G N O T E SG E N E R A L N O T E S
No. Revisions: Date:
1 ADDENDUM 001 04/27/22
AE2022
AE202
AE202
AE202 3
:1
:1
12:1212:12
:1
12:12
:1
:1
:1
12:12 12:12
:1
:1
12:1212:12
12:12
12:12 12:12
12:12
:1
:1
12:12
:1
12:1212:12
:1
TYP. TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
AE501
Sim4
AE501
Sim
AE501
Sim
AE501
Sim
TYP.
4 4
TYP.
TYP.
TYP.
TYP.
11 11122
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
DRAWING OF 24
C U s e rs
\n a te m
\O n e
D ri v e \D o c u m e n ts
\F F
E
M a ri o n
W a te r
In fi lt ra ti o n
B n a te
.m o u ld s .r v t
/1
/2
:5
:1
A
M
AE102
BUILDING 2 - ROOF PLAN
03/11/2021 PQ BL
MARION INDIANA
#610-20-102CONSTRUCTION
DOCUMENTS
CORRECT WATER
INFILTRATION
KEY PLAN
SCALE: 1/8" = 1'-0"
BUILDING 2 - ROOF PLAN
1 REMOVE EXISTING ASPHALT SHINGLES AND UNDERLAYMENT - REPLACE
WITH NEW STONE COATED STEEL SHINGLES OVER #30 FELT
UNDERLAYMENT OVER EXISTING SHEATHING. REPLACE SHEATHING AND
INSULATION WHERE DAMAGED - ASSUME 10% SHEATHING AND
INSULATION REPLACEMENT AT RAFTERS - SEE SECTIONS AND DETAILS ON
AE501 AND AE502.
2 VALLEY FLASHING BY SHINGLE MANUFACTURER.
3 RIDGE CAP BY SHINGLE MANUFACTURER TO MATCH ADJACENT SHINGLES
- TYPICAL.
4 REMOVE EXISTING ROOF HATCH - PATCH OPENING WITH WOOD FRAMING
AND SHEATHING - PREPARE TO RECEIVE NEW SHINGLES.
5 PROTECT EXISTING DOWNSPOUT DURING ALL PHASES OF
CONSTRUCTION.
6 PROVIDE NEW STEP FLASHING AT INTERSECTION WITH WALL.
7 REMOVE AND REPLACE EXISTING METAL ROOF WITH NEW STANDING
SEAM METAL ROOF - COLOR: COPPER.
8 REPLACE EXISTING BOX GUTTER - INSTALL NEW METAL GUTTER BOX,
PEEL & SEAL LINER, AND METAL CORNICE PROFILE AND ASSOCIATED
BLOCKING, TYPICAL UNLESS NOTED OTHERWISE - SEE DETAILS ON AE501
AND AE502.
9 EXISTING DOWNSPOUT SHALL REMAIN - EXTEND EXISTING DOWNSPOUT
TO EXISTING BOOT - APPROXIMATELY 12 INCHES.
10 EXISTING COPPER ROOF TO REMAIN. EXISTING COPPER GUTTERS AND
DOWNSPOUTS TO REMAIN.
11 NEW 3"X4" COPPER COLOR DOWNSPOUT TO EXISTING BOOT.
12 NEW GUTTER FORMED FROM SAME MATERIAL AS ROOF PANELS - COLOR:
COPPER
13 INSTALL CLAMP-TO-SEAM SNOW GUARDS AT 24" AND 36" FROM FASCIA
BOARD - 16" O.C. - COLOR: COPPER TO MATCH ROOFING MATERIAL.
A. THE ROOFING SYSTEM SHALL BE COMPLETELY WATERTIGHT AT THE END OF EACH DAY’S
CONSTRUCTION ACTIVITY. IF TEMPORARY ROOFING STRATEGIES ARE USED, MATERIALS
INSTALLED SHALL SERVE THE SAME FUNCTION AS EXISTING MATERIALS AND WILL BE
COMPATIBLE WITH EXISTING ROOF SYSTEM.
B. CONTRACTOR SHALL RELOCATE EXISTING SURFACE-MOUNTED LIGHTNING PROTECTION
SYSTEM AS NEEDED. REINSTALL SYSTEM AT COMPLETION OF ROOF WORK IN EACH ROOF
AREA. CONTRACTOR SHALL RECERTIFY ENTIRE LIGHTNING PROTECTION SYSTEM AT
CONCLUSION OF PROJECT.
C. NOTE REMOVED.
D. EXISTING PLUMBING VENTS ARE NOT SHOWN ON ROOF PLAN BUT SHALL BE INCLUDED IN THE
PROJECT BID AND COMPLETED ACCORDING TO DETAILS AND/OR ROOFING SYSTEM
REQUIREMENTS.
E. ALL DOORS AND WINDOWS ARE EXISTING TO REMAIN UNLESS NOTED OTHERWISE.
D R A W I N G N O T E SG E N E R A L N O T E S
1 ADDENDUM 001 04/27/2022
AE2032
AE203
AE203
AE203 3
:1
:1
12:1212:12
:1
12:12
:1
:1
:1
12:1212:12
:1
:1
:1
:1
:1
12:1212:12
:1
12:12
12:12 12:12
12:12
:1
:1
12:12
:1
12:1212:12
:1
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.2
AE501
Sim
AE501
Sim
AE501
Sim
AE501
Sim
AE203 AE203 6
TYP.
TYP.
TYP.
TYP.
10 112
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
DRAWING OF 24
C U s e rs
\n a te m
\O n e
D ri v e \D o c u m e n ts
\F F
E
M a ri o n
W a te r
In fi lt ra ti o n
B n a te
.m o u ld s .r v t
/1
/2
:0
:0
A
M
AE103
BUILDING 3 - ROOF PLAN
03/11/2021 PQ BL
MARION, INDIANA
#610-20-102CONSTRUCTION
DOCUMENTS
CORRECT WATER
INFILTRATION
KEY PLAN
SCALE: 1/8" = 1'-0"
BUILDING 3 - ROOF PLAN
1 REMOVE EXISTING ASPHALT SHINGLES AND UNDERLAYMENT - REPLACE
WITH NEW STONE COATED STEEL SHINGLES OVER #30 FELT
UNDERLAYMENT OVER EXISTING SHEATHING. REPLACE SHEATHING AND
INSULATION WHERE DAMAGED - ASSUME 10% SHEATHING AND
INSULATION REPLACEMENT AT RAFTERS - SEE SECTIONS AND DETAILS ON
AE501 AND AE502.
2 VALLEY FLASHING BY SHINGLE MANUFACTURER.
3 RIDGE CAP BY SHINGLE MANUFACTURER TO MATCH ADJACENT SHINGLES
- TYPICAL.
4 REMOVE EXISTING ROOF HATCH - PATCH OPENING WITH WOOD FRAMING
AND SHEATHING - PREPARE TO RECEIVE NEW SHINGLES.
5 PROTECT EXISTING DOWNSPOUT DURING ALL PHASES OF
CONSTRUCTION.
6 PROVIDE NEW STEP FLASHING AT INTERSECTION WITH WALL.
7 REMOVE AND REPLACE EXISTING METAL ROOF WITH NEW STANDING
SEAM METAL ROOF - COLOR: COPPER.
8 REPLACE EXISTING BOX GUTTER - INSTALL NEW METAL GUTTER BOX,
PEEL & SEAL LINER, AND METAL CORNICE PROFILE AND ASSOCIATED
BLOCKING, TYPICAL UNLESS NOTED OTHERWISE - SEE DETAILS ON AE501
AND AE502.
9 EXISTING COPPER ROOF TO REMAIN. EXISTING COPPER GUTTERS AND
DOWNSPOUTS TO REMAIN.
10 NEW 3"X4" COPPER COLOR DOWNSPOUT TO EXISTING BOOT.
11 NEW GUTTER FORMED FROM SAME MATERIAL AS ROOF PANELS - COLOR:
COPPER
12 INSTALL CLAMP-TO-SEAM SNOW GUARDS AT 24" AND 36" FROM FASCIA
BOARD - 16" O.C. - COLOR: COPPER TO MATCH ROOFING MATERIAL.
A. THE ROOFING SYSTEM SHALL BE COMPLETELY WATERTIGHT AT THE END OF EACH DAY’S
CONSTRUCTION ACTIVITY. IF TEMPORARY ROOFING STRATEGIES ARE USED, MATERIALS
INSTALLED SHALL SERVE THE SAME FUNCTION AS EXISTING MATERIALS AND WILL BE
COMPATIBLE WITH EXISTING ROOF SYSTEM.
B. CONTRACTOR SHALL RELOCATE EXISTING SURFACE-MOUNTED LIGHTNING PROTECTION
SYSTEM AS NEEDED. REINSTALL SYSTEM AT COMPLETION OF ROOF WORK IN EACH ROOF
AREA. CONTRACTOR SHALL RECERTIFY ENTIRE LIGHTNING PROTECTION SYSTEM AT
CONCLUSION OF PROJECT.
C. NOTE REMOVED.
D. EXISTING PLUMBING VENTS ARE NOT SHOWN ON ROOF PLAN BUT SHALL BE INCLUDED IN THE
PROJECT BID AND COMPLETED ACCORDING TO DETAILS AND/OR ROOFING SYSTEM
REQUIREMENTS.
E. ALL DOORS AND WINDOWS ARE EXISTING TO REMAIN UNLESS NOTED OTHERWISE.
D R A W I N G N O T E SG E N E R A L N O T E S
AE2042
AE204
AE204
AE204 3
:1
:1
12:1212:12
:1
12:12
:1
:1
:1
12:12 12:12
:1
:1
12:1212:1212:12
12:12 12:12
12:12
:1
:1
12:12
:1
12:1212:12
:1
TYP. TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
AE501
Sim
AE501
Sim
AE501
Sim
AE501
Sim
TYP.
TYP.
TYP.
1010 11 12
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
DRAWING OF 24
C U s e rs
\n a te m
\O n e
D ri v e \D o c u m e n ts
\F F
E
M a ri o n
W a te r
In fi lt ra ti o n
B n a te
.m o u ld s .r v t
/1
/2
:5
:4
A
M
AE104
BUILDING 4 - ROOF PLAN
03/11/2021 PQ BL
MARION, INDIANA
#610-20-102CONSTRUCTION
DOCUMENTS
CORRECT WATER
INFILTRATION
KEY PLAN
SCALE: 1/8" = 1'-0"
BUILDING 4 - ROOF PLAN
1 REMOVE EXISTING ASPHALT SHINGLES AND UNDERLAYMENT - REPLACE
WITH NEW STONE COATED STEEL SHINGLES OVER #30 FELT
UNDERLAYMENT OVER EXISTING SHEATHING. REPLACE SHEATHING AND
INSULATION WHERE DAMAGED - ASSUME 10% SHEATHING AND
INSULATION REPLACEMENT AT RAFTERS - SEE SECTIONS AND DETAILS ON
AE501 AND AE502.
2 VALLEY FLASHING BY SHINGLE MANUFACTURER.
3 RIDGE CAP BY SHINGLE MANUFACTURER TO MATCH ADJACENT SHINGLES
- TYPICAL.
4 REMOVE EXISTING ROOF HATCH - PATCH OPENING WITH WOOD FRAMING
AND SHEATHING - PREPARE TO RECEIVE NEW SHINGLES.
5 PROTECT EXISTING DOWNSPOUT DURING ALL PHASES OF
CONSTRUCTION.
6 PROVIDE NEW STEP FLASHING AT INTERSECTION WITH WALL.
7 REMOVE AND REPLACE EXISTING METAL ROOF WITH NEW STANDING
SEAM METAL ROOF - COLOR: COPPER.
8 REPLACE EXISTING BOX GUTTER - INSTALL NEW METAL GUTTER BOX,
PEEL & SEAL LINER, AND METAL CORNICE PROFILE AND ASSOCIATED
BLOCKING, TYPICAL UNLESS NOTED OTHERWISE - SEE DETAILS ON AE501
AND AE502.
9 EXISTING COPPER ROOF TO REMAIN. EXISTING COPPER GUTTERS AND
DOWNSPOUTS TO REMAIN.
10 NEW 3"X4" COPPER COLOR DOWNSPOUT TO EXISTING BOOT.
11 NEW GUTTER FORMED FROM SAME MATERIAL AS ROOF PANELS - COLOR:
COPPER
12 INSTALL CLAMP-TO-SEAM SNOW GUARDS AT 24" AND 36" FROM FASCIA
BOARD - 16" O.C. - COLOR: COPPER TO MATCH ROOFING MATERIAL.
A. THE ROOFING SYSTEM SHALL BE COMPLETELY WATERTIGHT AT THE END OF EACH DAY’S
CONSTRUCTION ACTIVITY. IF TEMPORARY ROOFING STRATEGIES ARE USED, MATERIALS
INSTALLED SHALL SERVE THE SAME FUNCTION AS EXISTING MATERIALS AND WILL BE
COMPATIBLE WITH EXISTING ROOF SYSTEM.
B. CONTRACTOR SHALL RELOCATE EXISTING SURFACE-MOUNTED LIGHTNING PROTECTION
SYSTEM AS NEEDED. REINSTALL SYSTEM AT COMPLETION OF ROOF WORK IN EACH ROOF
AREA. CONTRACTOR SHALL RECERTIFY ENTIRE LIGHTNING PROTECTION SYSTEM AT
CONCLUSION OF PROJECT.
C. NOTE REMOVED.
D. EXISTING PLUMBING VENTS ARE NOT SHOWN ON ROOF PLAN BUT SHALL BE INCLUDED IN THE
PROJECT BID AND COMPLETED ACCORDING TO DETAILS AND/OR ROOFING SYSTEM
REQUIREMENTS.
E. ALL DOORS AND WINDOWS ARE EXISTING TO REMAIN UNLESS NOTED OTHERWISE.
D R A W I N G N O T E SG E N E R A L N O T E S
AE2052
AE205
AE205
AE205 3
:1
:1
12:1212:12
:1
12:12
:1
:1
:1
12:1212:12
:1
:1
:1
:1
:1 211:1211:12
:1
12:12
12:12 12:12
12:12
:1
:1
12:12
:1
12:1212:12
:1
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP. TYP.
3 3
TYP.
TYP.
2 222
4 5
AE501
Sim
AE501
Sim
AE501
Sim
AE501
Sim
TYP.
TYP.
TYP.
TYP.
9 10 112
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
DRAWING OF 24
C U s e rs
\n a te m
\O n e
D ri v e \D o c u m e n ts
\F F
E
M a ri o n
W a te r
In fi lt ra ti o n
B n a te
.m o u ld s .r v t
/1
/2
:5
:5
A
M
AE105
BUILDING 5 - ROOF PLAN
03/11/2021 PQ BL
MARION, INDIANA
#610-20-102CONSTRUCTION
DOCUMENTS
CORRECT WATER
INFILTRATION
KEY PLAN
SCALE: 1/8" = 1'-0"
BUILDING 5 - ROOF PLAN
1 REMOVE EXISTING ASPHALT SHINGLES AND UNDERLAYMENT - REPLACE
WITH NEW STONE COATED STEEL SHINGLES OVER #30 FELT
UNDERLAYMENT OVER EXISTING SHEATHING. REPLACE SHEATHING AND
INSULATION WHERE DAMAGED - ASSUME 10% SHEATHING AND
INSULATION REPLACEMENT AT RAFTERS - SEE SECTIONS AND DETAILS ON
AE501 AND AE502.
2 VALLEY FLASHING BY SHINGLE MANUFACTURER.
3 RIDGE CAP BY SHINGLE MANUFACTURER TO MATCH ADJACENT SHINGLES
- TYPICAL.
4 NEW 3"X4" COPPER COLOR DOWNSPOUT TO EXISTING BOOT.
5 REMOVE EXISTING ROOF HATCH - PATCH OPENING WITH WOOD FRAMING
AND SHEATHING - PREPARE TO RECEIVE NEW SHINGLES.
6 PROVIDE NEW STEP FLASHING AT INTERSECTION WITH WALL.
7 REMOVE AND REPLACE EXISTING METAL ROOF WITH NEW STANDING
SEAM METAL ROOF - COLOR: COPPER.
8 REPLACE EXISTING BOX GUTTER - INSTALL NEW METAL GUTTER BOX,
PEEL & SEAL LINER, AND METAL CORNICE PROFILE AND ASSOCIATED
BLOCKING, TYPICAL UNLESS NOTED OTHERWISE - SEE DETAILS ON AE501
AND AE502.
9 NEW 3"X4" COPPER COLOR DOWNSPOUT TO EXISTING BOOT.
10 NEW GUTTER FORMED FROM SAME MATERIAL AS ROOF PANELS - COLOR:
COPPER
11 INSTALL CLAMP-TO-SEAM SNOW GUARDS AT 24" AND 36" FROM FASCIA
BOARD - 16" O.C. - COLOR: COPPER TO MATCH ROOFING MATERIAL.
A. THE ROOFING SYSTEM SHALL BE COMPLETELY WATERTIGHT AT THE END OF EACH DAY’S
CONSTRUCTION ACTIVITY. IF TEMPORARY ROOFING STRATEGIES ARE USED, MATERIALS
INSTALLED SHALL SERVE THE SAME FUNCTION AS EXISTING MATERIALS AND WILL BE
COMPATIBLE WITH EXISTING ROOF SYSTEM.
B. CONTRACTOR SHALL RELOCATE EXISTING SURFACE-MOUNTED LIGHTNING PROTECTION
SYSTEM AS NEEDED. REINSTALL SYSTEM AT COMPLETION OF ROOF WORK IN EACH ROOF
AREA. CONTRACTOR SHALL RECERTIFY ENTIRE LIGHTNING PROTECTION SYSTEM AT
CONCLUSION OF PROJECT.
C. NOTE REMOVED.
D. EXISTING PLUMBING VENTS ARE NOT SHOWN ON ROOF PLAN BUT SHALL BE INCLUDED IN THE
PROJECT BID AND COMPLETED ACCORDING TO DETAILS AND/OR ROOFING SYSTEM
REQUIREMENTS.
E. ALL DOORS AND WINDOWS ARE EXISTING TO REMAIN UNLESS NOTED OTHERWISE.
D R A W I N G N O T E SG E N E R A L N O T E S
AE2062
AE206
AE206
AE206 3
:1
:1
12:1212:12
:1
12:12
:1
:1
:1
12:12 12:12
:1 2 1
:1
12:1212:12
12:12
12:12 12:12
12:12
:1
:1
12:12
:1
12:1212:12
:1
TYP. TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
TYP.
2 2
AE501
Sim
AE501
Sim
AE501
Sim
AE501
Sim
5 5
8 9
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
DRAWING OF 24
C U s e rs
\n a te m
\O n e
D ri v e \D o c u m e n ts
\F F
E
M a ri o n
W a te r
In fi lt ra ti o n
B n a te
.m o u ld s .r v t
/1
/2
:5
:1
A
M
AE106
BUILDING 6 - ROOF PLAN
03/11/2021 PQ BL
MARION, INDIANA
#610-20-102CONSTRUCTION
DOCUMENTS
CORRECT WATER
INFILTRATION
KEY PLAN
SCALE: 1/8" = 1'-0"
BUILDING 6 - ROOF PLAN
1 REMOVE EXISTING ASPHALT SHINGLES AND UNDERLAYMENT - REPLACE
WITH NEW STONE COATED STEEL SHINGLES OVER #30 FELT
UNDERLAYMENT OVER EXISTING SHEATHING. REPLACE SHEATHING AND
INSULATION WHERE DAMAGED - ASSUME 10% SHEATHING AND
INSULATION REPLACEMENT AT RAFTERS - SEE SECTIONS AND DETAILS ON
AE501 AND AE502.
2 VALLEY FLASHING BY SHINGLE MANUFACTURER.
3 RIDGE CAP BY SHINGLE MANUFACTURER TO MATCH ADJACENT SHINGLES
- TYPICAL.
4 REMOVE EXISTING ROOF HATCH - PATCH OPENING WITH WOOD FRAMING
AND SHEATHING - PREPARE TO RECEIVE NEW SHINGLES.
5 PROTECT EXISTING DOWNSPOUT DURING ALL PHASES OF
CONSTRUCTION.
6 PROVIDE NEW STEP FLASHING AT INTERSECTION WITH WALL.
7 REMOVE AND REPLACE EXISTING METAL ROOF WITH NEW STANDING
SEAM METAL ROOF - COLOR: COPPER.
8 NEW 3"X4" COPPER COLOR DOWNSPOUT TO EXISTING BOOT.
9 NEW GUTTER FORMED FROM SAME MATERIAL AS ROOF PANELS - COLOR:
COPPER
10 EXISTING COPPER ROOF TO REMAIN. EXISTING COPPER GUTTERS AND
DOWNSPOUTS TO REMAIN.
11 REPLACE EXISTING BOX GUTTER - INSTALL NEW METAL GUTTER BOX,
PEEL & SEAL LINER, AND METAL CORNICE PROFILE AND ASSOCIATED
BLOCKING, TYPICAL UNLESS NOTED OTHERWISE - SEE DETAILS ON AE501
AND AE502.
12 INSTALL CLAMP-TO-SEAM SNOW GUARDS AT 24" AND 36" FROM FASCIA
BOARD - 16" O.C. - COLOR: COPPER TO MATCH ROOFING MATERIAL.
A. THE ROOFING SYSTEM SHALL BE COMPLETELY WATERTIGHT AT THE END OF EACH DAY’S
CONSTRUCTION ACTIVITY. IF TEMPORARY ROOFING STRATEGIES ARE USED, MATERIALS
INSTALLED SHALL SERVE THE SAME FUNCTION AS EXISTING MATERIALS AND WILL BE
COMPATIBLE WITH EXISTING ROOF SYSTEM.
B. CONTRACTOR SHALL RELOCATE EXISTING SURFACE-MOUNTED LIGHTNING PROTECTION
SYSTEM AS NEEDED. REINSTALL SYSTEM AT COMPLETION OF ROOF WORK IN EACH ROOF
AREA. CONTRACTOR SHALL RECERTIFY ENTIRE LIGHTNING PROTECTION SYSTEM AT
CONCLUSION OF PROJECT.
C. NOTE REMOVED.
D. EXISTING PLUMBING VENTS ARE NOT SHOWN ON ROOF PLAN BUT SHALL BE INCLUDED IN THE
PROJECT BID AND COMPLETED ACCORDING TO DETAILS AND/OR ROOFING SYSTEM
REQUIREMENTS.
E. ALL DOORS AND WINDOWS ARE EXISTING TO REMAIN UNLESS NOTED OTHERWISE.
D R A W I N G N O T E SG E N E R A L N O T E S
| 07.03_AE101 - BUILDING 1 - ROOF PLAN |
| AE101 - BUILDING 1 - ROOF PLAN |
| 07.04_AE102 - BUILDING 2 - ROOF PLAN |
| AE102 - BUILDING 2 - ROOF PLAN |
File details come from the government source that posted it. Updated .