Amendment 0006 Summary.docx

DOCX document 30 KB Posted

Attached to
Z1DA--Correct Water Infiltration 610-20-102 Federal contract opportunity
Solicitation number
36C25022B0009
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10

About this file

This document provides an amendment to an invitation for bid for a correct water infiltration project at the Veterans Affairs Medical Center in Marion, Indiana. The amendment includes clarifications to drawings and specifications. Specifically, it modifies notes on several drawings to clarify that new box gutters will be installed only at existing wood cornice locations on Buildings 15-17 to match existing, rather than at dormers which will retain existing aluminum gutters. The amendment renames details on drawings AE501 and AE502 for improved clarity. No other changes are made to specifications. The related federal contract opportunity is solicitation number 36C25022B0009 to provide all labor, materials, tools, and equipment necessary to complete the Correct Water Infiltration project numbered 610-20-102 at the specified VA Medical Center location according to the drawings, specifications, and statement of work. The contracting agency is the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--Correct Water Infiltration 610-20-102, newest first.
File Type Posted
Amendment A00006 Rev DWGs_Part8.pdf PDF
Amendment36C25022B0009 A00006.pdf PDF
Amendment A00006 Rev DWGs_Part5.pdf PDF
Amendment A00006 Rev DWGs_Part3.pdf PDF
Amendment A00006 Rev DWGs_Part2.pdf PDF
Amendment A00006 Rev DWGs_Part6.pdf PDF
Amendment A00006 Rev DWGs_Part7.pdf PDF
Amendment A00006 Rev DWGs_Part1.pdf PDF
Amendment A00006 Rev DWGs_Part4.pdf PDF
Amendment36C25022B0009 A00005.pdf PDF
Amendment 36C25022B0009 A00004.pdf PDF
610-20-102 Correct Water Infiltration pre bid site visit attendance.pdf PDF
2022-0427_Correct Water Infiltration AMEND 00001 DWGs_Part4.pdf PDF
2022-0427_Correct Water Infiltration AMEND 00001 DWGs_Part3.pdf PDF
2022-0427_Correct Water Infiltration AMEND 00001 DWGs_Part1.pdf PDF
2022-0427_Correct Water Infiltration AMEND 00001 DWGs_Part5.pdf PDF
2022-0427_Correct Water Infiltration AMEND 00001 DWGs_Part6.pdf PDF
2022-0427_Correct Water Infiltration AMEND 00001 DWGs_Part2.pdf PDF
Amendment A00003.docx DOCX document
Amendment 00002 Summary.pdf PDF
Amendment A00002 - RFI Responses.docx DOCX document
Amendment A00002 36C25022B0009.pdf PDF
36C25022B0009 Amendment A00001.pdf PDF
610-20-102 Correct Water Infiltration - comb dwgs.pdf PDF
Wage Determination.txt TXT text file
RFI Form.doc DOC document
36C25022B0009 Solicitation.pdf PDF
610-20-102 Correct Water Infiltration - spec.pdf PDF
Contractor Certification Regarding Safety and Environmental.pdf PDF
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

“CORRECT WATER INFILTRATION” PROJECT FOR THE

VETERANS AFFAIRS MEDICAL CENTER (VAMC)—NORTHERN INDIANA HEALTHCARE SYSTEM – MARION CAMPUS

PROJECT NUMBER: 610-20-102

UPDATED SPECIFICATIONS AND EXPLANATION OF REVISIONS

QUESTIONS AND ANSWERS (RFIs)

TO INVITATION FOR BID (IFB) NUMBER

36C25022B0009

IFB AMENDMENT NUMBER A00006 (AE #00002)

QUESTIONS AND ANSWERS

RFI #1 Question:

a) There is a note on multiple drawings calling out to install new metal cornice profile and associated blocking and states to see details AE501 and AE502.

Detail 6 shows the new aluminum gutter detail and then detail 7 AE501 shows a box gutter detail at wood cornice and states “Cornice shall be rebuilt to match existing construction”. Though the drawings do not indicate at all WHERE this wood cornice exists vs the metal cornice. There is no way to get an accurate quantity of each type of cornice. Can you please clarify and show on the drawings where each type of cornice exists.

Answer: Please see the following breakdown of cornices:

Buildings 1-6: Aluminum cornice profile – See detail 6/AE501 Buildings 15-17: Wood cornice – See detail 4/AE501 Building 124: Stone cornice – See detail 6/AE502 See revised Drawings in this Amendment for clarification. New box gutters will only be installed at existing locations – Dormers will not have new box gutters; existing aluminum K-style gutters will be existing to remain (per detail 5/AE501).

DRAWING MODIFICATIONS

AE107:

1. The note regarding the replacement of the existing box gutter has been modified to show a new wood box gutter to match existing. Reference to the detail on AE501 has been updated. Notes within the Revit software have put this modified note at the end of the Drawing Notes and renumbered previous notes across the sheet.

AE108:

2. The note regarding the replacement of the existing box gutter has been modified to show a new wood box gutter to match existing. Reference to the detail on AE501 has been updated. Notes within the Revit software have put this modified note at the end of the Drawing Notes and renumbered previous notes across the sheet. Additional tags have been added to the roof plan to clarify this is the typical condition at gutters on Building 16.

AE109:

3. The note regarding the replacement of the existing box gutter has been modified to show a new wood box gutter to match existing. Reference to the detail on AE501 has been updated. Notes within the Revit software have put this modified note at the end of the Drawing Notes and renumbered previous notes across the sheet.

AE207:

4. The note regarding the replacement of the existing box gutter has been modified to show a new wood box gutter to match existing. Reference to the detail on AE501 has been updated. Notes within the Revit software have put this modified note at the end of the Drawing Notes and renumbered previous notes across the sheet. Additional tags have been added to the roof plan to clarify this is the typical condition at gutters on Building 15.

AE208:

5. The note regarding the replacement of the existing box gutter has been modified to show a new wood box gutter to match existing. Reference to the detail on AE501 has been updated. Notes within the Revit software have put this modified note at the end of the Drawing Notes and renumbered previous notes across the sheet.

AE209:

6. The note regarding the replacement of the existing box gutter has been modified to show a new wood box gutter to match existing. Reference to the detail on AE501 has been updated. Notes within the Revit software have put this modified note at the end of the Drawing Notes and renumbered previous notes across the sheet.

7. Notes were removed from the elevation that erroneously called out a new box gutter at the dormers.

AE501:

8. Detail 6 has been renamed “BOX GUTTER DETAIL AT ALUMINUM CORNICE”

AE502:

9. Detail 6 has been renamed “BOX GUTTER DETAIL AT STONE CORNICE”

SPECIFICATION MODIFICATIONS

None.