541-18-101 - Upgrade Fire Alarm - Bid Documents Drawings_Part7.pdf
PDF 7 MB Posted
- Solicitation number
- 36C25020B0065
About this file
This solicitation is for Project #541-18-101 to upgrade the fire alarm system at the Louis Stokes VA Medical Center in Cleveland, Ohio. The multi-phased project will install a new campus fiber loop and Notifier head end units in Phase 1. Phase 2 will rewire existing field devices like strobes, horns, pull stations and smoke detectors to the appropriate zone panel. All devices will be reprogrammed to report to the correct Notifier control panel. Upon completion, each zone will have a dedicated control panel and devices contained within the smoke compartment. Interested contractors must register at SAM.gov for automatic updates. The estimated value is between $2-5 million. The NAICS code is 238210 and bonds are required. The site visit will be scheduled through an amendment. Questions must be submitted in writing by the deadline. Bids are due approximately 30 days after the solicitation is posted to SAM.gov on November 24, 2020. The contract duration shall not exceed 425 days from notice to proceed. There is no set-aside and all business types may submit bids.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F
F
F
F
F
F
F
F
F
F
F
F F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
F
J
F
F
F
F
F
F
DNDN
DN
DN
DN
DN
UP
█V-N15 L1 M99-10█V-N15 L1 M99-10
█V-N15 L1 M99-10
█V-N15 L1 M99-10 █V-N15 L1 M99-10
█V-N15 L1 M99-4
█V-N15 L1 M99-4 █V-N15 L1 M99-9
█V-N15 L1 M99-9
█V-N15 L1 M99-9
█V-N15 L1 M99-9
█V-N15 L1 M99-9
█V-N15 L1 M99-9 █V-N15 L1 M99-9
█V-N15 L1 M99-9
█V-N15 L1 M99-9 EOL
█V-N15 L1 M99-11█V-N15 L1 M99-11
█V-N15 L1 M99-2
█V-N15 L1 M99-2
█V-N15 L1 M99-11 █V-N15 L1 M99-11 █V-N15 L1 M99-11
█V-N15 L1 M99-11█V-N15 L1 M99-11
█V-N15 L1 M99-11
█V-N15 L1 M99-11
█V-N15 L1 M99-9
█V-N15 L1 M99-9
█V-N15 L1 M99-9
█V-N15 L1 M99-11 EOL
█V-N15 L1 M99-11
█V-N15 L1 M99-11
█V-N15 L1 M99-11
█V-N15 L1 M99-10
█V-N15 L1 M99-9
Conference
1F582
Special Chemistry 3
1F571
Storage-1
BE606-1
Elec Room
1F549
Special Chemestry 1 1F570
Stair 1F621
Soiled Disposal & Staging
BF602
Microbiology Office
1F557
Microbiology Office 2 1F556
Bio-Hazard Trash Hold 1F551
Chemesitry Office #4
1F535
Specimen Toilet 1F560
Chief Office 1F523
Assist. Chief Office
1F524
Clerical
1F526
Fluorescent Microscope
1F530 ANTE Room
1F531
Mycobacterology (TB) Mycology Lab Biosafety Level
1F534
ANTE Room 1F533
Fluorescent Microscop.
1F579
Chem Office #3 1F577
IT EDU Office 1F569
IRM Telecomm Room
1F515
Blood Bank Office
1F566
Electrical Panel
1F511
ANTE Room 1F561
Specimen Accessioning
1F564
Phlembotomy Supplies 1F562
Gross & Frozen Section 1F541
Phlembotomy Office 1F563
Pathologist Office
1F548
Toxicology GM/MASS SPEC Testing
1F552Toxicology GM/MASS Spec Extraction
1F553
ICP MASS SPEC
1F554
Histology Supervisor Office
1F546
Histology
1F544
Microbiology Specimen Prep
1F555
Bicrobiology BSL - 2 Lab 1F558
Ontology 1F543
Chemistry Office #1 1F567
Chemistry Office #2
1F568
Core Lab Automated Chemistry
1F574
Corridor 1F583
Pathologist Office
1F528
Pathologist Office 1F527
Pathologist Office 1F525
Screening Office
1F542
EMS
1F578
Electric Closet
1F516
Microscope & Slide Room 1F545
Corridor
1F547
Supplies
1F575
Immunology
1F576
Lounge
1F581
Molecular Vrology Lab Biosafety Level 3
1F532
Corridor
1F502
Stair A 1F550
Male Toilets
1F522
Female Toilets 1F520
Corridor-1
1F501-1
Corridor-2 1F501-2
Office 1E482 Conference Room
1E446
Office 1E448
Office 1E450
Work Area
1E484
Investigator K108B
Clean Receiving & Staging
BF601
Elevated Walkway 1F601
Vestibule
1F620
Blood Bank 1F565
Intake
1F540 EMS
1F521
Corridor
1F503
Urinalysis 1F573
Corridor
1F529
Special Chemestry 2
1F572
█A-N16 A2 S1
█A-N16 A1 S2
█A-N16 A2 S3
█A-N16 A2 S3
█A-N16 A2 S3
█A-N16 A2 S3
█A-N16 A2 S3
█A-N16 A2 S1
█A-N16 A2 S1 EOL
█A-N16 A2 S1
█A-N16 A1 S2
█A-N16 A2 S1
█A-N16 A1 S4
█A-N16 A1 S4
█A-N16 A2 S1
█A-N16 A2 S1
█A-N16 A2 S1
█A-N16 A2 S1
█A-N16 A2 S1
█A-N16 A2 S1
█A-N16 A2 S3 EOL
█A-N16 A2 S3
█A-N16 A2 S3
█A-N16 A2 S3
█A-N16 A2 S2
█A-N16 A2 S2
█A-N16 A2 S2
█A-N16 A2 S2
█A-N16 A2 S2
█A-N16 A2 S2
█A-N16 A2 S1
Z5 Z6 Z7 Z8
1N
2M
1K
1H
1G
1E
1C
3B 4B 5B 6B 8B7B
3D 4D 5D 6D 8D7D
3F 4F 5F 6F 8B7F
3J 4J 5J 6J 8J7J
3L 4L 5L 6L 8L7L
H1 B1G1 F1 C1
FAZE
NEW
1 2
1 2
4 4
4 4
XR
NEW
N E
W
NEW
NEW
NEW
UP TO 2ND FL STAIR DEVICES,
REFEEDS CIRCUIT FROM THIS
ZONE.
N E
W
NEW
█V-N15 L1 M99█V-N15 L1 M99 EOL
█V-N15 L1 M99
█V-N15 L1 M99
█V-N15 L1 M99-10
█A-N16 A1 S4█A-N16 A1 S4 EOL
█A-N16 A1 S4
█A-N16 A1 S4
█A-N16 A2 S2
Z5 Z6 Z7 Z8
1N
2M
3B 4B 5B 6B 8B7B
3D 4D 5D 6D 8D7D
3F 4F 5F 6F 8B7F
3J 4J 5J 6J 8J7J
3L 4L 5L 6L 8L7L
H1 B1G1 F1 C1
FAZE
NEW
1 2
NEW
UP FROM 1ST FLOOR. CONNECTION
HERE PICKS UP REMAINIG DEVICES
ON CIRCUIT ON BELOW 2 FLOORS.
NEW
672 EAST ROYALTON ROAD
BROADVIEW HTS., OHIO 44147
TEL. (440) 546-9696
FAX: (440) 546-9699
S
59459
M.P. LONG
R
ES
O F
I R
GE
NOI
S
P
E
N E
DERT
L EA
E I N
G
R
TS
TEA HF OO
IO
CONSULTANTS: ARCHITECT:
Drawing Title Project NumberProject Title
Building Number
Approved: Location
LOUIS STOKES MEDICAL CENTER 10701 EAST BLVD.
Office of
Facilities
Management
FULLY SPRINKLERED
Date
05/14/21
Checked Drawn
Drawing Number
Dwg. of DateRevisions:
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
D
C
B
A
E
F
D
C
B
A
E
F
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
VA FORM 08-6231, OCT 1978
DOCUMENT SET MUST BE PRINTED IN COLOR
BID DOCUMENTS SUBMISSION 05/14/21 17069
NODE 6.1 - LAB WAREHOUSE
FIRST FLOOR AND PENTHOUSE
- NOTIFICATION
541-18-101UPGRADE FIRE ALARM
MPL CPC
FA-N-6.1b
8' 16' 32' 64'
1/16" = 1' 0"
FIRST FLOOR FIRE ALARM PLAN - NOTIFICATION - NODE 6.1 1
8' 16' 32' 64'
1/16" = 1' 0"
SECOND FLOOR FIRE ALARM PLAN - NOTIFICATION - NODE 6.1 2
NOT TO SCALE
NODE 6.1 - FIRST FLOOR
FIRE ALARM KEY PLAN
NOT TO SCALE
NODE 6.1 - SECOND FLOOR
FIRE ALARM KEY PLAN
FIRE ALARM NOTIFICATION DEVICE SCHEDULE - LAB WAREHOUSE - FIRST FLOOR - NODE 6.1
CIRCUIT IDENTIFIER NEW STROBE CIRCUIT NEW AUDIO CIRCUIT
3 N6.1A Z2 L1 N6.1B Z2 A1
4 N6.1A Z2 L2 N6.1B Z2 A2
5 N6.1A Z2 L3 N6.1B Z2 A3
6 N6.1A Z3 L1 N6.1B Z3 A1
CODED NOTES
1 LOCATION OF FIRST STROBE AND AUDIO CIRCUIT SERIES CONNECTION FROM
EXISTING EXTENDER PANEL AND AMPLIFIER. DISCONNECT EXISTING INCOMING
STROBE AND AUDIO CIRCUITS FROM DEVICE. REMOVE EXISTING CONDUIT AND
WIRING COMPLETE BACK TO SOURCE. MAINTAIN CONNECTION OUT TO NEXT
DEVICE IN SERIES.
PROVIDE 3/4"C WITH NEW AUDIO AND STROBE CIRCUIT CONDUCTORS FROM FIRE
ALARM ZONE EQUIPMENT IN THIS ZONE (FIRE ALARM EXTENDER PANEL AND
DIGITAL AUDIO AMPLIFIER) AND CONNECT COMPLETE TO FIRE ALARM
NOTIFICATION APPLIANCE TO MIGRATE EXISTING DEVICES TO NEW EQUIPMENT.
IF FIRST DEVICE IS A STROBE-ONLY OR SPEAKER-ONLY DEVICE, CONTINUE
ROUTING UNUSED CIRCUIT TO NEXT DEVICE FOR CONNECTION.
REMOVE EXISTING CONDUIT AND FIRE ALARM CIRCUIT CONDUCTORS INDICATED
AND PROVIDE 3/4"C WITH NEW AUDIO AND STROBE CIRCUIT CONDUCTORS TO
DEVICES INDICATED AND CONNECT COMPLETE TO MIGRATE EXISTING DEVICES
THE CIRCUIT.
EXISTING DEVICE REQUIRES REWORKING TO REMOVE FROM CURRENT FIRE
ALARM CIRCUITS AND TO MERGE WITH CIRCUIT INDICATED. DISCONNECT
INCOMING CIRCUITS TO ISOLATE DEVICES. MAINTAIN CIRCUITS BETWEEN
DEVICES TO FACILITATE RECONNECTION TO NEW CIRCUITS.
FIRE ALARM GENERAL NOTES
F1 ALL FIRE ALARM SYSTEM DEVICES SHALL BE CONNECTED COMPLETE TO THE FIRE
ALARM CONTROL SYSTEM IN ACCORDANCE WITH ENGINEER APPROVED
MANUFACTURER'S SHOP DRAWINGS, WIRING DIAGRAMS, AND DETAILS.
F2 ALL FIRE ALARM SYSTEM CONDUCTORS SHALL BE INSTALLED IN 3/4" MINIMUM SIZE
CONDUIT SYSTEM.
F3 SMOKE DETECTORS SHALL BE INSTALLED ON CEILINGS WITH SPACING NOT TO
EXCEED MANUFACTURER'S RECOMMENDATION AND IN ACCORDANCE WITH NFPA 72.
F4 SMOKE DETECTORS SHALL BE INSTALLED WITHIN 5'-0" OF CENTERLINE OF SMOKE
DOORS ON HOLD-OPEN DEVICES. DETECTORS SHALL BE INSTALLED ON EACH SIDE
OF THE DOOR PER VA FIRE PROTECTION DESIGN MANUAL.
F5 FIRE ALARM SYSTEM SHALL BE SUB-DIVIDED INTO ZONES THAT CORRESPOND TO
THE SMOKE COMPARTMENTS AND SPRINKLER ZONES PER VA FIRE PROTECTION
DESIGN MANUALS.
F6 ALL EXISTING FIRE ALARM DEVICES THAT WILL NOT BE REUSED IN THE REMODELED
INSTALLATION SHALL BE REMOVED UNLESS OTHERWISE NOTED. THIS DEMOLITION
SHALL INCLUDED ALL ITEMS SHOWN ON THIS PLAN THAT ARE DESIGNATED BY "XR"
AND ALL OTHER ADDITIONAL ITEMS THAT ARE NOT SHOWN BUT THAT MUST BE
REMOVED IN OREDER TO PRODUCE A NEAT, FINISHED, PROPERLY FUNCTIONING
ELECTRICAL INSTALLATION. MAINTAIN CIRCUIT CONTINUITY TO ALL EXISTING
REUSED DEVICES - PROVIDE ALL CONDUIT AND WIRING NECESSARY TO ACHIEVE
THE SAME. THE CONTRACTOR SHALL FIELD VERIFY THE NATURE AND THE EXTENT
OF ALL DEMOLITION WORK AND SHALL INCLUDE COST FOR THE SAME IN THE BID
SUBMITTAL.
F7 ALL EXISTING REMOVED ELECTRICAL EQUIPMENT, DEVICES, ETC. THAT ARE NOT
RETAINED BY THE OWNER SHALL BE DISPOSED OF BY THE ELECTRICAL
CONTRACTOR.
F8 REFER TO THE LEGEND FOR ALL SYMBOL DESIGNATIONS. NOTE SPECIAL ATTENTION
TO SELECTED EXISTING DEVICES, WIREWAYS, ETC. MARKED "XB", "XRR", OR "XN"
AND REMOVE/BLANK OFF, RELOCATE, OR REPLACE THESE COMPONENTS AS
REQUIRED.
F9 CLOSELY COORDINATE ALL DEMOLITION WORK WITH THE GENERAL CONTRACTOR
TO PROVIDE PATCHING AND PAINTING FOR EXISTING WALLS WHERE
DEVICES/PANELS ARE REMOVED.
F10 CONTACT THE ENGINEER IF A QUESTION SHOULD ARISE CONCERING THE STATUS
OF ANY OUTLET, DEVICE, FIXTURE, ETC.
672 EAST ROYALTON ROAD
BROADVIEW HTS., OHIO 44147
TEL. (440) 546-9696
FAX: (440) 546-9699
S
59459
M.P. LONG
R
ES
O F
I R
GE
NOI
S
P
E
N E
DERT
L EA
E I N
G
R
TS
TEA HF OO
IO
CONSULTANTS: ARCHITECT:
Drawing Title
Approved: Location
Project Title
Date Checked Drawn
Drawing Number
Building Number
Project Number
Office of
Facilities
Management
Dwg. of o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
VA FORM 08-6231, OCT 1978
1 2 3 4 5 6 7 8 9 10
A
1 2 3 4 5 6 7 8 9 10
B
C
D
E
F
A
B
C
D
E
F
LOUIS STOKES MEDICAL CENTER 10701 EAST BLVD.
Revisions: Date
DOCUMENT SET MUST BE PRINTED IN COLOR
FULLY SPRINKLERED
17069
BID DOCUMENTS SUBMISSION 05/14/21
UPGRADE FIRE ALARM 541-18-101
CPCMPL
DEMOLITION FIRE ALARM SYSTEM
BACKBONE DIAGRAM
FA-R-0.1
05/14/21
672 EAST ROYALTON ROAD
BROADVIEW HTS., OHIO 44147
TEL. (440) 546-9696
FAX: (440) 546-9699
S
59459
M.P. LONG
R
ES
O F
I R
GE
NOI
S
P
E
N E
DERT
L EA
E I N
G
R
TS
TEA HF OO
IO
CONSULTANTS: ARCHITECT:
Drawing Title
Approved: Location
Project Title
Date Checked Drawn
Drawing Number
Building Number
Project Number
Office of
Facilities
Management
Dwg. of o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
VA FORM 08-6231, OCT 1978
1 2 3 4 5 6 7 8 9 10
A
1 2 3 4 5 6 7 8 9 10
B
C
D
E
F
A
B
C
D
E
F
LOUIS STOKES MEDICAL CENTER 10701 EAST BLVD.
Revisions: Date
DOCUMENT SET MUST BE PRINTED IN COLOR
FULLY SPRINKLERED
17069
BID DOCUMENTS SUBMISSION 05/14/21
UPGRADE FIRE ALARM 541-18-101
CPCMPL
NEW FIRE ALARM SYSTEM
BACKBONE DIAGRAM
FA-R-0.2
05/14/21
FIRE ALARM SYSTEM BACKBONE LEGEND:
NOTIFIER 3030 FIRE ALARM CONTROL PANEL (FACP) WITH OPTIONAL DIGITAL VOICE COMMAND (DVC) MODULE
- # INDICATES BUILDING AND SEQUENTIAL NODE IDENTIFICATION
- A OR B INDICATES FACP OR DVC MODULE
FOR EXAMPLE: 3.5A DENOTES BUILDING #3, NODE #5, FIRE ALARM CONTROL PANEL, 4.2B DENOTES BUILDING #4, NODE #2, DIGITAL VOICE COMMAND MODULE
REFER TO FIRE ALARM ZONE FLOOR PLANS FOR AREAS OF COVERAGE.
- #,#,# INDICATES NODE IDENTIFICATION, AND SEQUENTIAL COMPARTMENT IDENTIFICATION.
FOR EXAMPLE: ZONE 1.2.3 REFERS TO NODE 1.2 AND COMPARTMENT #3.
UL-LISTED CONTROL AND MONITORING WORKSTATION WITH 22" TOUCH SCREEN
UL-LISTED INTERACTIVE GRAPHICAL TOUCH SCREEN DISPLAY. AUTOMATICALLY DISPLAYS EMERGENCY EVENT LOCATION AND INFORMATION FOR ACCESS BY FIRST RESPONDERS AND STAFF.
NOTIFIRE NET CABLING - SINGLE-MODE, CLASS X FIBER LOOP - INSTALLED IN COMPLETE RIGID CONDUIT SYSTEM
FIRE ALARM SYSTEM CABLING - (1) 6-STRAND 62.5/125 FIBER OPTIC CABLE - AUDIO, (2) RED/BLACK #14 THHN PAIRS FOR STROBE SYNC, (4) RED 16-2 SHIELDED CABLES - SLC LOOP
EQUIPMENT IN EACH ZONE CONSISTS OF:
(1) HPFF8 FIRE ALARM EXTENDER PANEL - (2) STROBE CIRCUITS, (1) DOOR HOLD CIRCUIT, (1) SPARE
(1) DAA2-7525 DIGITAL AUDIO AMPLIFIER - (4) AUDIO CIRCUITS, 75WATT TOTAL OUTPUT.
FA PULL BOX
ZONE EQUIPMENT (FAZE)
SBB-D4R WITH DR-D4R DOOR
SPACE AVAILABLE FOR FUTURE
AMPLIFIER OR POWER SUPPLY
FIRE ALARM
CONTROL
DIGITAL AUDIO NETWORK
(TYPICAL FOR DIGITAL AUDIO
BETWEEN DVC AND AMP)
SLC LOOPS OUT TO ADDITIONAL
ZONES ON THE SAME NODE (TYPICAL)
VISUAL CIRCUIT - STROBE #1
VISUAL CIRCUIT - STROBE #2
24V OUTPUT - DOOR HOLDS
FIRE ALARM SYSTEM CODED NOTES:
NOTIFIER SYSTEM NODE ENCLOSURE
PROVIDE COMPONENTS AS NECESSARY IN NOTIFIER SYSTEM CABINET TO PROVIDE CONNECTION BETWEEN FIRE ALARM CONTROL EQUIPMENT (ADDRESSABLE CIRCUIT CONTROL PANEL AND VOICE COMMUNICATION SYSTEM) AND ZONE EQUIPMENT (NOTIFICATION APPLIANCE PANEL AND DIGITAL AUDIO AMPLIFIER.
A. NOTIFIER SYSTEM CABINET: 24-1/8"W x 37-1/4"H BOX AND HINGED COVER (#SBB-C4R WITH #DR-C4R)
B. FIRE ALARM SYSTEM CONTROL UNIT (NFS2-3030 WITH DISPLAY ON CHS-M3 CHASSIS)
C. ADDRESSABLE LOOP CONTROL MODULE: GENERATES (1) SLC LOOP. (LCM-320)
D. ADDRESSABLE LOOP EXTENDER MODULE: EXTENDS LCM TO (2) SLC LOOPS (LEM-320)
E. VOICE COMMUNICATIONS SYSTEM: GENERATES AUDIO ALARM MESSAGES (DVC-EM ON CA-1 CHASSIS) F. HIGH SPEED COMMUNICATION MODULE: PROVIDES FIBER OPTIC NETWORK CONNECTION FIRE ALARM
EQUIPMENT (FACP, DVC, ONYXWORKS WORKSTATIONS, AND FIRST VISION GRAPHICAL ANNUNCIATORS).
MOUNT ON TOP OF LOOP MODULES WHERE INDICATED. (HS-NCM-F)
G. IP GATEWAY: CONNECTS ONYXWORKS WORKSTATIONS AND FIRSTVISION GRAPHICAL ANNUNCIATORS TO NOTIFIER NETWORK VIA CAT6 CABLING AND INTEFRACE WITH HIGH-SPEED COMMUNICATION MODULE.
H. 24V DC POWER SUPPLY: 120VAC INPUT, 5A CONTROL UNIT OUTPUT, 3A AUXILIARY OUTPUT (AMPS-24) I. BACK-UP BATTERIES. PROVIDE BATTERIES AS REQUIRED PER SPECIFICATION SECTION 28 31 00. IF
NECESSARY, PROVIDE SEPARATE BATTERY CABINET. (NFN-GW-EM-3)
J. MISCELLANEOUS DRESS PLATES: FILL EMPTY/FUTURE SPACES IN PANEL AND ACCOMMODATE INSTALLED
MODULES. PROVIDE DRESS PLATES AS REQUIRED FOR DEVICES BEING INSTALLED (DP-DISP, DPA-1, DP-1B, BP2-4, ETC).
K. PROVIDE ALL CABLING INTERCONNECTION BETWEEN NODE EQUIPMENT (NFS-3030 CONTROL BOARD, DVC-EM, NETWORK CARDS, POWER SUPPLY/BATTERY CHARGER, ETC). SOME CONNECTIONS MAY NOT BE SHOWN FOR CLARITY (E.G. CONNECTION BETWEEN POWER SUPPLY/BATTERY CHARGER AND FIRE
ALARM SYSTEM CONTROL UNIT AND VOICE COMMUNICATIONS SYSTEM.)
NOTIFIER SYSTEM ZONE ENCLOSURE
PROVIDE COMPONENTS AS NECESSARY IN A NOTIFIER SYSTEM CABINET TO PROVIDE CONNECTION FOR
LOCAL DEVICES IN THE AREAS OUTLINED ON THE ZONE PLANS.
A. 24 1/8"W x 37 1/4"H BOX AND HINGED COVER (#SBB-C4R WITH #DR-C4R)
B. DAA2-7525 AMPLIFIER
C. APC-610 POWER EXTENDER PANEL (2 STROBE CIRCUITS, 1 DOOR HOLD CIRCUIT AND 1 SPARE) D. 7.0 Ah BATTERIES E. PROVIDE CONNECTION BETWEEN POWER SUPPLY/BATTERY CHARGER AND AMPLIFIER. (NOT SHOWN)
PROVIDE 6"H x 4"D RACEWAY WITH NONSLIP FLUSH COVER. RACEWAY SHALL BE LENGTH OF NOTIFIER SYSTEM EQUIPMENT. ROUTE FIRE ALARM SYSTEM WIRING THROUGH RACEWAY AND PROVIDE AN ORGANIZED ROUTING
OF WIRING. PROVIDE ADDITIONAL CONDUITS AND RACEWAY AS NECESSARY.
SLC CARDS
CPU2-3030D
VOICE
COMMAND
SYSTEM
DVC-EM
(1) LCM-320
(1) LEM-320
DIGITAL AUDIO AMPLIFIER
DAA2-7525
ADDRESSABLE POWER SUPPLY
ACPS-610
AUDIO CIRCUIT TO
SPEAKERS IN ZONE
TO NEXT AMPLIFIER
FIRE ALARM EQUIPMENT DIAGRAM GENERAL NOTES:
ALL FIRE ALARM CABLING SHOWN SHALL BE ROUTED WITHIN CONDUIT, RACEWAYS, ENCLOSURES, ETC. WIRING IS SHOWN FROM POINT-TO-POINT OR OUTSIDE OF CONDUIT FOR CLARITY OF CONNECTIONS BEING INDICATED.
FIRE ALARM CABLING SHOWN IS FOR REFERENCE ONLY. CONTRACTOR SHALL VERIFY ALL CONNECTION REQUIREMENTS WITH NOTIFIER PRIOR TO INSTALLATION. PROVIDE TYPICAL WIRING DIAGRAMS WITH SHOP
DRAWINGS FOR REVIEW.
BATTERY BATTERY
SPACE AVAILABLE FOR FUTURE
AMPLIFIER OR POWER SUPPLY
(PROVIDE ADDITIONAL POWER SUPPLY IN ZONES
THAT REQUIRE MORE THAN 2 STROBE CIRCUITS)
MICROPHONE
CMIC-1
NODE EQUIPMENT (FANE)
SBB-D4R WITH DR-C4R DOOR
BATTERY
BATTERY
24V POWER
SUPPLY
AMPS-24
(24) STRAND
WALL-MOUNTED,
FIBER TERMINATION BOX
(LC-STYLE CONNECTORS)
6-STRAND,
TIGHT-BUFFERED,
PLENUM RATED, INDOOR,
SINGLE-MODE FIBER OPTIC
CABLE IN 3/4" EMT COMPLETE
CONDUIT SYSTEM
FROM PREVIOUS NODE
6-STRAND,
TIGHT-BUFFERED,
PLENUM RATED, INDOOR,
SINGLE-MODE FIBER OPTIC
CABLE IN 3/4" EMT COMPLETE
CONDUIT SYSTEM
FROM PREVIOUS NODE
PROVIDE (1) 3/4"C OUT TO EACH ZONE FED FROM THE
NODE EQUIPMENT WITH SLC LOOP TO NEW ZONE
EQUIPMENT AND FIBER CONNECTION TO AMPLIFIER.
SLC CARDS
(1) LCM-320
(1) LEM-320
FIRE ALARM CABLING LEGEND:
SIGNALING LINE CIRCUIT (SLC) LOOP - (1) #16 UNSHIELDED TWISTED PAIR WITH OVERALL JACKET
AMPLIFIER NETWORK LOOP - (2) 9/125 SINGLE-MODE FIBER OPTIC CABLES
NOTIFIER NETWORK LOOP - 6-STRAND, TIGHT-BUFFERED, INDOOR, PLENUM-RATED, SINGLE-MODE
FIBER OPTIC CABLE IN COMPLETE 3/4" EMT CONDUIT SYSTEM
VISUAL CIRCUIT - (1) #14 AWG PAIR
AUDIO CIRCUIT - (1) #14 SHIELDED, TWISTED PAIR
24V OUTPUT CIRCUIT - (1) #14 AWG PAIR (UNLESS OTHERWISE NOTED)
SLC LOOP OUT TO NOTIFICATION
APPLIANCE EXTENDER PANEL IN THE
SAME ZONE AS THE NODE EQUIPMENT
SLC LOOP OUT TO ADDITIONAL
DEVICES ON THIS ZONE (TYPICAL)
FIBER OPTIC AUDIO CONNECTION TO
AMPLIFIER IN THE SAME ZONE AS THE
NODE EQUIPMENT
FA PULL BOX 3
FUTURE
SM FIBER PAIR FROM
LAST ZONE AMPLIFIER
NOTIFIER NUP CABLE
ETHERNET CONNECTION - (1) CAT6 CABLE
NETWORK CONNECTION OUT TO NEXT NODE
(WHERE NECESSARY, CONNECT FIBER OUTPUT OF NETWORK
CARD FOR DVC TO NETWORK CARD(S) FOR FIRSTVISION OR
ONYXWORKS. THEN ROUTE OUTPUT TO TERMINATION BOX
FOR OUTPUT TO NEXT NODE. NOT SHOWN FOR CLARITY)
NETWORK CONNECTION IN
FROM PREVIOUS NODE
NETWORK CARD
HS-NCM-F (FACP)
NETWORK CARD
HS-NCM-F (DVC)
NOTIFIER NUP CABLE
SPACE FOR FUTURE
LOOP MODULES
[PROVIDE ADDITIONAL
LOOP MODULES FOR
NODES THAT REQUIRE
MORE THAN (4) LOOPS]
HS-NCM-F +
NFN-GW-EM-3
NETWORK
CARD
REQUIRED IN NODES
WITH FIRSTVISION PANEL
HS-NCM-F +
NFN-GW-EM-3
NETWORK
CARD
REQUIRED IN NODES WITH
ONYXWORKS STATION
ONYXWORKS
STATION
FIRSTVISION
1.
2.
SPACE AVAILABLE FOR FUTURE USE
672 EAST ROYALTON ROAD
BROADVIEW HTS., OHIO 44147
TEL. (440) 546-9696
FAX: (440) 546-9699
S
59459
M.P. LONG
R
ES
O F
I R
GE
NOI
S
P
E
N E
DERT
L EA
E I N
G
R
TS
TEA HF OO
IO
CONSULTANTS: ARCHITECT:
Drawing Title
Approved: Location
Project Title
Date Checked Drawn
Drawing Number
Building Number
Project Number
Office of
Facilities
Management
Dwg. of o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
VA FORM 08-6231, OCT 1978
1 2 3 4 5 6 7 8 9 10
A
1 2 3 4 5 6 7 8 9 10
B
C
D
E
F
A
B
C
D
E
F
LOUIS STOKES MEDICAL CENTER 10701 EAST BLVD.
Revisions: Date
DOCUMENT SET MUST BE PRINTED IN COLOR
FULLY SPRINKLERED
17069BID DOCUMENTS SUBMISSION 05/14/21
UPGRADE FIRE ALARM 541-18-101
CPCMPL
FIRE ALARM SYSTEM DETAILS
FA-D-0.1
05/14/21
NOT TO SCALE
TYPICAL FIRE ALARM EQUIPMENT PANEL DETAIL 1
| X-0.1 - COVER SHEET |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| X-0.1 - COVER SHEET |
| FP-1-01 - PARTIAL SECOND AND FIFTH FLOOR FIRE PROTECTION PLAN |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FP-1-01 - PARTIAL SECOND AND FIFTH FLOOR FIRE PROTECTION PLAN |
| M-1-01 - PARTIAL SECOND AND FIFTH FLOOR MECHANICAL PLANS |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| M-1-01 - PARTIAL SECOND AND FIFTH FLOOR MECHANICAL PLANS |
| FA-L-0.1 - ELECTRICAL SYMBOL LEGEND AND GENERAL NOTES |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-L-0.1 - ELECTRICAL SYMBOL LEGEND AND GENERAL NOTES |
| FA-L-0.2 - FIRE ALARM INPUTOUTPUT AND ZONE TRIGGER MATRIX |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-L-0.2 - FIRE ALARM INPUT/OUTPUT AND ZONE TRIGGER MATRIX |
| FA-K-SB - SUB-BASEMENT FIRE ALARM ZONE KEY PLAN |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-K-SB - SUB-BASEMENT FIRE ALARM ZONE KEY PLAN |
| FA-K-B - BASEMENT FIRE ALARM ZONE KEY PLAN |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-K-B - BASEMENT FIRE ALARM ZONE KEY PLAN |
| FA-K-1 - FIRST FLOOR FIRE ALARM ZONE KEY PLAN |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-K-1 - FIRST FLOOR FIRE ALARM ZONE KEY PLAN |
| FA-K-2 - SECOND FLOOR FIRE ALARM ZONE KEY PLAN |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-K-2 - SECOND FLOOR FIRE ALARM ZONE KEY PLAN |
| FA-K-3 - THIRD FLOOR FIRE ALARM ZONE KEY PLAN |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-K-3 - THIRD FLOOR FIRE ALARM ZONE KEY PLAN |
| FA-K-4 - FOURTH FLOOR FIRE ALARM ZONE KEY PLAN |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-K-4 - FOURTH FLOOR FIRE ALARM ZONE KEY PLAN |
| FA-K-5 - FIFTH FLOOR FIRE ALARM ZONE KEY PLAN |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-K-5 - FIFTH FLOOR FIRE ALARM ZONE KEY PLAN |
| FA-K-6 - SIXTH FLOOR FIRE AND PENTHOUSE ALARM ZONE KEY PLANS |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-K-6 - SIXTH FLOOR FIRE AND PENTHOUSE ALARM ZONE KEY PLANS |
| FA-E-1.1 - BUILDING 1 - MAIN TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (1 OF 5) |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-E-1.1 - BUILDING 1 - MAIN TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (1 OF 5) |
| FA-E-1.2 - BUILDING 1 - MAIN TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (2 OF 5) |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-E-1.2 - BUILDING 1 - MAIN TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (2 OF 5) |
| FA-E-1.3 - BUILDING 1 - MAIN TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (3 OF 5) |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-E-1.3 - BUILDING 1 - MAIN TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (3 OF 5) |
| FA-E-1.4 - BUILDING 1 - MAIN TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (4 OF 5) |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-E-1.4 - BUILDING 1 - MAIN TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (4 OF 5) |
| FA-E-1.5 - BUILDING 1 - MAIN TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (5 OF 5) |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-E-1.5 - BUILDING 1 - MAIN TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (5 OF 5) |
| FA-E-2.1 - BUILDING 2 - ACC - ENLARGED FIRE ALARM EQUIPMENT LOCATION PLANS |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-E-2.1 - BUILDING 2 - ACC - ENLARGED FIRE ALARM EQUIPMENT LOCATION PLANS |
| FA-E-3.1 - BUILDING 3 - CARES TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (1 OF 3) |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-E-3.1 - BUILDING 3 - CARES TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (1 OF 3) |
| FA-E-3.2 - BUILDING 3 - CARES TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (2 OF 3) |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-E-3.2 - BUILDING 3 - CARES TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (2 OF 3) |
| FA-E-3.3 - BUILDING 3 - CARES TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (3 OF 3) |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-E-3.3 - BUILDING 3 - CARES TOWER - ENLARGED FIRE ALARM EQUIPMENT PLANS (3 OF 3) |
| FA-E-4.1 - BUILDING 4 - RESEARCH WING - ENLARGED FIRE ALARM EQUIPMENT PLANS (1 OF 1) |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-E-4.1 - BUILDING 4 - RESEARCH WING - ENLARGED FIRE ALARM EQUIPMENT PLANS (1 OF 1) |
| FA-E-5.1 - BUILDING 5 - ENERGY CENTER - ENLARGED FIRE ALARM EQUIPMENT PLANS (1 OF 1) |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-E-5.1 - BUILDING 5 - ENERGY CENTER - ENLARGED FIRE ALARM EQUIPMENT PLANS (1 OF 1) |
| FA-E-6.1 - BUILDING 6 - PALMSLAB WAREHOUSE - ENLARGED FIRE ALARM EQUIPMENT PLANS (1 OF 1) |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-E-6.1 - BUILDING 6 - PALMS/LAB WAREHOUSE - ENLARGED FIRE ALARM EQUIPMENT PLANS (1 OF 1) |
| FA-A-1.1 - NODE 1.1 - MAIN BUILDING BASEMENT - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.1 - NODE 1.1 - MAIN BUILDING BASEMENT - ADDRESSABLE |
| FA-A-1.2 - NODE 1.2 - MAIN BUILDING BASEMENT - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.2 - NODE 1.2 - MAIN BUILDING BASEMENT - ADDRESSABLE |
| FA-A-1.3a - NODE 1.3 - MAIN BUILDING SUB-BASEMENT - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.3a - NODE 1.3 - MAIN BUILDING SUB-BASEMENT - ADDRESSABLE |
| FA-A-1.3b - NODE 1.3 - MAIN BUILDING BASEMENT - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.3b - NODE 1.3 - MAIN BUILDING BASEMENT - ADDRESSABLE |
| FA-A-1.3c - NODE 1.3 - PARKING STRUCTURE BASEMENT - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.3c - NODE 1.3 - PARKING STRUCTURE BASEMENT - ADDRESSABLE |
| FA-A-1.3d - NODE 1.3 - PARKING STRUCTURE FIRST FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.3d - NODE 1.3 - PARKING STRUCTURE FIRST FLOOR - ADDRESSABLE |
| FA-A-1.3e - NODE 1.3 - PARKING STRUCTURE SECOND FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.3e - NODE 1.3 - PARKING STRUCTURE SECOND FLOOR - ADDRESSABLE |
| FA-A-1.3f - NODE 1.3 - PARKING STRUCTURE THIRD FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.3f - NODE 1.3 - PARKING STRUCTURE THIRD FLOOR - ADDRESSABLE |
| FA-A-1.4 - NODE 1.4 - MAIN BUILDING FIRST FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.4 - NODE 1.4 - MAIN BUILDING FIRST FLOOR - ADDRESSABLE |
| FA-A-1.5 - NODE 1.5 - MAIN BUILDING BASEMENT AND FIRST FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.5 - NODE 1.5 - MAIN BUILDING BASEMENT AND FIRST FLOOR - ADDRESSABLE |
| FA-A-1.6 - NODE 1.6 - MAIN BUILDING FIRST FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.6 - NODE 1.6 - MAIN BUILDING FIRST FLOOR - ADDRESSABLE |
| FA-A-1.7 - NODE 1.7 - MAIN BUILDING FIRST FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.7 - NODE 1.7 - MAIN BUILDING FIRST FLOOR - ADDRESSABLE |
| FA-A-1.8 - NODE 1.8 - MAIN BUILDING SECOND FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.8 - NODE 1.8 - MAIN BUILDING SECOND FLOOR - ADDRESSABLE |
| FA-A-1.9 - NODE 1.9 - MAIN BUILDING SECOND FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.9 - NODE 1.9 - MAIN BUILDING SECOND FLOOR - ADDRESSABLE |
| FA-A-1.10 - NODE 1.10 - MAIN BUILDING SECOND AND THIRD FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.10 - NODE 1.10 - MAIN BUILDING SECOND AND THIRD FLOOR - ADDRESSABLE |
| FA-A-1.11 - NODE 1.11 - MAIN BUILDING THIRD FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.11 - NODE 1.11 - MAIN BUILDING THIRD FLOOR - ADDRESSABLE |
| FA-A-1.12 - NODE 1.12 - MAIN BUILDING FOURTH FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.12 - NODE 1.12 - MAIN BUILDING FOURTH FLOOR - ADDRESSABLE |
| FA-A-1.13 - NODE 1.13 - MAIN BUILDING FIFTH FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.13 - NODE 1.13 - MAIN BUILDING FIFTH FLOOR - ADDRESSABLE |
| FA-A-1.14a - NODE 1.14 - MAIN BUILDING SIXTH FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.14a - NODE 1.14 - MAIN BUILDING SIXTH FLOOR - ADDRESSABLE |
| FA-A-1.14b - NODE 1.14 - MAIN BUILDING PENTHOUSE - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-1.14b - NODE 1.14 - MAIN BUILDING PENTHOUSE - ADDRESSABLE |
| FA-A-2.1 - NODE 2.1 - ACC BUILDING BASEMENT - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-2.1 - NODE 2.1 - ACC BUILDING BASEMENT - ADDRESSABLE |
| FA-A-2.2 - NODE 2.2 - ACC BUILDING FIRST FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-2.2 - NODE 2.2 - ACC BUILDING FIRST FLOOR - ADDRESSABLE |
| FA-A-2.3 - NODE 2.2 AND 2.3 - ACC BUILDING SECOND FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-2.3 - NODE 2.2 AND 2.3 - ACC BUILDING SECOND FLOOR - ADDRESSABLE |
| FA-A-2.4 - NODE 2.4 - ACC BUILDING THIRD FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-2.4 - NODE 2.4 - ACC BUILDING THIRD FLOOR - ADDRESSABLE |
| FA-A-2.5 - NODE 2.5 - ACC BUILDING FOURTH FLOOR AND PENTHOUSE - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-2.5 - NODE 2.5 - ACC BUILDING FOURTH FLOOR AND PENTHOUSE - ADDRESSABLE |
| FA-A-3.1 - NODE 3.1 - CARES TOWER LEVEL A - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-3.1 - NODE 3.1 - CARES TOWER LEVEL A - ADDRESSABLE |
| FA-A-3.2 - NODE 3.2 - CARES TOWER BASEMENT - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-3.2 - NODE 3.2 - CARES TOWER BASEMENT - ADDRESSABLE |
| FA-A-3.3 - NODE 3.3 - CARES TOWER FIRST FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-3.3 - NODE 3.3 - CARES TOWER FIRST FLOOR - ADDRESSABLE |
| FA-A-3.4 - NODE 3.4 - CARES TOWER SECOND FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-3.4 - NODE 3.4 - CARES TOWER SECOND FLOOR - ADDRESSABLE |
| FA-A-3.5 - NODE 3.5 - CARES TOWER THIRD FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-3.5 - NODE 3.5 - CARES TOWER THIRD FLOOR - ADDRESSABLE |
| FA-A-3.6 - NODE 3.6 - CARES TOWER FOURTH FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-3.6 - NODE 3.6 - CARES TOWER FOURTH FLOOR - ADDRESSABLE |
| FA-A-3.7 - NODE 3.7 - CARES TOWER FIFTH FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-3.7 - NODE 3.7 - CARES TOWER FIFTH FLOOR - ADDRESSABLE |
| FA-A-3.8 - NODE 3.8 - CARES TOWER SIXTH FLOOR AND PENTHOUSE - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-3.8 - NODE 3.8 - CARES TOWER SIXTH FLOOR AND PENTHOUSE - ADDRESSABLE |
| FA-A-4.1a - NODE 4.1 - RESEARCH WING BASEMENT AND FIRST FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-4.1a - NODE 4.1 - RESEARCH WING BASEMENT AND FIRST FLOOR - ADDRESSABLE |
| FA-A-4.1b - NODE 4.1 - RESEARCH WING SECOND AND THIRD FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-4.1b - NODE 4.1 - RESEARCH WING SECOND AND THIRD FLOOR - ADDRESSABLE |
| FA-A-5.1 - NODE 5.1 - ENERGY CENTER BASEMENT AND FIRST FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-5.1 - NODE 5.1 - ENERGY CENTER BASEMENT AND FIRST FLOOR - ADDRESSABLE |
| FA-A-6.1a - NODE 6.1 - LAB WAREHOUSE BASEMENT - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-6.1a - NODE 6.1 - LAB WAREHOUSE BASEMENT - ADDRESSABLE |
| FA-A-6.1b - NODE 6.1 - LAB WAREHOUSE FIRST FLOOR - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-6.1b - NODE 6.1 - LAB WAREHOUSE FIRST FLOOR - ADDRESSABLE |
| FA-A-6.1c - NODE 6.1 - LAB WAREHOUSE PENTHOUSE - ADDRESSABLE |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-A-6.1c - NODE 6.1 - LAB WAREHOUSE PENTHOUSE - ADDRESSABLE |
| FA-N-1.1 - NODE 1.1 - MAIN BUILDING BASEMENT - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.1 - NODE 1.1 - MAIN BUILDING BASEMENT - NOTIFICATION |
| FA-N-1.2 - NODE 1.2 - MAIN BUILDING BASEMENT - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.2 - NODE 1.2 - MAIN BUILDING BASEMENT - NOTIFICATION |
| FA-N-1.3a - NODE 1.3 - MAIN BUILDING SUB-BASEMENT - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.3a - NODE 1.3 - MAIN BUILDING SUB-BASEMENT - NOTIFICATION |
| FA-N-1.3b - NODE 1.3 - MAIN BUILDING BASEMENT - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.3b - NODE 1.3 - MAIN BUILDING BASEMENT - NOTIFICATION |
| FA-N-1.3c - NODE 1.3 - PARKING STRUCTURE BASEMENT - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.3c - NODE 1.3 - PARKING STRUCTURE BASEMENT - NOTIFICATION |
| FA-N-1.3d - NODE 1.3 - PARKING STRUCTURE FIRST FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.3d - NODE 1.3 - PARKING STRUCTURE FIRST FLOOR - NOTIFICATION |
| FA-N-1.3e - NODE 1.3 - PARKING STRUCTURE SECOND FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.3e - NODE 1.3 - PARKING STRUCTURE SECOND FLOOR - NOTIFICATION |
| FA-N-1.3f - NODE 1.3 - PARKING STRUCTURE THIRD FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.3f - NODE 1.3 - PARKING STRUCTURE THIRD FLOOR - NOTIFICATION |
| FA-N-1.4 - NODE 1.4 - MAIN BUILDING FIRST FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.4 - NODE 1.4 - MAIN BUILDING FIRST FLOOR - NOTIFICATION |
| FA-N-1.5 - NODE 1.5 - MAIN BUILDING BASEMENT AND FIRST FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.5 - NODE 1.5 - MAIN BUILDING BASEMENT AND FIRST FLOOR - NOTIFICATION |
| FA-N-1.6 - NODE 1.6 - MAIN BUILDING FIRST FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.6 - NODE 1.6 - MAIN BUILDING FIRST FLOOR - NOTIFICATION |
| FA-N-1.7 - NODE 1.7 - MAIN BUILDING FIRST FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.7 - NODE 1.7 - MAIN BUILDING FIRST FLOOR - NOTIFICATION |
| FA-N-1.8 - NODE 1.8 - MAIN BUILDING SECOND FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.8 - NODE 1.8 - MAIN BUILDING SECOND FLOOR - NOTIFICATION |
| FA-N-1.9 - NODE 1.9 - MAIN BUILDING SECOND FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.9 - NODE 1.9 - MAIN BUILDING SECOND FLOOR - NOTIFICATION |
| FA-N-1.10 - NODE 1.10 - MAIN BUILDING SECOND AND THIRD FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.10 - NODE 1.10 - MAIN BUILDING SECOND AND THIRD FLOOR - NOTIFICATION |
| FA-N-1.11 - NODE 1.11 - MAIN BUILDING THIRD FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.11 - NODE 1.11 - MAIN BUILDING THIRD FLOOR - NOTIFICATION |
| FA-N-1.12 - NODE 1.12 - MAIN BUILDING FOURTH FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.12 - NODE 1.12 - MAIN BUILDING FOURTH FLOOR - NOTIFICATION |
| FA-N-1.13 - NODE 1.13 - MAIN BUILDING FIFTH FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.13 - NODE 1.13 - MAIN BUILDING FIFTH FLOOR - NOTIFICATION |
| FA-N-1.14a - NODE 1.14 - MAIN BUILDING SIXTH FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.14a - NODE 1.14 - MAIN BUILDING SIXTH FLOOR - NOTIFICATION |
| FA-N-1.14b - NODE 1.14 - MAIN BUILDING PENTHOUSE FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-1.14b - NODE 1.14 - MAIN BUILDING PENTHOUSE FLOOR - NOTIFICATION |
| FA-N-2.1 - NODE 2.1 - ACC BUILDING BASEMENT - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-2.1 - NODE 2.1 - ACC BUILDING BASEMENT - NOTIFICATION |
| FA-N-2.2 - NODE 2.2 - ACC BUILDING FIRST FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-2.2 - NODE 2.2 - ACC BUILDING FIRST FLOOR - NOTIFICATION |
| FA-N-2.3 - NODE 2.2 AND 2.3 - ACC BUILDING SECOND FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-2.3 - NODE 2.2 AND 2.3 - ACC BUILDING SECOND FLOOR - NOTIFICATION |
| FA-N-2.4 - NODE 2.4 - ACC BUILDING THIRD FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-2.4 - NODE 2.4 - ACC BUILDING THIRD FLOOR - NOTIFICATION |
| FA-N-2.5 - NODE 2.5 - ACC BUILDING FOURTH FLOOR AND PENTHOUSE - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-2.5 - NODE 2.5 - ACC BUILDING FOURTH FLOOR AND PENTHOUSE - NOTIFICATION |
| FA-N-3.1 - NODE 3.1 - CARES TOWER LEVEL A - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-3.1 - NODE 3.1 - CARES TOWER LEVEL A - NOTIFICATION |
| FA-N-3.2 - NODE 3.2 - CARES TOWER BASEMENT - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-3.2 - NODE 3.2 - CARES TOWER BASEMENT - NOTIFICATION |
| FA-N-3.3 - NODE 3.3 - CARES TOWER FIRST FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-3.3 - NODE 3.3 - CARES TOWER FIRST FLOOR - NOTIFICATION |
| FA-N-3.4 - NODE 3.4 - CARES TOWER SECOND FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-3.4 - NODE 3.4 - CARES TOWER SECOND FLOOR - NOTIFICATION |
| FA-N-3.5 - NODE 3.5 - CARES TOWER THIRD FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-3.5 - NODE 3.5 - CARES TOWER THIRD FLOOR - NOTIFICATION |
| FA-N-3.6 - NODE 3.6 - CARES TOWER FOURTH FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-3.6 - NODE 3.6 - CARES TOWER FOURTH FLOOR - NOTIFICATION |
| FA-N-3.7 - NODE 3.7 - CARES TOWER FIFTH FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-3.7 - NODE 3.7 - CARES TOWER FIFTH FLOOR - NOTIFICATION |
| FA-N-3.8 - NODE 3.8 - CARES TOWER SIXTH FLOOR AND PENTHOUSE - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-3.8 - NODE 3.8 - CARES TOWER SIXTH FLOOR AND PENTHOUSE - NOTIFICATION |
| FA-N-4.1a - NODE 4.1 - RESEARCH WING BASEMENT AND FIRST FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-4.1a - NODE 4.1 - RESEARCH WING BASEMENT AND FIRST FLOOR - NOTIFICATION |
| FA-N-4.1b - NODE 4.1 - RESEARCH WING SECOND AND THIRD FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-4.1b - NODE 4.1 - RESEARCH WING SECOND AND THIRD FLOOR - NOTIFICATION |
| FA-N-5.1 - NODE 5.1 - ENERGY CENTER BASEMENT AND FIRST FLOOR - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-5.1 - NODE 5.1 - ENERGY CENTER BASEMENT AND FIRST FLOOR - NOTIFICATION |
| FA-N-6.1a - NODE 6.1 - LAB WAREHOUSE BASEMENT - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-6.1a - NODE 6.1 - LAB WAREHOUSE BASEMENT - NOTIFICATION |
| FA-N-6.1b - NODE 6.1 - LAB WAREHOUSE FIRST FLOOR AND PENTHOUSE - NOTIFICATION |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-N-6.1b - NODE 6.1 - LAB WAREHOUSE FIRST FLOOR AND PENTHOUSE - NOTIFICATION |
| FA-R-0.1 - DEMOLITION FIRE ALARM SYSTEM BACKBONE DIAGRAM |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-R-0.1 - DEMOLITION FIRE ALARM SYSTEM BACKBONE DIAGRAM |
| FA-R-0.2 - NEW FIRE ALARM SYSTEM BACKBONE DIAGRAM |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-R-0.2 - NEW FIRE ALARM SYSTEM BACKBONE DIAGRAM |
| FA-D-0.1 - FIRE ALARM SYSTEM DETAILS |
| 17069 FFH CF - FIRE ALARM STUDY - R19_Ryan.P.Hewit |
| FA-D-0.1 - FIRE ALARM SYSTEM DETAILS |
File details come from the government source that posted it. Updated .