280500 - COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY. - Revised 7-26 -2021.pdf

PDF 252 KB Posted

Attached to
Z2BG--PROJECT 541-18-101: UPGRADE FIRE ALARM SYSTEM (CONSTRUCTION) - LOUIS STOKES VA MEDICAL CENTER (VAMC) - CLEVELAND, OH **NOTE: UNRESTRICTED - FULL AND OPEN COMPETITION
Solicitation number
36C25020B0065
Issued by

About this file

This federal contract opportunity announcement solicits bids for Project #541-18-101 to upgrade the fire alarm system at the Louis Stokes VA Medical Center in Cleveland, Ohio. The multi-phase project will install a new campus fiber loop andNotifierA head end units in Phase 1. Phase 2 will rewire existing field devices like strobes, horns, pull stations and smoke detectors to report to the correct zone controller. All devices will be reprogrammed. Upon completion, each smoke compartment will have a dedicated NotifierA control panel and associated devices contained within the zone. The project magnitude is between $2 million to $5 million. The duration shall not exceed 425 calendar days from the notice to proceed. Bids are due approximately 30 days following the November 24, 2020 posting at SAM.gov. Bonds are required. A site visit will be scheduled.

View the file

Other files

File Type Posted
36C25020B0065 0010.docx DOCX document
WD Cuyahoga 07.30.2021.pdf PDF
36C25020B0065 0009.docx DOCX document
36C25020B0065 0008.docx DOCX document
36C25020B0065 0007.docx DOCX document
541-18-101 - Upgrade Fire Alarm - Bid Documents Drawings_Part7.pdf PDF
541-18-101 - Upgrade Fire Alarm - Bid Documents Drawings_Part6.pdf PDF
36C25020B0065 0006.docx DOCX document
36C25020B0065 0005.docx DOCX document
541-18-101 - Upgrade Fire Alarm - Bid Documents Drawings_Part5.pdf PDF
541-18-101 - Upgrade Fire Alarm - Bid Documents Drawings_Part4.pdf PDF
36C25020B0065 0004.docx DOCX document
541-18-101 - Upgrade Fire Alarm - Bid Documents Drawings_Part3.pdf PDF
36C25020B0065 0003.docx DOCX document
36C25020B0065 0002.docx DOCX document
541-18-101 - Upgrade Fire Alarm - Bid Documents Drawings_Part2.pdf PDF
541-18-101 - Upgrade Fire Alarm - Bid Documents Drawings_Part1 (1).pdf PDF
36C25020B0065 0001.docx DOCX document
541-18-101 - Upgrade Fire Alarm - Bid Documents Specifications 02.pdf PDF
36C25020B0065_1.docx DOCX document
CUY WD 04.30.2021.pdf PDF
VAMC Health Requirements 05.26.2021.pdf PDF
Notifier JA Complete REDACTED.pdf PDF
VHA Directive 1192.01, Seasonal Influenza Prevention Program for VHA Health Care Personnel.pdf PDF
Corwin Russwin JA Complete REDACTED.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA PROJECT NO. 541-18-101

LOUIS STOKES CLEVELAND VAMC – UPGRADE FIRE ALARM

BID DOCUMENTS SUBMISSION

28 05 00 - 1

SECTION 28 05 00

COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY

PART 1 - GENERAL

1.1 DESCRIPTION

A. This Section, Common Work Results for Electronic Safety and Security (ESS), applies to all sections of Division 28.

B. This section shall apply to newly installed systems, devices, equipment and to connections between new systems and existing devices. References to additional systems not provided under the scope of this project shall not be applicable.

C. Furnish and install fully functional electronic safety and security cabling system(s), equipment and approved accessories in accordance with the specification section(s), drawing(s), and referenced publications. Capacities and ratings of cable and other items and arrangements for the specified items are shown on each system's required Bill of Materials (BOM) and verified on the approved system drawing(s). If there is a conflict between contract's specification(s) and drawings(s), the contract's specification requirements shall prevail.

D. Repair Service Replacement Parts On-site service during the warranty period shall be provided as specified under Emergency

Service. The Contractor shall guarantee all parts and labor for a term of one (1) year, unless dictated otherwise in this specification from the acceptance date of the system as described in Part 5 of this Specification. The Contractor shall be responsible for all equipment, software, shipping, transportation charges, and expenses associated with the service of the system for one (1) year. The Contractor shall provide 24-hour telephone support for the software program at no additional charge to the owner. Software support shall include all software updates that occur during the warranty period.

E. Section Includes:

1. Description of Work for Electronic Safety and Security Systems,

2. Electronic Safety and security equipment coordination with relating Divisions,

3. Submittal Requirements for Electronic Safety and Security,

4. Miscellaneous Supporting equipment and materials for Electronic Safety and Security,

5. Electronic Safety and security installation requirements.

1.2 RELATED WORK

A. Section 010000 - GENERAL REQUIREMENTS. For General Requirements.

B. Section 078400 - FIRESTOPPING. Requirements for firestopping application and use.

28 05 00 - 2

C. Section 087100 - DOOR HARDWARE. Requirements for door installation.

D. Section 260511 - REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.

Requirements for connection of high voltage.

E. Section 260521 - LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES (600 VOLTS AND BELOW). Requirements for power cables.

F. Section 260533 - RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS.

Requirements for infrastructure.

G. Section 280513 - CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY. Requirements for conductors and cables.

H. Section 280526 - GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY. Requirements for grounding of equipment.

I. Section 280528.33 - CONDUITS AND BOXES FOR ELECTRONIC SAFETY AND SECURITY. Requirements for infrastructure.

J. Section 280800 - COMMISIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS. Requirements for Commissioning.

1.3 DEFINITIONS

A. AGC: Automatic Gain Control.

B. Basket Cable Tray: A fabricated structure consisting of wire mesh bottom and side rails.

C. BICSI: Building Industry Consulting Service International.

D. Central Station: A PC with software designated as the main controlling PC of the ESS system. Where this term is presented with initial capital letters, this definition applies.

E. Channel Cable Tray: A fabricated structure consisting of a one-piece, ventilated-bottom or solid-bottom channel section.

F. Controller: An intelligent peripheral control unit that uses a computer for controlling its operation. Where this term is presented with an initial capital letter, this definition applies.

G. CPU: Central processing unit.

H. Credential: Data assigned to an entity and used to identify that entity.

I. EMI: Electromagnetic interference.

J. EMT: Electric Metallic Tubing.

K. ESS: Electronic Security System.

L. File Server: A PC in a network that stores the programs and data files shared by users.

M. GFI: Ground fault interrupter.

N. IDC: Insulation displacement connector.

O. I/O: Input/Output.

P. Ladder Cable Tray: A fabricated structure consisting of two longitudinal side rails connected by individual transverse members (rungs).

28 05 00 - 3

Q. LAN: Local area network.

R. LCD: Liquid-crystal display.

S. LED: Light-emitting diode.

T. Location: A Location on the network having a PC-to-Controller communications link, with additional Controllers at the Location connected to the PC-to-Controller link with RS-485 communications loop. Where this term is presented with an initial capital letter, this definition applies.

U. Low Voltage: As defined in NFPA 70 for circuits and equipment operating at less than 50 V or for remote-control and signaling power-limited circuits.

V. NEC: National Electric Code

W. NEMA: National Electrical Manufacturers Association

X. NFPA: National Fire Protection Association

Y. NTSC: National Television System Committee.

Z. NRTL: Nationally Recognized Testing Laboratory.

AA. Open Cabling: Passing telecommunications cabling through open space (e.g., between the studs of a wall cavity).

BB. PACS: Physical Access Control System; A system comprised of cards, readers, door controllers, servers and software to control the physical ingress and egress of people within a given space

CC. PC: Personal computer. This acronym applies to the Central Station, workstations, and file servers.

DD. PCI Bus: Peripheral component interconnect; a peripheral bus providing a high-speed data path between the CPU and peripheral devices (such as monitor, disk drive, or network).

EE. PDF: (Portable Document Format.) The file format used by the Acrobat document exchange system software from Adobe.

FF. RCDD: Registered Communications Distribution Designer.

GG. RFI: Radio-frequency interference.

HH. RIGID: Rigid conduit is galvanized steel tubing, with a tubing wall that is thick enough to allow it to be threaded.

II. RS-232: An TIA/EIA standard for asynchronous serial data communications between terminal devices. This standard defines a

25-pin connector and certain signal characteristics for interfacing computer equipment.

JJ. RS-485: An TIA/EIA standard for multipoint communications.

KK. Solid-Bottom or Non-ventilated Cable Tray: A fabricated structure consisting of integral or separate longitudinal side rails, and a bottom without ventilation openings.

LL. TCP/IP: Transport control protocol/Internet protocol incorporated into Microsoft Windows.

28 05 00 - 4

MM. Trough or Ventilated Cable Tray: A fabricated structure consisting of integral or separate longitudinal rails and a bottom having openings sufficient for the passage of air and using 75 percent or less of the plan area of the surface to support cables.

NN. UPS: Uninterruptible Power Supply

OO. UTP: Unshielded Twisted Pair

PP. Workstation: A PC with software that is configured for specific limited security system functions.

1.4 QUALITY ASSURANCE

A. Manufacturers Qualifications: The manufacturer shall regularly and presently produce, as one of the manufacturer's principal products, the equipment and material specified for this project, and shall have manufactured the item for at least three years.

B. Product Qualification:

1. Manufacturer's product shall have been in satisfactory operation, on three installations of similar size and type as this project, for approximately three years.

2. The Government reserves the right to require the Contractor to submit a list of installations where the products have been in operation before approval.

C. Contractor Qualification:

28 05 00 - 5

1. The Contractor or ESS system sub-contractor shall be licensed with a minimum of five (5) years experience installing and servicing systems of similar scope and complexity. The

Contractor shall be an authorized regional representative of the ESS system manufacturer. The Contractor shall provide four (4) current references from clients with systems of similar scope and complexity which became operational in the past three (3) years. At least three (3) of the references shall be utilizing the same system components, in a similar configuration as the proposed system. The references must include a current point of contact, company or agency name, address, telephone number, complete system description, date of completion, and approximate cost of the project. The owner reserves the option to visit the reference sites, with the site owner's permission and representative, to verify the quality of installation and the references' level of satisfaction with the system. The Contractor shall provide copies of system manufacturer certification for all technicians. The Contractor shall only utilize factory-trained technicians to install, program, and service the ESS system. The Contractor shall only utilize factory-trained technicians to install, terminate and service controller/field panels and modules. The technicians shall have a minimum of five (5) continuous years of technical experience in electronic safety and security systems. The Contractor shall have a local service facility. The facility shall be located within 60 miles of the project site. The local facility shall include sufficient spare parts inventory to support the service requirements associated with this contract. The facility shall also include appropriate diagnostic equipment to perform diagnostic procedures. The COR reserves the option of surveying the company's facility to verify the service inventory and presence of a local service organization.

2. The Contractor shall provide proof project superintendent with BICSI Certified Commercial Installer Level 1, Level 2, or

Technician to provide oversight of the project.

3. Cable installer must have on staff a Registered Communication Distribution Designer (RCDD) certified by Building Industry

Consulting Service International. The staff member shall provide consistent oversight of the project cabling throughout design, layout, installation, termination and testing.

D. Service Qualifications: There shall be a permanent service organization maintained or trained by the manufacturer which will render satisfactory service to this installation within four hours of receipt of notification that service is needed. Submit name and address of service organizations.

28 05 00 - 6

1.5 GENERAL ARANGEMENT OF CONTRACT DOCUMENTS

A. The Contract Documents supplement to this specification indicates approximate locations of equipment. The installation and/or locations of the equipment and devices shall be governed by the intent of the design; specification and Contract Documents, with due regard to actual site conditions, recommendations, ambient factors affecting the equipment and operations in the vicinity.

The Contract Documents are diagrammatic and do not reveal all offsets, bends, elbows, components, materials, and other specific elements that may be required for proper installation. If any departure from the contract documents is deemed necessary, or in the event of conflicts, the Contractor shall submit details of such departures or conflicts in writing to the owner or owner's representative for his or her comment and/or approval before initiating work.

B. Anything called for by one of the Contract Documents and not called for by the others shall be of like effect as if required or called by all, except if a provision clearly designed to negate or alter a provision contained in one or more of the other

Contract Documents shall have the intended effect. In the event of conflicts among the Contract Documents, the Contract Documents shall take precedence in the following order: the Form of

Agreement; the Supplemental General Conditions; the Special

Conditions; the Specifications with attachments; and the drawings.

1.6 SUBMITTALS

A. Submit in accordance with Section 013323, SHOP DRAWINGS, PRODUCT

DATA, AND SAMPLES.

B. The Government's approval shall be obtained for all equipment and material before delivery to the job site. Delivery, storage or installation of equipment or material which has not had prior approval will not be permitted at the job site.

C. Submittals for individual systems and equipment assemblies which consist of more than one item or component shall be made for the system or assembly as a whole. Partial submittals will not be considered for approval.

1. Mark the submittals, "SUBMITTED UNDER

SECTION__________________".

2. Submittals shall be marked to show specification reference including the section and paragraph numbers.

3. Submit each section separately.

D. The submittals shall include the following:

1. Information that confirms compliance with contract requirements. Include the manufacturer's name, model or catalog numbers, catalog information, technical data sheets, shop drawings, pictures, nameplate data and test reports as required.

2. Parts list which shall include those replacement parts recommended by the equipment manufacturer, quantity of parts, current price and availability of each part.

28 05 00 - 7

E. Submittals shall be in full compliance of the Contract Documents.

All submittals shall be provided in accordance with this section.

Submittals lacking the breath or depth these requirements will be considered incomplete and rejected. Submissions are considered multidisciplinary and shall require coordination with applicable divisions to provide a complete and comprehensive submission package. All submittals shall include adequate descriptive literature, catalog cuts, shop drawings and other data necessary for the Government to ascertain that the proposed equipment and materials comply with specification requirements. Catalog cuts submitted for approval shall be legible and clearly identify equipment being submitted. Additional general provisions are as follows:

1. The Contractor shall schedule submittals in order to maintain the project schedule. For coordination drawings refer to

Specification Section 013310 - Design Submittal Procedures, which outline basic submittal requirements and coordination.

Section 013310 shall be used in conjunction with this section.

2. The Contractor shall identify variations from requirements of Contract Documents and state product and system limitations, which may be detrimental to successful performance of the completed work or system.

3. Each package shall be submitted at one (1) time for each review and include components from applicable disciplines

(e.g., electrical work, architectural finishes, door hardware, etc.) which are required to produce an accurate and detailed depiction of the project.

4. Manufacturer's information used for submittal shall have pages with items for approval tagged, items on pages shall be identified, and capacities and performance parameters for review shall be clearly marked through use of an arrow or highlighting. Provide space for COR and Contractor review stamps.

5. Technical Data Drawings shall be in the latest version of AutoCAD®, drawn accurately, and in accordance with VA CAD

Standards CAD Standard Application Guide, and VA BIM Guide.

FREEHAND SKETCHES OR COPIED VERSIONS OF THE CONSTRUCTION

DOCUMENTS WILL NOT BE ACCEPTED. The Contractor shall not reproduce Contract Documents or copy standard information as the basis of the Technical Data Drawings. If departures from the technical data drawings are subsequently deemed necessary by the Contractor, details of such departures and the reasons thereof shall be submitted in writing to the COR for approval before the initiation of work.

6. Packaging: The Contractor shall organize the submissions according to the following packaging requirements.

a. Binders: For each manual, provide heavy duty, commercial quality, durable three (3) ring vinyl covered loose leaf binders, sized to receive 8.5 x 11 in paper, and appropriate capacity to accommodate the contents. Provide a clear plastic sleeve on the spine to hold labels describing the contents. Provide pockets in the covers to receive folded sheets.

28 05 00 - 8

1) Where two (2) or more binders are necessary to accommodate data; correlate data in each binder into related groupings according to the Project Manual table of contents. Cross-referencing other binders where necessary to provide essential information for communication of proper operation and/or maintenance of the component or system.

2) Identify each binder on the front and spine with printed binder title, Project title or name, and subject matter covered. Indicate the volume number if applicable.

b. Dividers: Provide heavy paper dividers with celluloid tabs for each Section. Mark each tab to indicate contents.

c. Protective Plastic Jackets: Provide protective transparent plastic jackets designed to enclose diagnostic software for computerized electronic equipment.

d. Text Material: Where written material is required as part of the manual use the manufacturer's standard printed material, or if not available, specially prepared data, neatly typewritten on 8.5 inches by 11 inches 20 pound white bond paper.

e. Drawings: Where drawings and/or diagrams are required as part of the manual, provide reinforced punched binder tabs on the drawings and bind them with the text.

1) Where oversized drawings are necessary, fold the drawings to the same size as the text pages and use as a foldout.

2) If drawings are too large to be used practically as a foldout, place the drawing, neatly folded, in the front or rear pocket of the binder. Insert a type written page indicating the drawing title, description of contents and drawing location at the appropriate location of the manual.

3) Drawings shall be sized to ensure details and text is of legible size. Text shall be no less than 1/16“ tall.

f. Manual Content: Submit in accordance with Section 010000, GENERAL REQUIREMENTS.

1) Maintenance and Operation Manuals: Submit as required for systems and equipment specified in the technical sections. Furnish four copies, bound in hardback binders, (manufacturer's standard binders) or an approved equivalent. Furnish one complete manual as specified in the technical section but in no case later than prior to performance of systems or equipment test, and furnish the remaining manuals prior to contract completion.

28 05 00 - 9

2) Inscribe the following identification on the cover: the words "MAINTENANCE AND OPERATION MANUAL," the name and location of the system, equipment, building, name of

Contractor, and contract number. Include in the manual the names, addresses, and telephone numbers of each subcontractor installing the system or equipment and the local representatives for the system or equipment.

3) The manuals shall include:

a) Internal and interconnecting wiring and control diagrams with data to explain detailed operation and control of the equipment.

b) A control sequence describing start-up, operation, and shutdown.

c) Description of the function of each principal item of equipment.

d) Installation and maintenance instructions.

e) Safety precautions.

f) Diagrams and illustrations.

g) Testing methods.

h) Performance data.

i) Pictorial "exploded" parts list with part numbers.

Emphasis shall be placed on the use of special tools and instruments. The list shall indicate sources of supply, recommended spare parts, and name of servicing organization.

j) Appendix; list qualified permanent servicing organizations for support of the equipment, including addresses and certified qualifications.

g. Binder Organization: Organize each manual into separate sections for each piece of related equipment. At a minimum, each manual shall contain a title page, table of contents, copies of Product Data supplemented by drawings and written text, and copies of each warranty, bond, certifications, and service Contract issued. Refer to Group

I through V Technical Data Package Submittal requirements for required section content.

h. Title Page: Provide a title page as the first sheet of each manual to include the following information; project name and address, subject matter covered by the manual, name and address of the Project, date of the submittal, name, address, and telephone number of the Contractor, and cross references to related systems in other operating and/or maintenance manuals.

28 05 00 - 10

i. Table of Contents: After the title page, include a type written table of contents for each volume, arranged systematically according to the Project Manual format.

Provide a list of each product included, identified by product name or other appropriate identifying symbols and indexed to the content of the volume. Where more than one

(1) volume is required to hold data for a particular system, provide a comprehensive table of contents for all volumes in each volume of the set.

j. General Information Section: Provide a general information section immediately following the table of contents, listing each product included in the manual, identified by product name. Under each product, list the name, address, and telephone number of the installer and maintenance

Contractor. In addition, list a local source for replacement parts and equipment.

k. Drawings: Provide specially prepared drawings where necessary to supplement the manufacturers printed data to illustrate the relationship between components of equipment or systems, or provide control or flow diagrams.

Coordinate these drawings with information contained in

Project Record Drawings to assure correct illustration of the completed installation.

l. Manufacturer's Data: Where manufacturer's standard printed data is included in the manuals, include only those sheets that are pertinent to the part or product installed. Mark each sheet to identify each part or product included in the installation. Where more than one (1) item in tabular format is included, identify each item, using appropriate references from the Contract Documents. Identify data that is applicable to the installation and delete references to information which is not applicable.

m. Where manufacturer's standard printed data is not available and the information is necessary for proper operation and maintenance of equipment or systems, or it is necessary to provide additional information to supplement the data included in the manual, prepare written text to provide the necessary information. Organize the text in a consistent format under a separate heading for different procedures.

Where necessary, provide a logical sequence of instruction for each operating or maintenance procedure. Where similar or more than one product is listed on the submittal the

Contractor shall differentiate by highlighting the specific product to be utilized.

n. Calculations: Provide a section for circuit and panel calculations.

o. Loading Sheets: Provide a section for DGP Loading Sheets.

p. Certifications: Provide section for Contractor's manufacturer certifications.

28 05 00 - 11

7. Contractor Review: Review submittals prior to transmittal.

Determine and verify field measurements and field construction criteria. Verify manufacturer's catalog numbers and conformance of submittal with requirements of contract documents. Return non-conforming or incomplete submittals with requirements of the work and contract documents. Apply

Contractor's stamp with signature certifying the review and verification of products occurred, and the field dimensions, adjacent construction, and coordination of information is in accordance with the requirements of the contract documents.

8. Resubmission: Revise and resubmit submittals as required within 15 calendar days of return of submittal. Make resubmissions under procedures specified for initial submittals. Identify all changes made since previous submittal.

9. Product Data: Within 15 calendar days after execution of the contract, the Contractor shall submit for approval a complete list of all of major products proposed for use. The data shall include name of manufacturer, trade name, model number, the associated contract document section number, paragraph number, and the referenced standards for each listed product.

F. Group 1 Technical Data Package: Group I Technical Data Package shall be one submittal consisting of the following content and organization. Refer to VA Special Conditions Document for drawing format and content requirements. The data package shall include the following:

1. Section I - Drawings:

a. General - Drawings shall conform to VA CAD Standards Guide.

All text associated with security details shall be 1/8” tall and meet VA text standard for AutoCAD¢ drawings.

b. Cover Sheet - Cover sheet shall consist of Project Title and Address, Project Number, Area and Vicinity Maps.

c. General Information Sheets - General Information Sheets shall consist of General Notes, Abbreviations, Symbols, Wire and Cable Schedule, Project Phasing, and Sheet Index.

d. Floor Plans - Floor plans shall be produced from the Architectural backgrounds issued in the Construction

Documents. The contractor shall receive floor plans from the prime A/E to develop these drawing sets. ESS system devices shall be placed on drawings in scale. All text associated with security details shall be 1/8” tall and meet VA text standard for AutoCAD¢ drawings. Floor plans shall identify the following:

1) Devices by symbol,

2) The associated device point number (derived from the loading sheets),

3) Wire & cable types and counts

4) Conduit sizing and routing

5) Conduit riser systems

28 05 00 - 12

6) Device and area detail call outs

Riser Diagrams - Contractor shall provide a riser diagram indicating riser architecture and distribution of the ESS system throughout the facility (or area in scope).

e. Block Diagrams - Contractor shall provide a block diagram for the entire system architecture and interconnections with ESS subsystems.

f. Interconnection Diagrams - Contractor shall provide interconnection diagram for each sensor, and device component. Interconnection diagram shall identify termination locations, standard wire detail to include termination schedule. Diagram shall also identify interfaces to other systems such as elevator control, fire alarm systems, and security management systems.

g. Electrical Panel Schedule - Electrical Panel Details shall be provided for all ESS systems electrical power circuits.

Panel details shall be provided identifying panel type

(Standard, Emergency Power, Emergency/Uninterrupted Power

Source, and Uninterrupted Power Source Only), panel location, circuit number, and circuit amperage rating.

2. Section II - Construction Mock-up: In areas with exposed EMT/Conduit Raceways, contractor shall conceal raceway as much as practical and unobtrusively. In addition, historic significance must be considered to determine installation means and methods for approval by the owner.

3. Section III - Manufacturers' Data: The data package shall include manufacturers' data for all materials and equipment, including sensors, local processors and console equipment provided under this specification.

4. Section IV - System Description and Analysis: The data package shall include system descriptions, analysis, and calculations used in sizing equipment required by these specifications. Descriptions and calculations shall show how the equipment will operate as a system to meet the performance requirements of this specification. The data package shall include the following:

a. Central processor memory size; communication speed and protocol description; rigid disk system size and configuration; flexible disk system size and configuration;

back-up media size and configuration; alarm response time calculations; command response time calculations; start-up operations; expansion capability and method of implementation; sample copy of each report specified; and color photographs representative of typical graphics.

b. Software Data: The data package shall consist of descriptions of the operation and capability of the system, and application software as specified.

c. Overall System Reliability Calculations: The data package shall include all manufacturers' reliability data and calculations required to show compliance with the specified reliability.

28 05 00 - 13

5. Section V - Certifications & References: All specified manufacturer's certifications shall be included with the data package. Contractor shall provide Project references as outlined in Paragraph 1.4 Quality Assurance.

G. Group II Technical Data Package

1. The Contractor shall prepare a report of Current Site Conditions and submit a report to the COR documenting changes to the site, particularly those conditions that affect performance of the system to be installed. The Contractor shall provide specification sheets, or written functional requirements to support the findings, and a cost estimate to correct those site changes or conditions which affect the installation of the system or its performance. The Contractor shall not correct any deficiency without written permission from the COR.

2. System Configuration and Functionality: The contractor shall provide the results of the meeting with VA to develop system requirements and functionality including but not limited to:

a. Baseline configuration

b. System monitoring and reporting (unit level and central control)

c. Naming conventions and descriptors

H. Group III Technical Data Package

1. Development of Test Procedures: The Contractor will prepare performance test procedures for the system testing. The test procedures shall follow the format of the VA Testing procedures and be customized to the contract requirements.

The Contractor will deliver the test procedures to the COR for approval at least 60 calendar days prior to the requested test date.

I. Group IV Technical Data Package

1. Performance Verification Test

a. Based on the successful completion of the pre-delivery test, the Contractor shall finalize the test procedures and report forms for the performance verification test (PVT) and the endurance test. The PVT shall follow the format, layout and content of the pre-delivery test. The

Contractor shall deliver the PVT and endurance test procedures to the COR for approval. The Contractor may schedule the PVT after receiving written approval of the test procedures. The Contractor shall deliver the final

PVT and endurance test reports within 14 calendar days from completion of the tests. Refer to Part 3 of this section for System Testing and Acceptance requirements.

2. Training Documentation

28 05 00 - 14

a. New Facilities and Major Renovations: Familiarization training shall be provided for new equipment or systems.

Training can include site familiarization training for VA technicians and administrative personnel. Training shall include general information on new system layout including closet locations, turnover of the completed system including all documentation, including manuals, software, key systems, and full system administration rights. Lesson plans and training manuals training shall be oriented to type of training to be provided.

System Configuration and Data Entry:

b. The contractor is responsible for providing all system configuration and data entry for the Fire Alarm System.

All data entry shall be performed per VA standards & guidelines. The Contractor is responsible for participating in all meetings with the client to compile the information needed for data entry. These meetings shall be established at the beginning of the project and incorporated in to the project schedule as a milestone task. The contractor shall be responsible for all data collection, data entry, and system configuration. The contractor shall collect, enter, & program and/or configure the following components:

1) Fire Alarm System components

Graphics: Based on CAD as-built drawings developed for the construction project, create all map sets showing locations of all alarms and field devices. Graphical maps of all alarm points installed under this contract including perimeter and exterior alarm points shall be delivered with the system. The

Contractor shall create and install all graphics needed to make the system operational. The Contractor shall utilize data from the contract documents, Contractor's field surveys, and all other pertinent information in the Contractor's possession to complete the graphics. The Contractor shall identify and request from the COR, any additional data needed to provide a complete graphics package. Graphics shall have sufficient level of detail for the system operator to assess the alarm. The Contractor shall supply hard copy, color examples at least 203.2 x 254 mm (8 x 10 in) of each type of graphic to be used for the completed Fire Alarm system. The graphics examples shall be delivered to the COR for review and approval at least 90 calendar days prior to the scheduled date the Contractor requires them.

28 05 00 - 15

J. Group V Technical Data Package: Final copies of the manuals shall be delivered to the COR as part of the acceptance test.

The draft copy used during site testing shall be updated with any changes required prior to final delivery of the manuals. Each manual's contents shall be identified on the cover. The manual shall include names, addresses, and telephone numbers of each sub-contractor installing equipment or systems, as well as the nearest service representatives for each item of equipment for each system. The manuals shall include a table of contents and tab sheets. Tab sheets shall be placed at the beginning of each chapter or section and at the beginning of each appendix. The final copies delivered after completion of the endurance test shall include all modifications made during installation, checkout, and acceptance. One (1) soft copy on CD of each item listed below shall be delivered as a part of final systems acceptance.

1. Functional Design Manual: The functional design manual shall identify the operational requirements for the entire system and explain the theory of operation, design philosophy, and specific functions. A description of hardware and software functions, interfaces, and requirements shall be included for all system operating modes. Manufacturer developed literature may be used; however, shall be produced to match the project requirements.

2. Equipment Manual: A manual describing all equipment furnished including:

a. General description and specifications; installation and checkout procedures; equipment electrical schematics and layout drawings; system schematics and layout drawings;

alignment and calibration procedures; manufacturer's repair list indicating sources of supply; and interface definition.

3. Software Manual: The software manual shall describe the functions of all software and include all other information necessary to enable proper loading, testing, and operation.

The manual shall include:

a. Definition of terms and functions; use of system and applications software; procedures for system initialization, start-up, and shutdown; alarm reports;

reports generation, database format and data entry requirements; directory of all disk files; and description of all communications protocols including data formats, command characters, and a sample of each type of data transfer.

4. Operator's Manual: The operator's manual shall fully explain all procedures and instructions for the operation of the system, including:

a. Computers and peripherals; system start-up and shutdown procedures; use of system, command, and applications software; recovery and restart procedures; graphic alarm presentation; use of report generator and generation of reports; data entry; operator commands' alarm messages, and printing formats; and system access requirements.

28 05 00 - 16

5. Maintenance Manual: The maintenance manual shall include descriptions of maintenance for all equipment including inspection, recommend schedules, periodic preventive maintenance, fault diagnosis, and repair or replacement of defective components.

6. Spare Parts & Components Data: At the conclusion of the Contractor's work, the Contractor shall submit to the CORCOR a complete list of the manufacturer's recommended spare parts and components required to satisfactorily maintain and service the systems, as well as unit pricing for those parts and components.

7. Operation, Maintenance & Service Manuals: The Contractor shall provide two (2) complete sets of operating and maintenance manuals in the form of an instructional manual for use by the VA Security Guard Force personnel. The manuals shall be organized into suitable sets of manageable size.

Where possible, assemble instructions for similar equipment into a single binder. If multiple volumes are required, each volume shall be fully indexed and coordinated.

8. Equipment and Systems Maintenance Manual: The Contractor shall provide the following descriptive information for each piece of equipment, operating system, and electronic system:

a. Equipment and/or system function.

b. Operating characteristics.

c. Limiting conditions.

d. Performance curves.

e. Engineering data and test.

f. Complete nomenclature and number of replacement parts.

g. Provide operating and maintenance instructions including assembly drawings and diagrams required for maintenance and a list of items recommended to stock as spare parts.

h. Provide information detailing essential maintenance procedures including the following: routine operations, trouble shooting guide, disassembly, repair and re-assembly, alignment, adjusting, and checking.

i. Provide information on equipment and system operating procedures, including the following; start-up procedures, routine and normal operating instructions, regulation and control procedures, instructions on stopping, shut-down and emergency instructions, required sequences for electric and electronic systems, and special operating instructions.

j. Manufacturer equipment and systems maintenance manuals are permissible.

28 05 00 - 17

9. Project Redlines: During construction, the Contractor shall maintain an up-to-date set of construction redlines detailing current location and configuration of the project components.

The redline documents shall be marked with the words 'Master

Redlines' on the cover sheet and be maintained by the

Contractor in the project office. The Contractor will provide access to redline documents anytime during the project for review and inspection by the COR or authorized Office of

Protection Services representative. Master redlines shall be neatly maintained throughout the project and secured under lock and key in the contractor's onsite project office. Any project component or assembly that is not installed in strict accordance with the drawings shall be so noted on the drawings. Prior to producing Record Construction Documents, the contractor will submit the Master Redline document to the

COR for review and approval of all changes or modifications to the documents. Each sheet shall have COR initials indicating authorization to produce As Built documents. Field drawings shall be used for data gathering & field changes. These changes shall be made to the master redline documents daily.

Field drawings shall not be considered master redlines.

10. Record Specifications: The Contractor shall maintain one (1) copy of the Project Specifications, including addenda and modifications issued, for Project Record Documents. The

Contractor shall mark the Specifications to indicate the actual installation where the installation varies substantially from that indicated in the Contract

Specifications and modifications issued. (Note related

Project Record Drawing information where applicable). The

Contractor shall pay particular attention to substitutions, selection of product options, and information on concealed installations that would be difficult to identify or measure and record later. Upon completion of the mark ups, the

Contractor shall submit record Specifications to the COR. As with master relines, Contractor shall maintain record specifications for COR review and inspection at anytime.

11. Record Product Data: The Contractor shall maintain one (1) copy of each Product Data submittal for Project Record

Document purposes. The Data shall be marked to indicate the actual product installed where the installation varies substantially from that indicated in the Product Data submitted. Significant changes in the product delivered to the site and changes in manufacturer's instructions and recommendations for installation shall be included.

Particular attention will be given to information on concealed products and installations that cannot be readily identified or recorded later. Note related Change Orders and mark up of

Record Construction Documents, where applicable. Upon completion of mark up, submit a complete set of Record Product

Data to the COR.

28 05 00 - 18

12. Miscellaneous Records: The Contractor shall maintain one (1) copy of miscellaneous records for Project Record Document purposes. Refer to other Specifications for miscellaneous record-keeping requirements and submittals concerning various construction activities. Before substantial completion, complete miscellaneous records and place in good order, properly identified and bound or filed, ready for use and reference. Categories of requirements resulting in miscellaneous records include a minimum of the following:

a. Certificates received instead of labels on bulk products.

b. Testing and qualification of tradesmen. (Contractor's Qualifications)

c. Documented qualification of installation firms.

d. Load and performance testing.

e. Inspections and certifications.

f. Final inspection and correction procedures.

g. Project schedule

13. Record Construction Documents (Record As-Built)

a. Upon project completion, the contractor shall submit the project master redlines to the COR prior to development of

Record construction documents. The COR shall be given a minimum of a thirty (30) day review period to determine the adequacy of the master redlines. If the master redlines are found suitable by , the COR will initial and date each sheet and turn redlines over to the contractor for as built development.

b. The Contractor shall provide the COR a complete set of "as-built" drawings and original master redlined marked "as-built" blue-line in the latest version of AutoCAD drawings unlocked on CD or DVD. The as-built drawing shall include security device number, security closet connection location, data gathering panel number, and input or output number as applicable. All corrective notations made by the

Contractor shall be legible when submitted to the COR. If, in the opinion of the COR, any redlined notation is not legible, it shall be returned to the Contractor for re-submission at no extra cost to the Owner. The Contractor shall organize the Record Drawing sheets into manageable sets bound with durable paper cover sheets with suitable titles, dates, and other identifications printed on the cover. The submitted as built shall be in editable formats and the ownership of the drawings shall be fully relinquished to the owner.

28 05 00 - 19

c. Where feasible, the individual or entity that obtained record data, whether the individual or entity is the installer, sub-contractor, or similar entity, is required to prepare the mark up on Record Drawings. Accurately record the information in a comprehensive drawing technique. Record the data when possible after it has been obtained. For concealed installations, record and check the mark up before concealment. At the time of substantial completion, submit the Record Construction Documents to the

COR. The Contractor shall organize into bound and labeled sets for the COR's continued usage. Provide device, conduit, and cable lengths on the conduit drawings. Exact in-field conduit placement/routings shall be shown. All conduits shall be illustrated in their entire length from termination in security closets; no arrowed conduit runs shall be shown. Pull box and junction box sizes are to be shown if larger than 100mm (4 inch).

K. Approvals will be based on complete submission of manuals together with shop drawings.

L. After approval and prior to installation, furnish the COR with one sample of each of the following:

1. A 300 mm (12 inch) length of each type and size of wire and cable along with the tag from the coils of reels from which the samples were taken.

2. Each type of conduit and pathway coupling, bushing and termination fitting.

3. Conduit hangers, clamps and supports.

4. Duct sealing compound.

M. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 280800 COMMISSIONING

OF ELECTRONIC SAFETY AND SECURITY SYSTEMS.

1.7 APPLICABLE PUBLICATIONS

A. The publications listed below (including amendments, addenda, revisions, supplement, and errata) form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.

B. American National Standards Institute (ANSI)/ International Code Council (ICC):

1. A117.1 Standard on Accessible and Usable Buildings and

Facilities

C. American National Standards Institute (ANSI):

1. ANSI S3.2-99 Method for measuring the Intelligibility of

Speech over Communications Systems

D. American Society for Testing and Materials (ASTM)

1. B1-07 Standard Specification for Hard-Drawn Copper Wire

28 05 00 - 20

2. B3-07 Standard Specification for Soft or Annealed Copper

Wire

3. B8-04 Standard Specification for Concentric-Lay-Stranded

Copper Conductors, Hard, Medium-Hard, or Soft

4. C1238-97 (R03) Standard Guide for Installation of Walk-Through Metal Detectors

5. D2301-04 Standard Specification for Vinyl Chloride Plastic Pressure Sensitive Electrical Insulating Tape

E. Architectural Barriers Act (ABA), 1968

F. Department of Justice: American Disability Act (ADA)

1. 28 CFR Part 36-2010 ADA Standards for Accessible Design

G. Department of Veterans Affairs:

1. VHA National CAD Standard Application Guide, 2006

H. VA BIM Guide, V1.0 10

I. Federal Communications Commission (FCC):

J. (47 CFR 15) Part 15 Limitations on the Use of Wireless

Equipment/Systems

K. Federal Specifications (Fed. Spec.):

1. A-A-59544-08 Cable and Wire, Electrical (Power, Fixed

Installation)

L. Government Accountability Office (GAO):

1. GAO-03-8-02 Security Responsibilities for Federally Owned and Leased Facilities

M. Institute of Electrical and Electronics Engineers (IEEE):

1. 81-1983 IEEE Guide for Measuring Earth Resistivity, Ground

Impedance, and Earth Surface Potentials of a Ground System

2. 802.3af-08 Power over Ethernet Standard

3. 802.3at-09 Power over Ethernet (PoE) Plus Standard

4. C2-07 National Electrical Safety Code

5. C62.41-02 IEEE Recommended Practice on Surge Voltages in

Low-Voltage AC Power Circuits

6. C95.1-05 Standards for Safety Levels with Respect to Human Exposure in Radio Frequency Electromagnetic Fields

N. National Electrical Manufactures Association (NEMA):

1. 250-08 Enclosures for Electrical Equipment (1000 Volts

Maximum)

2. FB1-07 Fittings, Cast Metal Boxes and Conduit Bodies for

Conduit, Electrical Metallic Tubing and Cable

O. National Fire Protection Association (NFPA):

1. 70-11 National Electrical Code (NEC)

2. 731-08 Standards for the Installation of Electric Premises

Security Systems

28 05 00 - 21

3. 99-2005 Health Care Facilities

P. Section 508 of the Rehabilitation Act of 1973

Q. Underwriters Laboratories, Inc. (UL):

1. 1-05 Flexible Metal Conduit

2. 5-04 Surface Metal Raceway and Fittings

3. 6-07 Rigid Metal Conduit

4. 44-05 Thermoset-Insulated Wires and Cables

5. 50-07 Enclosures for Electrical Equipment

6. 83-08 Thermoplastic-Insulated Wires and Cables

7. 360-09 Liquid-Tight Flexible Steel Conduit

8. 444-08 Safety Communications Cables

9. 464-09 Audible Signal Appliances

10. 467-07 Electrical Grounding and Bonding Equipment

11. 486A-03 Wire Connectors and Soldering Lugs for Use with

Copper Conductors

12. 486C-04 Splicing Wire Connectors

13. 486D-05 Insulated Wire Connector Systems for

Underground Use or in Damp or Wet Locations

14. 486E-00 Equipment Wiring Terminals for Use with

Aluminum and/or Copper Conductors

15. 493-07 Thermoplastic-Insulated Underground Feeder and

Branch Circuit Cable

16. 514A-04 Metallic Outlet Boxes

17. 514B-04 Fittings for Cable and Conduit

18. 51-05 Schedule 40 and 80 Rigid PVC Conduit

19. 797-07 Electrical Metallic Tubing

20. 1242-06 Intermediate Metal Conduit

21. 1479-03 Fire Tests of Through-Penetration Fire Stops

22. 60950 Safety of Information Technology Equipment

23. 60950-1 Information Technology Equipment - Safety -

Part 1: General Requirements

R. Uniform Federal Accessibility Standards (UFAS) 1984

S. United States Department of Commerce:

1. Special Pub 500-101 Care and Handling of Computer Magnetic Storage Media

1.8 COORDINATION

A. Coordinate arrangement, mounting, and support of electronic safety and security equipment:

28 05 00 - 22

1. To allow maximum possible headroom unless specific mounting heights that reduce headroom are indicated.

2. To provide for ease of disconnecting the equipment with minimum interference to other installations.

3. To allow right of way for piping and conduit installed at required slope.

4. So connecting raceways, cables, wireways, cable trays, and busways will be clear of obstructions and of the working and access space of other equipment.

B. Coordinate installation of required supporting devices and set sleeves in cast-in-place concrete, masonry walls, and other structural components as they are constructed.

C. Coordinate location of access panels and doors for electronic safety and security items that are behind finished surfaces or otherwise concealed.

1.9 MAINTENANCE & SERVICE

A. General Requirements

1. The Contractor shall provide all services required and equipment necessary to maintain the entire newly installed electronic safety and security system or sub-system (including points of integration to existing systems) in an operational state as specified for a period of one (1) year after formal written acceptance of the system.