36C25019B0046-002.pdf
PDF 4 MB Posted
- Attached to
- Upgrade Smart Building System 541-19-201 Louis Stoke VA Medical Center Cleveland, Ohio 44106
- Solicitation number
- 36C25019B0046
About this file
36C25019B0046 541-19-201 - Project Specifications Combined Final.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25019C0255-000.docx | DOCX document | |
| 36C25019B0046-0001002.pdf | ||
| 36C25019B0046-0001001.pdf | ||
| 36C25019B0046-0001000.docx | DOCX document | |
| 36C25019B0046-0001000.docx | DOCX document | |
| 36C25019B0046-0001001.pdf | ||
| 36C25019B0046-0001002.pdf | ||
| 36C25019B0046-004.pdf | ||
| 36C25019B0046-003.pdf | ||
| 36C25019B0046-005.pdf | ||
| 36C25019B0046-007.pdf | ||
| 36C25019B0046-001.docx | DOCX document | |
| 36C25019B0046-002.pdf | ||
| 36C25019B0046-006.pdf | ||
| 36C25019B0046-006.pdf | ||
| 36C25019B0046-005.pdf | ||
| 36C25019B0046-003.pdf | ||
| 36C25019B0046-007.pdf | ||
| 36C25019B0046-001.docx | DOCX document | |
| 36C25019B0046-004.pdf | ||
| 36C25019B0046-000.docx | DOCX document | |
| 36C25019B0046-000.docx | DOCX document |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL SPECIFICATIONS
Department of Veterans Affairs Louis Stokes Cleveland VA Medical Center
WADE PARK
10701 East Boulevard Cleveland, OH 44106
UPGRADE SMART BUILDING SYSTEM
Project No. 541-19-201
PREPARED BY:
Fredrick, Fredrick & Heller Engineers 672 East Royalton Road Broadview Heights, Ohio 4414 P (440) 546-9696 Project Director: Michael Long, PE
Interactive Energy, LLC 1133 Kingwood Dr.
Marion, Ohio 43302 P (614) 546-9796 Project Director: James Burtch
FINAL:
ISSUE DATE: July 19, 2019
FINAL VAMC WADE PARK CLEVELAND
07/19/2019 Upgrade Smart Building System
VA Project No. 541-19-201
Table of Contents 00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS VERSION
DATE
00 01 10 Table of Contents - 00 01 15 Drawing Index -
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 2018-12
01 00 05 Supplement to General Requirements for Integrated Automation -
01 32 16.15 Project Schedules 2015-02 01 33 23 Shop Drawings, Product Data, and Samples 2017-05 01 35 26 Safety Requirements 2017-02 01 42 19 Reference Standards 2016-05 01 45 00 Quality Controls 2018-01 01 74 19 Construction Waste Management 2013-09 01 81 13 Sustainable Construction Requirements 2017-10 01 91 00 General Commissioning Requirements 2015-10
DIVISION 02 – EXISTING CONDITIONS
DIVISION 03 – CONCRETE
DIVISION 04 – MASONRY
DIVISION 05 – METALS
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 81 00 Applied Fireproofing 2017-10 07 84 00 Firestopping 2016-02 07 92 00 Joint Sealants 2017-10
DIVISION 08 - OPENINGS
DIVISION 09 – FINISHES
09 91 00 Painting -
DIVISION 10 – SPECIALTIES
DIVISION 11 – EQUIPMENT
FINAL VAMC WADE PARK CLEVELAND
07/19/2019 Upgrade Smart Building System
VA Project No. 541-19-201
Table of Contents 00 01 10-2
DIVISION 12 – FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
DIVISION 14– CONVEYING EQUIPEMENT
DIVISION 21- FIRE SUPPRESSION
DIVISION 22 – PLUMBING
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
DIVISION 25 – INTEGRATED AUTOMATION
25 05 11 Requirements for Integrated Automation - 25 10 00 Integrated Automation Network 25 15 00 Integrated Automation Enterprise Platform
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 2016-11 26 05 19 Low-Voltage Electrical Power Conductors and Cables 2017-01 26 05 26 Grounding and Bonding for Electrical Systems 2017-01 26 05 33 Raceway and Boxes for Electrical Systems 2018-01 26 08 00 Commissioning of Electrical Systems 2016-11 26 27 26 Wiring Devices 2018-01
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 2015-06 27 05 26 Grounding and Bonding for Communication Systems 2016-06 27 05 33 Raceway and Boxes for Communication Systems 2018-10 27 08 00 Commissioning of Communication Systems 2016-11 27 10 00 Control, Communication and Signal Wiring 2015-06 27 15 00 Communications Structured Cabling 2016-11
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
DIVISION 31 – EARTHWORK
DIVISION 32 – EXTERIOR IMPROVEMENTS
DIVISION 33 – UTILITIES
DIVISION 34 – TRANSPORTATION
DIVISION 48 – Electrical Power Generation
FINAL
07/19/2019
VAMC WADE PARK CLEVELAND
Upgrade Smart Building System
Project No. 541-19-201
DRAWING INDEX
00 01 15 - 1
SECTION 00 01 15
DRAWING INDEX
The drawings listed below accompanying this specification form a part of the contract.
DRAWING NO. TITLE
GENERAL
X0.1 COVER SHEET
X1.1 SUB-BASEMENT KEY PLAN
X1.2 BASEMENT KEY PLAN
X1.3 FIRST FLOOR KEY PLAN
X1.4 SECOND FLOOR KEY PLAN
X1.5 THIRD FLOOR KEY PLAN
X1.6 FOURTH FLOOR KEY PLAN
X1.7 FIFTH FLOOR KEY PLAN
X1.8 SIXTH FLOOR KEY PLAN
X1.9 LEARNING EXCHANGE KEY PLAN
MECHANICAL
M1.1 BOILER FLUE ECONOMIZER ENERGY METER PLAN
TECHNOLOGY
T0.1 TECHNOLOGY LEGEND
T1.1 SUB-BASEMENT AREA PLANS – FOTP-19
T1.2 BASEMENT AREA PLANS – FOTP-4, AND FOTP-10
T1.3 BASEMENT AREA PLANS – FOTP-6, AND FOTP-8
T1.4 BASEMENT AREA PLANS – FOTP-9
T1.5 BASEMENT AREA PLANS – FOTP-11, FOTP-15, AND FOTP-19
T1.6 FIRST FLOOR AREA PLANS – FOTP-4, FOTP-6, FOTP-10, AND FOTP-
T1.7 FIRST FLOOR AREA PLANS – FOTP-7, FOTP-14, AND FOTP-15
T1.8 SECOND FLOOR AREA PLANS – FOTP-6, FOTP-15, AND FOTP-19
T1.9 SECOND FLOOR AREA PLANS – FOTP-15, AND FOTP-16
T1.10 THIRD FLOOR AREA PLANS – FOTP-1, FOTP-17, AND FOTP-19
T1.11 FOURTH FLOOR AREA PLANS – FOTP-3, AND FOTP-19
T1.12 FIFTH FLOOR AREA PLANS – FOTP-3, FOTP-19, AND FOTP-20
T1.13 SIXTH FLOOR AREA PLANS – FOTP-12
T1.14 SEVENTH FLOOR AREA PLANS – FOTP-3
T1.15 SEVENTH FLOOR AREA PLANS – FOTP-12
T1.16 LEARNING EXCHANGE FLOOR PLANS – FOTP-18
T2.1 NEW NETWORK BACKBONE AND SBS ARCHITECTURE
T2.2 ANDOVER NETWORK DEMOLITION SCHEMATIC
T2.3 ANDOVER NETWORK FOTP CONNECTION SCHEMATIC
T2.4 CARES TOWER ANDOVER NETWORK DEMOLITION SCHEMATIC
T2.5 CARES TOWER ANDOVER NETWORK FOTP CONNECTION SCHEMATIC
Final 07/19/2019
VAMC WADE PARK CLEVELAND
REPLACEMENT OF AHU-17 & AHU-18
Project No. 541-18-104
DRAWING NO. TITLE
DRAWING INDEX
00 01 15 - 2
T3.1 FOTP SWITCH PORT LISTS (1 OF 2)
T3.2 FOTP SWITCH PORT LISTS (2 OF 2)
T3.3 TECHNOLOGY DETAILS
T3.4 DEVICE CONNECTION SCHEMATICS
T3.5 DEVICE CONNECTION SCHEMATICS
T3.6 ELECTRICAL METERS CONNECTION DETAILS
- - - E N D - - -
FINAL SPEC REVISION 12-01-18
07/19/2019 VAMC WADE PARK CLEVELAND
Upgrade Smart Building System Project No. 541-19-201 i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 RESTORATION
1.10 LAYOUT OF WORK
1.11 AS-BUILT DRAWINGS
1.12 USE OF ROADWAYS
1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.14 TEMPORARY USE OF EXISTING ELEVATORS
1.15 TEMPORARY TOILETS
1.16 AVAILABILITY AND USE OF UTILITY SERVICES
1.17 INSTRUCTIONS
1.18 GOVERNMENT-FURNISHED PROPERTY
1.19 RELOCATED EQUIPMENT ITEMS
1.20 CONSTRUCTION SIGN
1.21 SAFETY SIGN
Upgrade Smart Building System Project No. 541-19-201 ii
ATTACHMENTS
> Attachment 1 - OSHA Requirements and Safety and Health Regulations
> Attachment 2 - Pre-Construction Risk Assessment
> Attachment 3 - Construction Safety Poster - Cleveland VA
> Attachment 4 - Interim Life Safety Risk Assessment Form
> Attachment 5 - Contractor Safety and Security Orientation
> Attachment 6 - Job Safety Check Sheet
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
B. Refer to attachments at the end of this section
> Attachment 1 - OSHA Requirements and Safety and Health Regulations > Attachment 2 - Pre-Construction Risk Assessment > Attachment 3 - Construction Safety Poster - Cleveland VA > Attachment 4 - Interim Life Safety Risk Assessment Form > Attachment 5 - Contractor Safety and Security Orientation > Attachment 6 - Job Safety Check Sheet
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the upgrade of the smart building system, which includes new fiber optic cabling, new network switches, new copper Cat 6 cabling and outlets, upgraded and new
Tridium Niagara N4 supervisors, upgraded and new Tridium Vykon JACE’s, new Tridium Energy Analytics software, integration of existing steam trap monitoring system, integration of existing electrical meters, integration of new boiler plant flue economizer energy meters. Each phase includes demolition and removal of existing building systems, and the installation of new electrical, technology and integrated automation systems. Complete work as required by drawings and specifications.
Refer to 01 00 05 “Supplement to General Requirements for Integrated
Automaton” for further details on general intent.
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Engineering Officer.
C. Offices of Fredrick, Fredrick and Heller Engineers Inc.,(FF&H
Engineers) will render certain technical services during construction.
Such services shall be considered as advisory to the Government and
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -2 shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. General Contractor shall refer to solicitation for bid item descriptions.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -3
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security escort can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR)for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
E. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -4
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for General
Contractor and its employees for parking in designated areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -5 the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -6 by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to
COR and Contractor.
J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -7
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
K. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR [Chief Engineer][Chief of
Facilities Management]. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the
Medical Center Director’s prior knowledge and written approval.
Refer to specification Sections 26 05 11, REQUIREMENTS FOR
ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR COMMUNICATIONS
INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC
SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days n advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -8
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR .
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -9
N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.
Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR
52.243-4 and VAAR 852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -10 of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -11
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
4. PCB Transformers and Capacitors : The Contractor shall be responsible for disposal of the Polychlorinated Biphenyl (PCB) transformers and capacitors . The transformers and capacitors shall be taken out of service and handled in accordance with the procedures of the Environmental Protection Agency (EPA) and the
Department of Transportation (DOT) as outlined in Code of Federal
Regulation (CFR), Titled 40 and 49 respectively. The EPA's Toxic
Substance Control Act (TSCA) Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7 also apply. Upon removal of PCB transformers and capacitors for disposal, the "originator" copy of the Uniform
Hazardous Waste Manifest (EPA Form 8700-22), along with the Uniform
Hazardous Waste Manifest Continuation Sheet (EPA Form 8700-22A) shall be returned to the Contracting Officer who will annotate the contract file and transmit the Manifest to the Medical Center's COR.
a. Copies of the following listed CFR titles may be obtained from the Government Printing Office:
40 CFR 261 .......Identification and Listing of Hazardous Waste
40 CFR 262 .......Standards Applicable to Generators of Hazardous
Waste
40 CFR 263 .......Standards Applicable to Transporters of
Hazardous Waste
40 CFR 761 .......PCB Manufacturing, Processing, Distribution in
Commerce, and use Prohibitions
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -12
49 CFR 172 .......Hazardous Material tables and Hazardous
Material Communications Regulations
49 CFR 173 .......Shippers - General Requirements for Shipments and Packaging
49 CRR 173 .......Subpart A General
49 CFR 173 .......Subpart B Preparation of Hazardous Material for
Transportation
49 CFR 173 .......Subpart J Other Regulated Material; Definitions and Preparation
TSCA .............Compliance Program Policy Nos. 6-PCB-6 and 6-
PCB-7
1.9 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -13
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.10 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.
If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
B. Establish and plainly mark lines for each partition and such other lines that are reasonably necessary to properly assure that location, orientation, and elevations established are in accordance with lines and elevations shown on contract drawings.
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the Architect's or COR's review, as often as requested.
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -14
C. Contractor shall submit two approved completed sets of as-built drawings within 14 calendar days after the acceptance of the project by the COR, in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT
DATA, AND SAMPLES.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -15 immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
1.14 TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing elevators for handling building materials and
Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the COR for use of elevators.
The COR will ascertain that elevators are in proper condition.
Contractor may use elevators for daily use for personnel only between the hours of 7:00 am and 6:00 pm and for special
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -16 nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of
Veterans Affairs.
2. Contractor covers and provides maximum protection of following elevator components:
a. Entrance jambs, heads soffits and threshold plates.
b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c. Finish flooring.
3. If brake lining of elevators are excessively worn or damaged during temporary use, they shall be removed and replaced by new brake lining at the contractors expense.
4. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts at the contractors expense, if recommended by elevator inspector after elevator is released by Contractor.
5. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.
1.15 TEMPORARY TOILETS
A. Contractor may have for use of Contractor's workmen, such toilet accommodations as may be assigned to Contractor by the COR. Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.
1.16 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -17 the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the
Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair or restore the infrastructure as required.
C. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, as determined by the COR, will not be permitted.
Maintain minimum temperatures as specified for various materials.
D. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
E. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection. Water is available at no cost to the Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR's discretion) of use of water from Medical Center's system.
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -18
F. Steam: Furnish steam system for testing required in various sections of specifications.
1. Obtain steam for testing by connecting to the Medical Center steam distribution system. Steam is available at no cost to the
Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve steam-use so none is wasted. Failure to stop leakage or other waste will be cause for revocation (at COR's discretion), of use of steam from the Medical Center's system.
1.17 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -19
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned
Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.
This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.18 GOVERNMENT-FURNISHED PROPERTY
A. The Government shall deliver to the Contractor, the
Government-furnished property shown on the drawings.
B. Equipment furnished by Government to be installed by Contractor will be furnished to Contractor at the Medical Center.
C. Contractor shall be prepared to receive this equipment from Government and store or place such equipment not less than 90 days before
Completion Date of project.
D. Notify Contracting Officer in writing, 60 days in advance, of date on which Contractor will be prepared to receive equipment furnished by
Government. Arrangements will then be made by the Government for delivery of equipment.
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -20
1. Immediately upon delivery of equipment, Contractor shall arrange for a joint inspection thereof with a representative of the Government.
At such time the Contractor shall acknowledge receipt of equipment described, make notations, and immediately furnish the Government representative with a written statement as to its condition or shortages.
2. Contractor thereafter is responsible for such equipment until such time as acceptance of contract work is made by the Government.
E. Equipment furnished by the Government will be delivered in a partially assembled (knock down) condition in accordance with existing standard commercial practices, complete with all fittings, fastenings, and appliances necessary for connections to respective services installed under contract. All fittings and appliances (i.e., couplings, ells, tees, nipples, piping, conduits, cables, and the like) necessary to make the connection between the Government furnished equipment item and the utility stub-up shall be furnished and installed by the contractor at no additional cost to the Government.
F. Completely assemble and install the Government furnished equipment in place ready for proper operation in accordance with specifications and drawings.
G. Furnish supervision of installation of equipment at construction site by qualified factory trained technicians regularly employed by the equipment manufacturer.
1.19 RELOCATED EQUIPMENT ITEMS
A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all existing items indicated to be relocated by Contractor.
B. Perform relocation of such equipment or items at such times and in such a manner as directed by the COR.
C. Suitably cap existing service lines, such as steam, condensate return, water, drain, gas, air, vacuum and/or electrical, at the main whenever such lines are disconnected from equipment to be relocated. Remove
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -21 abandoned lines in finished areas and cap as specified herein before under paragraph "Abandoned Lines".
D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated equipment; and leave such equipment in proper operating condition.
E. All service lines such as noted above for relocated equipment shall be in place at point of relocation ready for use before any existing equipment is disconnected. Make relocated existing equipment ready for operation or use immediately after reinstallation.
1.20 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Provide three 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 1200 mm (four feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts. Make posts full height of sign. Brace posts with 50 x 100 mm (two by four inch) material as directed.
B. Paint all surfaces of sign and posts two coats of white gloss paint.
Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the COR.
1.21 SAFETY SIGN
A. Provide a Safety Sign where directed by COR. Face of sign shall be 19 mm (3/4 inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm
(three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with gloss paint of colors noted.
Upgrade Smart Building System Project No. 541-19-201
01 00 00 -22
C. Maintain sign and remove it when directed by COR.
D. Standard Detail Drawing Number SD10000-02(Found on VA TIL) of safety sign showing required legend and other characteristics of sign.
- - - E N D - - -
FINAL SPEC REVISION
Upgrade Smart Building System Project No. 541-19-201
LOUIS STOKES CLEVELAND VAMC
OSHA Requirements and Safety and Health Regulations - Attachment 1
OSHA Requirements and Safety and Health Regulations
PART 1 - OSHA Requirements
1.1 General
A. Contractors are required to comply with the Occupational Safety and Health Act of 1970. This will include the safety and health standard found in Code of Federal Regulations (CFR) 1910 and 1926. Copies of those standards can be obtained from the Superintendent of Documents, U.S. Government Printing Office, Washington, D.C., 20420.
B. In addition, Contractor will be required to comply with other applicable Medical Center policies and safety regulations.
These policies and regulations will be presented to the Contractor at the pre-construction meeting. Each of the Contractor’s employees will be required to read the statement of policies and regulations, and sign an acknowledgment that such policies and regulations are understood. Signed acknowledgment will be returned to the Contract Officer Technical Representative.
C. Contractors involved with the removal, alteration or disturbance of asbestos-type insulation or materials or lead paint will be required to comply strictly with the regulations found in CFR 1910.1001 and the appropriate Environmental Protection Agency (EPA) lead regulations regarding disposal of asbestos or lead paint. Assistance in identifying asbestos or lead can be requested from the Medical Center’s Industrial Hygienist and the COR.
D. Contractors entering locations of asbestos contamination or lead paint residue (i.e., pipe, basements, walls, windows) shall be responsible for providing respiratory protection to their employees and ensuring respirators are worn in accordance with the Occupational Safety and Health Administration (OSHA) [CFR 1910.1001(g)]. Asbestos-or lead paint-contaminated areas shall be defined on project drawings. The minimum equipment requirements will be a half-mask air-purifying respirator equipped with high efficiency filters and disposable coveralls, or as determined by air monitoring results.
E. Contractor, along with other submittals and at least two weeks prior to bringing any materials on-site, must submit a complete list of chemicals the Contractor will use and Material Safety Data Sheets (MEDS) for all hazardous materials as defined in OSHA 1910.1200(d), Hazard Determination.
Upgrade Smart Building System Project No. 541-19-201
LOUIS STOKES CLEVELAND VAMC
OSHA Requirements and Safety and Health Regulations - Attachment 1
Contracting Officer shall have final approval of all materials brought on site.
F. The Contractor will be held solely responsible for the safety and health of their employees. The contractor will also be held responsible for protecting the health and safety of the VA Community (patients, staff, and visitors) from the unwanted effects of construction. VA staff will monitor the Contractor's performance in complying with all safety and health aspects of the project.