05_SOW 516-26-117.pdf
PDF 217 KB Posted
- Solicitation number
- 36C24827Q0004
About this file
This is a Statement of Work (SOW) dated February 2, 2026, for repair and temporary heating services at Bay Pines Veterans Health Administration (VHA) facility in St. Petersburg, Florida. The work addresses an active steam leak in an underground steam manhole that serves Buildings 1, 71/101, 2, 37, 23, and 22. The scope comprises two primary objectives: installation of temporary rental heating hot water boilers in Buildings 71 and 101 (the only patient-occupied buildings on the affected steam line) with diesel-powered generators to maintain heating during the multi-month repair period, and complete replacement of damaged steam piping both inside and outside the manhole, including excavation to at least six feet from the manhole, welding, pressure testing, insulation, and commissioning. The period of performance is eight months from contract award.
The rental system scope requires the vendor to provide electric-powered boilers (Lattner S165 LW for Building 71 and TB-209 for Building 101), appropriately sized diesel generators, all necessary electrical connections and cable protection, high-temperature hose fabrication, safety fencing (6-foot chain-link, double-locked with VA access), and full maintenance and emergency replacement capabilities (replacement boilers within 36 hours if non-repairable within 24 hours; replacement generators within 24 hours). The leak repair scope mandates replacement of four proprietary jacketed pipe sections from Rovanco (job 41556) with long lead times, replacement of all internal steam and pumped condensate piping, installation of new valves (300 GATE for high-pressure steam, 150 GATE for pumped condensate), replacement of the steam trap with a bucket trap, installation of a Watson McDaniel sparge flash arrestor, comprehensive welding per ASME B31.1 with 100% visual inspection and ultrasonic testing of all underground welds, hydrostatic pressure testing (HPS piping at double working pressure; PC piping at 113 PSIG), complete pipe insulation with corrosion-resistant jackets, installation of a new sump pump, masonry wall repair, waterproofing per VHA Spec 07 12 00, site restoration including sod replacement, and removal of all old materials. Work must follow VHA Specifications 33 63 00 (Steam Energy Distribution) and 33 08 00 (Commissioning of Site Utility Systems), with critical coordination requirements including pre-ordering of long-lead piping, Rovanco representative inspections twice during installation, and FMS staff coordination for pressure testing and system cleandown.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| EMR 1 page.docx | DOCX document | |
| WD-FL20260222 DATED 5-18-26.pdf | ||
| 36C24827Q0004_1.pdf | ||
| PPQ.pdf | ||
| SHOP DRAWINGS HIGH PRESSURE STEAM PUMPED ROVANCO PIPING SYSTEM.pdf | ||
| Base Offer Price Breakdown - 1 page.xlsx | XLSX spreadsheet | |
| 516-26-117 Specifications 00 01 10.pdf | ||
| 05_Drawings SECTION LP302- 516-26-117.pdf | ||
| ASBUILTS-516-26-117.pdf | ||
| SHOP DRAWINGS HIGH PRESSURE STEAM PUMPED ROVANCO PIPING SYSTEM.pdf | ||
| WD-FL20260222 DATED 5-18-26.pdf | ||
| 05_Drawings SECTION LP302- 516-26-117.pdf | ||
| PPQ -Request form.docx | DOCX document | |
| PPQ.pdf | ||
| Base Offer Price Breakdown - 1 page.xlsx | XLSX spreadsheet | |
| 05_ASBUILTS-516-26-117.pdf | ||
| 36C24827Q0004_1.pdf | ||
| 516-26-117 Specifications 00 01 10.pdf | ||
| EMR 1 page.docx | DOCX document | |
| SHOP DRAWINGS HIGH PRESSURE STEAM PUMPED CONDENSATE ROVANCO PIPING SYSTEM.pdf | ||
| 05_Drawings LP302- 516-26-117.pdf | ||
| 36C24827Q0004.docx | DOCX document |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Dated: February 2, 2026
A. OVERVIEW
Bay Pines VHA uses steam to create hot water used for heating buildings and to make domestic hot water. The pipes that carry this steam leaves the boiler plant (Building
#100F) and go underground out to locations where the steam is used. If there are locations where this underground steam diverges and goes to two separate buildings this is done in a manhole
There is a steam manhole between buildings 1 and 111 on the Bay Pines VHA campus.
This manhole is the junction point for the steam as it leaves the energy plant and goes to
Buildings 1, 71/101, 2, 37, 23 and 22. The steam at this location splits and goes to
Buildings 1, 22 and 23 via one pipe and the remainder of the buildings via another pipe.
There is an active steam leak in this steam manhole. The only way to safely evaluate this leak (determine the extent of the leak and thus the material needed to fix the leak) is to shut the steam down to this manhole from the energy plant. Due to the extent of the leak, it is thought (by in house, steam subject matter experts) that the steam will not be able to be turned back on to this manhole once it has been shut down, until the repair is made.
This will leave no heat to the buildings listed above until the leak is fixed. It is anticipated this leak will takes several months of time to repair due to lead time for materials and the amount of work to be done.
The piping on the exterior of this manhole is a proprietary jacketed system. Some of this pipe needs to be replaced to fix this leak, that is known. This pipe has a long lead time of months. In order to reduce the downtime for this repair new sections of this pipe will be ordered to ensure all possible leak and repair situations are covered before shut downs happen and repairs begin.
B. OBJECTIVE
The objective of this work is twofold.
First is to install rental heating hot water boilers in B71 and 101 to provide heating hot water to these buildings for the duration of the repair. These are the only buildings fed by this steam leg that houses patients overnight. Even with preordering the exterior piping before shutting down the steam to this manhole, this repair will take weeks to complete.
These boilers will need to be powered from a diesel powered generator as there is not sufficient available electrical power in the buildings.
Second is to purchase, install and test/commission all required steam piping to repair this leak. This will include digging up the ground at least 6 foot away from this manhole to replace 2 sets of pipes that go into and come out of this manhole as well as replacing all piping and fittings inside the manhole.
C. SCOPE OF WORK (RENTAL)
NOTE: Before the rental systems are procured and put into operation, all new underground piping needs to be ordered from Rovanco. Planning for and obtaining of the items needed for the rental systems can be done to coincide with an anticipated delivery date of the pipe. Once these new pipes have been received on site is when rental systems can be installed and started up.
Communication of these events to VHA FMS staff is critical.
1. To keep heat and domestic hot water to the patient occupied buildings of the
CLC (71 and 101) vendor shall provide all required systems and piping connections to provide heating hot water and domestic hot water to these buildings.
2. Vendor will provide electric powered hot water boilers. These boilers will be located inside the mechanical rooms of B71 and B101. The work of installing rental boilers for these buildings has been done recently and at that time a
Lattner, S165 LW (16.5 HP) and a TB-209 (27.5 HP) boiler were used for this purpose.
a. It is responsibility of the vendor to verify the sizing of each of these boilers based on the heating hot water and domestic hot water heat exchanger sizes in the buildings as these temporary boilers will be used for both heating hot water and domestic hot water. The above can be used for reference.
b. Spool pieces of piping are available on site to be used to connect these boilers to the buildings heating hot water systems. Spool pieces are VA property and will be returned to the VA at the end of the rental period.
c. Final connection from the boiler to the spool piece needs to be done with high temperature rubber hose. Vendor will be responsible for fabricating and installing this hose for each boiler.
d. Vendor will be responsible for all required maintenance of these boilers for the duration of the rental.
e. In the event of a failure that is not repairable within 24 hours vendor will provide replacement boiler(s) within 36 hours.
3. Vendor shall provide a diesel generator(s) large enough to power these boilers.
a. Vendor is responsible for sizing of these generators to ensure they are the right size and power (Volts, amps, phase) for the boilers.
b. Vendor will be responsible for keeping these generator(s) fueled. This will include checking the oil level while the generator is off for refueling.
c. Vendor will be responsible for all other required maintenance of these generator(s) for the duration of the rental. Oil changes, coolant level inspections /changes and other preventive maintenance required by the manufacturer.
d. In the event of a failure that is not repairable vendor will provide a replacement generator within 24 hours.
4. Maintenance of the boilers and generators shall be planned to coincide with each other when possible to limit down time.
a. All maintenance (planned or emergency) shall be communicated to the
COR for this project.
5. Vendor will provide all electrical power cords needed to safety go between generator(s) and boilers.
a. This will include any cable protection needed for areas power cords will cross walkways.
6. Vendor shall provide fence to go around generator(s) for duration of the rental period. 6 foot tall minimum. Double locked with a VA lock to allow VA access.
7. Vendor will start up and verify full operation of this rental system. This start up can be done on a weekday.
a. All systems (generator and boiler) shall be tested for full operation before final connections are made to reduce downtime.
8. Once the rental systems to provide hot water (heating and domestic) are complete to B101 and B71 then the steam to the manhole can be shutdown and
LOTO.
9. Once the need for the rental system is complete, vendor will be responsible for disconnecting the boilers from the piping systems and restoring the piping systems to what they where reconnecting the heating hot water in the mechanical room for B71 and B101. This cannot be done until steam has been restored to B71and B101 mechanical rooms.
SCOPE OF WORK (LEAK REPAIR)
NOTE: All piping, fittings, valves, welding and other associated work done for this repair shall follow VHA TIL spec section 33 63 00, Steam Energy Distribution and 33 08 00
Commissioning of Site Utility Systems. There are other notes throughout this section that are above and beyond these specs. They need to be followed as well.
1. All HPS (high pressure steam) and PC (pumped condensate) pipes are being replaced. This applies for pipes internal and external to the manhole. (External to ~6 feet of the manholes or to the anchors, which ever is further)
2. If investigations are needed of the pipe outside the manhole that is allowed before the steam system is shut down.
a. No shutdown of the existing system to investigate the inside of the manhole is allowed.
b. Investigation holes are not required to be back filled, provided 6 foot tall chain link fence surrounds the investigation locations.
3. Vendor shall work with Rovanco piping company to obtain 4 pieces of jacketed pipe to be used to replace the pipe on the exterior of the manhole.
a. Pipe must match the pipe defined in Rovanco job no 41556.
Documents for this Job no. can be found in Appendix B of this SOW.
b. For the pipes that go to the West of the manhole (to Building 1) and to the North of the manhole (from B100) there is a concrete anchor (thrust block) within 5 feet of the manhole. Enough pipe will have to be ordered to allow this anchor to be replaced and these sections of pipe will need the anchor detail (from drawing set) to allow the anchor to be replaced.
i. If exploratory digs need to be made to determine the exact location of these anchors to then determine the amount of pipe to be ordered, that is allowed. Holes will not have to be refilled, just will need to be protected by fencing. (6’ chainlink)
c. All pipes that go to the south of the manhole (to B71) do not need to be replaced.
d. The underground High Pressure Condensate pipes (From b100 into
Manhole and from Manhole to B71) are not being replaced. They are being abandoned in place.
e. Rovanco will determine the amount of total pipe that needs to be ordered and the materials and procedures to be followed for installing these sections of pipe. Pipe will not be ordered from Rovanco without them creating a drawing set for this order with installation instructions.
f. These sections of pipe shall all have Rovanco manufactured above ground end seals on the ends going into the manhole.
i. Carrier pipe for each pipe section shall extend at least 3 foot past the end plate for connection of the piping inside the manhole.
g. This step (ordering the pipe) is critical to happen first. This pipe has a long lead time and no other work can happen on this project until this pipe has an anticipated delivery date or the pipe has been delivered to the site.
h. It is critical to follow all Rovanco handling and storage recommendations for this pipe. Damage to the pipe, rusting of the pipe, wet insulation will render these section of pipe unusable and they will have to be replaced at vendors cost.
i. This includes unloading of the pipe, when the pipe is being stored on site and while it is being installed.
4. Vendor shall provide a LOTO procedure for the steam to the manhole. This shall include all HPS, HPC, PC and electrical sources of energy into that manhole.
5. The exterior work around this manhole will need a dewatering system to ensure water is removed from the excavations. Vendor needs to plan for that.
6. Once ends of the underground PC pipes are exposed vendor shall hydrostatically pressure test all pipes to 113 PSIG. These pipes are
a. the PC pipe from B100 towards Manhole
b. the PC pipe to B1 from Manhole
c. the PC pipe to B71/101 from Manhole
d. This test has to be done in conjunction with the FMS plumbing shop to prevent damage to systems. A work plan submission will be required for this test. (All valves from / to these buildings should be off and
LOTO prior to work starting)
7. Vendor shall install four new sections of Rovanco pipe.
a. Care shall be taken to ensure water does enter the jacketed part of the pipe left underground, does not saturate the insulation of the pipe remaining in the ground and that debris or water does not enter steam or
PC carrier pipes.
8. It is required a Rovanco representative be on site at least twice during the installation to inspect the installation. Once after the welding of the carrier pipe to inspect the weld and installation of the carrier insulation and once during the installation of the field applied foam insulation, HDPE split mold and Polyethylene wrap shrink material.
9. Replace all HPS and PC piping in the manhole. Piping shall meet all requirements of the 33 63 00 VHA Spec.
a. Details for existing piping in manhole can be found in Appendix C of this SOW.
b. No unions are allowed unless noted. Unions shall be done with flanges.
c. No cast iron pipe or fittings allowed
d. No A307 bolts allowed for any part of the steam or PC piping system.
e. All pipe and fittings shall be manufactured in the USA
f. Replacement Piping can follow existing routing or be modified. New piping can not block access to manhole structure via the existing man holes.
10. Replace all HPS and PC valves that exist on manhole now.
a. HPS valves shall be 300 GATE.
b. PC valves shall be 150 GATE
c. Gaskets shall be FLEXITALLIC
11. Add HPS and PC valves to the B101/71 pipes. If piping layout needs to be adjusted from original to allow these valves to not be tight to the exterior walls of the manhole, pipe layout shall be adjusted.
12. All HPC pipe in the manhole shall be removed.
a. HPC pipes coming into and leaving manhole shall have PC rated valves installed on it.
13. Replace the steam trap in the manhole. Use a bucket trap. Steam trap and union for it shall be threaded.
14. Install a sparge flash arrestor in the PC pipe to allow the condensate from the trap to be introduced into the PC pipe. Sparge flash arrestor shall have flanges on it. This unit shall be a Watson McDaniel FA Flash Arrestor or equivalent.
Unit shall be SS.
a. Connect the steam trap to this sparge flash arrestor per the manufacturers specifications.
15. Replace all link seals for all pipes into and out of the manhole (including the
HPC pipes and sump pump pipe.)
16. All welding shall be in compliance with ASME B31.1.
a. All butt welds on steam and condensate piping systems shall have a
GTAW root pass. Backing rings shall not be used.
i. This requirement is for all piping inside and outside of the manhole.
b. 100% of welds will be visually inspected.
c. 100% of all undergrounds welds shall be evaluated with ultrasonic testing (UT) by phased array. All persons performing and evaluating ultrasonic examinations will be certified for NDT Level II as recognized by the American Society for Nondestructive Testing
(ANST). In lieu of UT, radiography testing can be performed, but this requires all persons within a 25 to 50 feet radius to be cleared out during the film exposure. This applies to carrier pipe only.
d. 10% or 2 welds (which ever is higher) of welds in the manhole shall be evaluated with ultrasonic testing by phased array.
17. All new HPS piping shall be hydrostatically pressure tested to double the working pressure for 2 hours minimum with no pressure decay.
18. All new PC piping shall be hydrostatically pressure tested to 113 PSIG for 2 hours minimum with no pressure decay.
19. All piping inside the manhole shall be supported from below. It shall not be supported from the structure roof. All supporting systems shall meet industry standard for span between them and size of pipe they are supporting. All supporting systems shall be Stainless steel, aluminum or other approved corrosion resistant material. No carbon steel system, fasteners or washers are allowed.
20. Internal Cleaning of piping.
a. Once steam piping installation is complete, all welding inspections complete and pressure tests complete, FMS will work with vendor to crack open steam valve to the new piping and let the condensate drain for 4 hours. Vendor shall be responsible for monitoring condensate and blowing down the drip legs during this process.
b. Coordinate with FMS to ensure Steam Condensate is fully drained and sent to drain.
21. Insulate entire piping system in the manhole.
a. Pipe shall not be insulated until all welds have been inspected and pressure tests complete.
b. Insulation shall be per section 3.13 of the 33 63 00 spec.
c. All insulation shall have a corrosion resistant metal jacket.
d. Valves and steam trap shall be insulated with premade steam rated compressed blankets made for that type and size fitting. Jackets shall be installed and removeable with Velcro type material.
22. Install a new sump pump in the manhole.
a. If an electric pump, it shall be a duplex pump system rated for high temperature (180 deg F)
b. If a steam driven pump it shall be Watson McDaniel or equivalent.
c. Replace the discharge pipe for the manhole sump pump with SS pipe to the point of discharge into a storm structure. Minimum schedule 10 pipe with underground rated fittings.
d. Install pipe such that it does not interfere with repair of the masonry wall.
23. Inside room Service Bay 1-7 of B100, the HPC pipe needs to be cut and capped on both ends of the cut pipe.
a. Cut and cap location needs to be after existing connection location for the condensate from the High pressure steam trap.
b. All welds in this location need to follow weld specifications and inspection protocol listed in this document.
c. At least a 1 foot gaps needs to be left between cut ends.
d. Remaining sections of HPC pipe needs to be properly supported.
e. The building side (pressurized) of the HPC piping will need to be reinsulated, to match existing.
f. Install a sparge flash arrestor in the PC pipe to allow the condensate from the trap to be introduced into the PC pipe. Sparge flash arrestor shall have flanges on it. This unit shall be a Watson McDaniel FA Flash
Arrestor or equivalent. Unit shall be SS.
i. This section of pipe shall be reinsulated in kind as existing.
g. A new bucket trap shall be installed off the HPS steam pipe.
i. Trap shall be installed with a union.
ii. Steam trap shall be insulated with premade steam rated compressed blankets made for that type and size fitting. Jackets shall be installed and removeable with Velcro type material.
iii. All trap piping (existing and new) shall be insulated.
h. Connect the steam trap to this sparge flash arrestor per the manufacturers specifications.
24. All vertical walls of the manhole shall be exposed during this work below the wall to floor seam and new water proofing applied. Follow VHA Spec 07 12
00 for this.
a. Water proofing shall be a liquid applied material. Manufacturer of material shall warranty application for a minimum of 5 years.
b. If the lid of the manhole is removed for interior work, a new gasket shall be installed when lid is reinstalled. Water proofing shall extend to top edge of the entire manhole, over the seam between lid and side walls.
c. New water proofing must be compatible with existing water proofing material. Written confirmation of this compatibility from the product manufacturer is required.
25. Any damaged sidewalks or concrete (Moving machinery in and out of site, or other) shall be repaired by vendor. Damaged sidewalks are a safety hazard and will be repaired when damage is found, not at end of project.
a. If concrete pads for picnic tables need to be removed. They shall be replaced in kind.
26. Any damaged irrigation pipes, control wiring or control valves shall be reported to FMS staff for repair by FMS staff.
27. There are other known utilities in the area. Locations for these utilities need to happen and appropriate digging techniques used to not cause damage to these systems. Vendor needs to have utility survey done as well.
28. There is a power pole near the manhole. It needs to stay there and either not be touched or replaced in kind if removed for other work.
29. Vendor shall be responsible for providing fence around entire work site. 6 foot tall chain-link.
30. Vendor shall remove and dispose of all old pipe, insulation, concrete (anchors and other) and fittings.
31. Vendor shall rebuild masonry wall south of manhole. Details for wall are in
Appendix A.
a. Area behind wall shall be back filled, smoothed, top soil applied and sod placed.
b. Before area is back filled consult with FMS staff to ensure they have opportunity to install irrigation piping and heads.
32. All ground damaged and disturbed during repair work shall be returned to a state better then it is in currently.
33. Grass shall be replaced as sod (not seed) in all disturbed areas.
34. Ruts caused by equipment shall be filled in, to the satisfaction of the grounds supervisor.
D. PERIOD OF PERFORMANCE
a. The period of performance of this contract shall be for 8 months after award of contract.
E. LOCATION
a. Work shall be performed at Bay Pines VHA, 10000 Bay Pines Blvd, St
Petersburg FL 33744
Appendix A: Drawing showing details for the masonry wall to be repaired.
Appendix B: Rovanco pipe drawing set.
Appendix C: Existing steam line and manhole details
File details come from the government source that posted it. Updated .