This is a specification section for hollow metal doors and frames for the Tuscaloosa VAMC Laundry Renovation and Addition Building 18 project (Project No. 679-24-102) in Tuscaloosa, Alabama, dated March 15, 2026.

The specification requires hollow metal doors and frames complying with ANSI A250.8 standards and various ASTM material specifications. Exterior doors must be 44 mm (1-3/4 inches) thick Level 3, extra-heavy duty construction with galvanized sheet steel faces and polystyrene or polyurethane cores. Interior doors require the same thickness and duty level with sheet steel faces and kraft paper honeycomb cores. Fire-rated doors and frames must be UL 10C and NFPA 80 labeled per drawings. Blast-resistant doors are specified for Mission Critical Protected applications at 50 feet standoff distance with a maximum of 14 gauge metal, frame rotation not exceeding L/40, and blast-compliant glazing. Hollow metal frames must be knock-down ANSI A250.8 construction with interior frames at 1.0 mm thickness and exterior frames at 1.3 mm minimum thickness, utilizing sheet steel for interior and galvanized steel for exterior applications. Sustainable construction requirements mandate 30 percent recycled content minimum for steel, 70 percent for stainless steel, and 50 percent for aluminum. All products must be sourced from a single manufacturer with documented project experience on five similar installations for minimum five years.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tuscaloosa VAMC March 15, 2026 Laundry Renovation and Addition Bldg.18 Addendum #1 Tuscaloosa, AL 35404 Project No: 679-24-102

VA 01-01-21

08 11 13 - 1

SECTION 08 11 13

HOLLOW METAL DOORS AND FRAMES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Hollow metal doors hung in hollow metal frames at exterior locations.

2. Hollow metal door frames for wood doors and borrowed lights at interior locations.

1.2 RELATED WORK

A. Section 05 50 00, METAL FABRICATIONS: Frames fabricated of structural steel.

B. Section 08 71 00, DOOR HARDWARE: Door Hardware:

C. Section 08 80 00, GLAZING: Glazing.

D. Card Readers and Biometric Devices: Section 28 13 00, PHYSICAL

ACCESS CONTROL SYSTEM.

1.3 APPLICABLE PUBLICATIONS

A. Comply with references to extent specified in this section.

B. American National Standard Institute (ANSI):

A250.8-2014 .......... Standard Steel Doors and Frames

C. ASTM International (ASTM):

A240/A240M-15b ....... Chromium and Chromium-Nickel Stainless

Steel Plate, Sheet, and Strip for Pressure

Vessels and for General Applications

A653/A653M-15 ........ Steel Sheet, Zinc-Coated (Galvanized) or

Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip

A1008/A1008M-15 ...... Steel, Sheet, Cold-Rolled, Carbon, Structural, High Strength Low Alloy and

High Strength Low Alloy with Improved

08 11 13 - 2

Formability, Solution Hardened, and Bake

Hardenable

B209-14 .............. Aluminum and Aluminum-Alloy Sheet and Plate

B209M-14 ............. Aluminum and Aluminum-Alloy Sheet and Plate

(Metric)

B221-14 .............. Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes

B221M-13 ............. Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes (Metric)

D3656/D3656M-13 ...... Insect Screening and Louver Cloth Woven from Vinyl Coated Glass Yarns

E90-09 ............... Laboratory Measurement of Airborne Sound

Transmission Loss of Building Partitions and Elements

D. Federal Specifications (Fed. Spec.):

L-S-125B ............. Screening, Insect, Nonmetallic

E. Master Painters Institute (MPI):

No. 18 ............... Primer, Zinc Rich, Organic

F. National Association of Architectural Metal Manufacturers

(NAAMM):

AMP 500-06 ........... Metal Finishes Manual

G. National Fire Protection Association (NFPA):

80-16 ................ Fire Doors and Other Opening Protectives

H. UL LLC (UL):

10C-09 ............... Positive Pressure Fire Tests of Door

Assemblies

1784-15 .............. Air Leakage Tests of Door Assemblies and

Other Opening Protectives

I. Department of Veterans Affairs

VA Physical Security and Resiliency Design Manual October 1, 08 11 13 - 3

1.4 SUBMITTALS

A. Submittal Procedures: Section 01 33 23, SHOP DRAWINGS, PRODUCT

DATA, AND SAMPLES.

B. Submittal Drawings:

1. Show size, configuration, and fabrication and installation details.

C. Manufacturer's Literature and Data:

1. Description of each product.

2. Include schedule showing each door and frame requirements fire label for openings.

3. Installation instructions.

D. Sustainable Construction Submittals:

1. Recycled Content: Identify post-consumer and pre-consumer recycled content percentage by weight.

E. Test reports: Certify products comply with specifications.

1. Sound rated door.

F. Qualifications: Substantiate qualifications comply with specifications.

1. Manufacturer with project experience list.

1.5 QUALITY ASSURANCE

A. Manufacturer Qualifications:

1. Regularly manufactures specified products.

2. Manufactured specified products with satisfactory service on five similar installations for minimum five years.

a. Project Experience List: Provide contact names and addresses for completed projects.

1.6 DELIVERY

A. Fasten temporary steel spreaders across the bottom of each door frame before shipment.

B. Deliver products in manufacturer's original sealed packaging.

C. Mark packaging, legibly. Indicate manufacturer's name or brand, type, production run number, and manufacture date.

08 11 13 - 4

D. Before installation, return or dispose of products within distorted, damaged, or opened packaging.

1.7 STORAGE AND HANDLING

A. Store products indoors in dry, weathertight conditioned facility.

B. Protect products from damage during handling and construction operations.

1.8 WARRANTY

A. Construction Warranty: FAR clause 52.246-21, "Warranty of

Construction."

PART 2 - PRODUCTS

2.1 SYSTEM PERFORMANCE

A. Design hollow metal doors and frames complying with specified performance:

1. Fire Doors and Frames: UL 10C; NFPA 80 labeled.

a. Fire Ratings: See drawings.

2. Blast Resistant Doors: Door, Frame and Anchorage:

a. Standoff Distance: 50 feet (Mission Critical Protected)

b. Design Threat W1 at the standoff distance not to exceed pressure and impulse associated with GP2 threat for Mission

Critical Protected buildings.

c. Frame Rotation not to exceed L/20 (Life Safety Protected

L/40 (Mission Critical Protected) while experiencing design level pressure and impulse.

d. Glazing: Glazing shall meet the blast requirements.

e. Minimum gauge of metal used on blast resistant doors shall be 14 gauge.

2.2 MATERIALS

A. Sheet Steel: ASTM A1008/A1008M, cold-rolled.

B. Galvanized Sheet Steel: ASTM A653.

C. (ASTM B221).

08 11 13 - 5

2.3 PRODUCTS - GENERAL

A. Basis of Design: As indicated.

B. Provide hollow metal doors and frames from one manufacturer.

C. Sustainable Construction Requirements:

1. Steel Recycled Content: 30 percent total recycled content, minimum.

2. Stainless Steel Recycled Content: 70 percent total recycled content, minimum.

3. Aluminum Recycled Content: 50 percent total recycled content, minimum.

2.4 HOLLOW METAL DOORS

A. Hollow Metal Doors: ANSI A250.8; 44 mm (1-3/4 inches) thick. See drawings for sizes and designs.

1. Interior Doors: Level 3 and Physical Performance Level A, extra-heavy duty.

2. Exterior Doors: Level 3 and Physical Performance Level A, extra-heavy duty.

B. Door Faces:

1. Interior Doors: Sheet steel.

2. Exterior Doors: Galvanized sheet steel minimum.

C. Door Cores:

1. Interior Doors: Kraft paper honeycomb.

2. Exterior Doors: Polystyrene or polyurethane.

3. Fire Doors: Manufacturer's standard complying with specified fire rating performance.

2.5 HOLLOW METAL FRAMES

A. Hollow Metal Frames: ANSI A250.8; Knock-down See drawings for sizes and designs.

1. Interior Frames:

a. Level 1 Hollow Metal Doors: 1.0 mm (0.042 inch) thick.

b. Level 1 Hollow Metal Doors: 1.0 mm (0.042 inch) thick.

08 11 13 - 6

c. Interior Automatic Operator Door Frames: 1.7 mm

(0.067 inch) thick.

d. Exterior Frames:

1) Level 3 Hollow Metal Doors: 1.3 mm (0.053 inch) thick.

B. Frame Materials:

1. Interior Frames: Sheet steel.

2. Exterior Frames: Galvanized sheet steel minimum

2.6 FABRICATION

A. Hardware Preparation: ANSI A250.8; for hardware specified in

Section 08 71 00, DOOR HARDWARE.

B. Hollow Metal Door Fabrication:

1. Close top edge of exterior doors flush and seal to prevent water intrusion.

2. Fill spaces between vertical steel stiffeners with insulation.

C. Fire Doors:

1. Close top and vertical edges flush.

2. Apply steel astragal to active leaf at pair and double egress doors.

a. Exception: Where vertical rod exit devices are specified for both leaves swinging in same direction.

3. Fire Door Clearances: NFPA 80.

D. Hollow Metal Frame Fabrication:

1. Terminated Stops: ANSI A250.8.

2. Two Piece Frames:

a. One piece unequal leg finished rough buck sub-frames as shown, drilled for anchor bolts.

b. Unequal leg finished frames formed to fit subframes and secured to subframe legs with countersunk, flat head screws, spaced 300 mm (12 inches) on center at head and jambs on both sides.

c. Preassemble at factory for alignment.

3. Frame Anchors:

a. Floor anchors:

08 11 13 - 7

1) Provide extension type floor anchors to compensate for depth of floor fills.

2) Provide 1.3 mm (0.053 inch) thick steel clip angles welded to jamb and drilled to receive floor fasteners.

3) Provide 50 mm by 50 mm by 9 mm (2 inch by 2 inch by

3/8 inch) clip angle for lead lined frames, drilled for floor fasteners.

4) Provide mullion 2.3 mm (0.093 inch) thick steel channel anchors, drilled for two floor fasteners and frame anchor screws.

5) Provide continuous 1 mm (0.042 inch) thick steel rough bucks drilled for floor fasteners and frame anchor screws for sill sections.

a) Space floor bolts50 mm (24 inches) on center.

b. Jamb anchors:

1) Place anchors on jambs:

a) Near top and bottom of each frame.

b) At intermediate points at maximum 600 mm (24 inches) spacing.

2) Form jamb anchors from steel minimum 1 mm (0.042 inch) thick.

3) Anchors set in masonry: Provide adjustable anchors designed for friction fit against frame and extended into masonry minimum 250 mm (10 inches). Provide one of following types:

a) Wire Loop Type: 5 mm (3/16 inch) diameter wire.

b) T-Shape type.

c) Strap and stirrup type: Corrugated or perforated sheet steel.

4) Anchors for stud partitions: Provide tabs for securing anchor to sides of studs. Provide one of the following:

a) Welded type.

b) Lock-in snap-in type.

08 11 13 - 8

5) Anchors for frames set in prepared openings:

a) Steel pipe spacers 6 mm (1/4 inch) inside diameter, welded to plate reinforcing at jamb stops, or hat shaped formed strap spacers 50 mm (2 inches) wide, welded to jamb near stop.

b) Drill jamb stop and strap spacers for 6 mm (1/4 inch) flat head bolts to pass through frame and spacers.

c) Two piece frames: Subframe or rough buck drilled for

6 mm (1/4 inch) bolts.

6) Anchors for observation windows and other continuous frames set in stud partitions.

a) Weld clip anchors to sills and heads of continuous frames over 1200 mm (4 feet) long.

b) Space maximum 600 mm (24 inches) on centers.

7) Modify frame anchors to fit special frame and wall construction.

8) Provide special anchors where shown on drawings and where required to suit application.

E. Sound Rated Door Frames:

1. Seals: Integral continuous gaskets on frames.

2.7 FINISHES

A. Steel and Galvanized Steel: ANSI A250.8; shop primed.

B. Stainless Steel: NAAMM AMP 500; No. 4 polished finish.

1. Blend welds to match adjacent finish.

C. Finish exposed surfaces after fabrication.

2.8 ACCESSORIES

A. Primers: ANSI A250.8.

B. Barrier Coating: ASTM D1187/D1187M.

C. Welding Materials: AWS D1.1/D1.1M, type to suit application.

D. Clips Connecting Members and Sleeves: Match door faces.

E. Fasteners: Galvanized steel.

1. Metal Framing: Steel drill screws.

08 11 13 - 9

2. Masonry and Concrete: Expansion bolts and power actuated drive pins.

F. Anchors: Galvanized steel.

G. Galvanizing Repair Paint: MPI No. 18.

H. Insulation: Unfaced mineral wool.

PART 3 - EXECUTION

3.1 PREPARATION

A. Examine and verify substrate suitability for product installation.

B. Protect existing construction and completed work from damage.

C. Apply barrier coating to metal surfaces in contact with cementitious materials to minimum 0.7 mm (30 mils) dry film thickness.

3.2 INSTALLATION - GENERAL

A. Install products according to manufacturer's instructions and approved submittal drawings.

1. When manufacturer's instructions deviate from specifications, submit proposed resolution for Contracting Officer's

Representative consideration.

2. Install fire doors and frames according to NFPA 80.

3.3 FRAME INSTALLATION

A. Apply barrier coating to concealed surfaces of frames built into masonry.

B. Plumb, align, and brace frames until permanent anchors are set.

1. Use triangular bracing near each corner on both sides of frames with temporary wood spreaders at midpoint.

2. Use wood spreaders at bottom of frame when shipping spreader is removed.

3. Where construction permits concealment, leave shipping spreaders in place after installation, otherwise remove spreaders when frames are set and anchored.

4. Remove wood spreaders and braces when walls are built and jamb anchors are secured.

08 11 13 - 10

C. Floor Anchors:

1. Anchor frame jambs to floor with two expansion bolts.

a. Lead Lined Frames: Use 9 mm (3/8 inch) diameter bolts.

b. Other Frames: Use 6 mm (1/4 inch) diameter bolts.

2. Power actuated drive pins are acceptable to secure frame anchors to concrete floors.

D. Jamb Anchors:

1. Masonry Walls:

a. Embed anchors in mortar.

b. Fill space between frame and masonry with grout or mortar as walls are built.

2. Metal Framed Walls: Secure anchors to sides of studs with two fasteners through anchor tabs.

3. Prepared Masonry and Concrete Openings:

a. Direct Securement: 6 mm (1/4 inch) diameter expansion bolts through spacers.

b. Subframe or Rough Buck Securement:

1) 6 mm (1/4 inch) diameter expansion bolts on 600 mm

(24 inch) centers.

2) Power activated drive pins on 600 mm (24 inches) centers.

c. Secure two-piece frames to subframe or rough buck with machine screws on both faces.

E. Frames for Sound Rated Doors: Fill frames with insulation.

F. Lead Lined Frames:

1. Extend jambs and anchor with clip angles to structure above.

a. Fasteners to Concrete: Minimum two, 9 mm (3/8 inch) diameter expansion bolts.

b. Connection to Structural Steel: Welded.

G. Touch up damaged factory finishes.

1. Repair galvanized surfaces with galvanized repair paint.

2. Repair painted surfaces with touch up primer.

3.4 DOOR INSTALLATION

A. Install doors plumb and level.

08 11 13 - 11

B. Adjust doors for smooth operation.

C. Touch up damaged factory finishes.

1. Repair galvanized surfaces with galvanized repair paint.

2. Repair painted surfaces with touch up primer.

3.5 CLEANING

A. Clean exposed door and frame surfaces. Remove contaminants and stains.

3.6 PROTECTION

A. Protect doors and frames from traffic and construction operations.

B. Remove protective materials immediately before acceptance.

C. Repair damage.

- - - E N D - - -

SECTION 08 11 13 HOLLOW METAL DOORS AND FRAMES
PART 1 - GENERAL
1.1 SUMMARY
1.2 RELATED WORK
1.3 APPLICABLE PUBLICATIONS
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
1.6 DELIVERY
1.7 STORAGE AND HANDLING
PART 2 - PRODUCTS
2.1 SYSTEM PERFORMANCE
2.2 MATERIALS
2.3 PRODUCTS - GENERAL
2.4 HOLLOW METAL DOORS
2.5 HOLLOW METAL FRAMES
2.6 FABRICATION
2.7 FINISHES
2.8 ACCESSORIES
PART 3 - EXECUTION
3.1 PREPARATION
3.2 INSTALLATION - GENERAL
3.3 FRAME INSTALLATION
3.4 DOOR INSTALLATION
3.5 CLEANING
3.6 PROTECTION

File details come from the government source that posted it. Updated .