This file consists of Questions and Answers (RFIs) regarding Project 557-21-103: Correct Critical Roof and Exterior Wall Deficiencies, a federal construction project under contract number 36C24726R0030.
The project involves comprehensive roof and exterior wall repairs at a Virginia facility, with work governed by Davis Bacon Wage requirements. Key roofing specifications include either 60-mil PVC or TPO membrane systems with manufacturer warranties of 20 years, overall insulation R-value of RSI-57 (R-25) minimum, and 16-gauge metal decking with shims as needed for existing conditions. The contractor must maintain a dedicated Contractor Qualified Control (CQC) person on-site with USACE Contractor Quality Control certification, independent from the superintendent, project manager, and installer roles. This CQC person shall manage comprehensive photographic documentation using 50-megapixel cameras, cloud-based storage (Procore basis of design), and standardized filing systems organized by date, location, and work type. Heat-welded walk pads (not peel-and-stick) must connect all egress points to serviceable equipment, and 13-mm (½-inch) gypsum cover board is required over insulation. The contractor should expect approximately 10,000 square feet of roof deck replacement due to rot, removal of 4 feet in all directions around roof hatches, and restoration of slate tile repairs matching existing 7"x14" dimensions. All built-up roofing must be removed to substrate level before new installation. Interior work in active areas requires solid wall or metal stud/drywall systems floor-to-ceiling, with zip-wall systems for non-active areas. The project phasing plan requires contractor submission for approval, with all major closure events scheduled, punch list corrections allowing seven days, and manufacturer warranty inspections preceding final VA/design team inspections. Plumbing and mechanical work within the contractor's scope is limited to roof-mounted items including vent removal/reinstallation and curb flashing, with interior modifications handled by respective trades. Core samples and asbestos testing information will be addressed in subsequent RFI responses.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project 557-21-103: Correct Critical Roof and Exterior Wall Deficiencies- RFI’s 36C24726R0030
Compliance and Documentation:
1. Is this a Davis Bacon Wage project? If so, what is the roofing rate? VA
RESPONSE: YES, WAGE RATE IS IN THE SOLICITATION ON SAM.GOV
GA20260095 01/23/2026
2. Reference spec section 01 00 00 section 1.22. Please confirm if photographic documentation including the electronic indexing, utilizing drawings, and making drawings interactive with photos is required for this project.
AE RESPONSE: YES, PHOTOGRAPH RECORD-KEEPING, TESTING, AND
REPORTING.
THE CONTRACTOR IS TO MAINTAIN A CONTRACTOR QUALIFIED
CONTROL (CQC) PERSON ON SITE WHILE WORK IS BEING
PREFORMED.
A PROJECT SUPERINTENDENT MAY NOT PERFORM THE CQC ROLE.
THIS PERSON SHALL SUBMIT A SAMPLE REPORT WITH
PHOTOGRAPHS FOR APPROVAL.
INSTALLERS DIRECTING AND PERFORMING THE WORK CAN NOT
WORK AS THE CQC. THE SUPERINTENDENT CAN NOT ALSO BE THE
SSHO AND CAN NOT BE THE OFFICIAL PHOTOGRAPHER OR RECORD
KEEPER.
THE CQC WILL USE PHOTOS AND DESCRIPTIONS TO SHOW ALL
FUTURE INSTALLERS THE APPROVED PROCESSES ESTABLISHED IN
THE MOCKUP PROCESS OR AGREED TO MANUFACTURER’S
APPROVED PROCESSES.
THE CQC PERSON WILL SUBMIT THE INSTALLATION MEETING
MATERIAL TO THE RESPECTIVE MANUFACTURER'S SHOWING
GENERAL INSTALLATION PRACTICES. UPON SUGGESTIONS BY THE
COR, INSTALLER, MANUFACTURER OR TESTING AGENT, ADDITIONAL
EDITS MAY BE AMENDED TO THE CQC SITE SPECIFIC TRAINING
MATERIAL. THE CQC PERSON SHALL ADMINISTER AND MAINTAIN A
SIGNED-OFF SHEET OF INSTALLERS WHO HAVE SEEN AND
UNDERSTAND THE INSTALLATION MANUAL WITH PHOTOGRAPHS
AND OR VIDEO. ONLY INSTALLERS WHO HAVE REVIEWED AND
UNDERSTAND THE INSTALLATION DOCUMENTS PREPARED BY THE
CQC ARE PERMITTED TO INSTALL ON THIS PROJECT.
PROGRESS PHOTOGRAPHS, RECORD-KEEPING, TESTING, AND
REPORTING FILE STORAGE
THE CQC PERSON SHALL BE RESPONSIBLE FOR ALL CAPTURED
PHOTOS USING A 50-MEGAPIXEL, OR BETTER, CAMERA ABLE TO
CAPTURE INSTALLATION DETAIL. CQC PERSON SHALL SUBMIT
PHOTOGRAPHS, TESTING, AND REPORTING USING A CLOUD-BASED
MANAGEMENT SYSTEM AND SHALL SAVE ALL INFORMATION IN AN
AGREED VA / CONTRACTOR METHOD. SUBMIT A SAMPLE REPORT
TAKEN OF ANY TEST AREA WITHIN THE QUALITY CONTROL REPORT
TO THE COR FOR PHOTO QUALITY AND CONTENT APPROVAL. USING
A CLOUD-BASED REPORTING SOFTWARE. BASIS OF DESIGN IS
PROCORE. THIS SUBMITTAL SHALL INCLUDE THE CQC'S STANDARD
REPORTING FORMAT. THE FORM SHALL HAVE THE FORM NAME,
DATE, ITEM BEING REPORTED ON, LOCATION WITHIN THE BUILDING,
PHOTO, PHOTO SAVED NAME AND LOCATION (SEE BELOW), AND A
PORTION OF THE ELEVATION SHOWING THE PHOTO LOCATION. IF
THIS SHOWS A TEST LOCATION, STATE TEST STATUS, APPROVED / IN
PROGRESS / FAILED, AND WHO THE FORM WAS SENT TO. NAME OF
INSTALLATION COMPANY, CQC'S NAME, CQC'S COMPANY NAME.
THESE FORMS CAN BE STANDARDIZED USING THE CLOUD-BASED
SOFTWARE (PROCORE BASIS OF DESIGN). ALL FORMS MUST BE
PRINTABLE IN PDF FORMAT.
ALL PHOTOGRAPHS AND FILES SHALL BE KEPT ON A CLOUD BASED
SERVER. THE BASIS OF DESIGN IS PROCORE. THE PHOTO LOCATION
CAN BE TRACKED USING FILE NAMES OR MULT VISTA LOCATION
POINTERS (COLOR CODED ARROWS) SUPERIMPOSED ON THE
ELEVATION DRAWINGS.
ALL PHOTOGRAPHS AND REPORTS SHALL ALSO BE FILED AND
TURNED OVER THE COR USING AN AGREED TO IDENTIFICATION
SYSTEM LIKE THE FOLLOWING:
1. DATE OF PHOTO (MM/DD/YY)
2. COLUMN LINE (CL-##) OR WINDOW NUMBER (WN-##)
3. NAME OF REPORT (BACKER ROD, SEALANT, PAINT, EXISTING
CONDITION,....)
PHOTOGRAPH RECORDS EXPECTATIONS ARE ONE PHOTO WITH A
DESCRIPTION FOR EACH PROGRESS AREAS. IF CONTENT REQUIRES
MORE THAN ONE PHOTOGRAPH THE CQC PERSON IS ENCOURAGED
TO CAPTURE THAT CONTENT AND LABEL IT IN ADDITIONAL
PHOTOGRAPHS USING THE SAME LABELING SYSTEM. SEE SAMPLE
OF RECORD PHOTO DETAIL THIS PAGE.
ALL FILES WILL BE SAVED USING A CONTRACTOR-SUBMITTED AND
COR-APPROVED FILING SYSTEM.
EXAMPLE FILE FOLDER:
DATE:
FILE FOLDER: SEALANTS
FILES IN FOLDER: 09242023_WN24_SEALANT_1
UPON COMPLETION OF THE PROJECT SUPPLY THE COR WITH A
DIGITAL COPY OF THE FILE FOLDER AND ALL OF THE WINDOW CQC
VIDEO AND PHOTO CONTENT ORGANIZED IN THE COR APPROVED
FILE FOLDER SYSTEM.
CQC SHALL PROVIDE CLOUD BASED ACCESS TO THE VA AND DESIGN
TEAM AND WILL ASSUME ALL ASSOCIATED COST FOR THIS ACCESS.
3. Reference spec section 01 45 00 which states the Quality Control Manager "is required to be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of 10 years PM or SRE". This spec also states that the CQC Manager also has duties as the project Superintendent.
Please confirm if the CQC Manager is required to have one of the 3 degrees listed above. VA RESPONSE: THESE SPECIFIC DEGREES ARE NOT
REQUIRED, HOWEVER, CQC MANAGER MUST HAVE AT LEAST 10
YEARS OF EXPERIENCE IN A CQC ROLE.
4. Please confirm the minimum number of onsite personnel that will be required by the GC to fulfill the roles of Superintendent, QC Manager, and SSHO. . VA
RESPONSE: ONE PERSON CAN WEAR A MAXIMUM OF TWO ROLES.
AE RESPONSE: QC MANAGER SHOULD BE AN INDEPENDENT
PERSON WITH A PROFESSIONAL LICENSE AND MUST HAVE THE
USACE CONTRACTOR QUALITY CONTROL CERTIFICATE.
5. We request that a second site visit be allowed. Please confirm if there are any other available times for a visit. VA RESPONSE: NO ADDITIONAL SITE
VISIT WILL BE HELD.
6. Is an additional site visit(s) possible? VA RESPONSE: NO ADDITIONAL SITE
VISIT WILL BE HELD.
Materials and Specifications:
7. PVC or TPO? Is 60 mil required?
AE RESPONSE: EITHER PVC OR TPO IS ACCEPTABLE. THE BASIS OF
DESIGN IS 60MIL SEE SPECIFICATIONS. HOWEVER, THE VENDOR
WARRANTY SHOULD GOVERN:
07 54 19
1.10 WARRANTY
A. CONSTRUCTION WARRANTY: FAR CLAUSE 52.246-21, "WARRANTY
OF CONSTRUCTION."
B. MANUFACTURER'S WARRANTY: WARRANT ROOFING SYSTEM
AGAINST MATERIAL AND MANUFACTURING DEFECTS AND AGREE TO
REPAIR ANY LEAK CAUSED BY A DEFECT IN THE ROOFING SYSTEM
MATERIALS OR WORKMANSHIP OF THE INSTALLER.
1. WARRANTY PERIOD: 20 YEARS. BASIS OF DESIGN IS A 60MIL.
HOWEVER, KEY CONCERN IS OBTAINING VENDOR WARRANTY.
8. Is a 20-year weather tight warranty required?
AE RESPONSE: SEE 07 54 19
1.10 WARRANTY
A. CONSTRUCTION WARRANTY: FAR CLAUSE 52.246-21, "WARRANTY
OF
CONSTRUCTION."
B. MANUFACTURER'S WARRANTY: WARRANT ROOFING SYSTEM
AGAINST MATERIAL AND
MANUFACTURING DEFECTS AND AGREE TO REPAIR ANY LEAK
CAUSED BY A DEFECT
IN THE ROOFING SYSTEM MATERIALS OR WORKMANSHIP OF THE
INSTALLER.
1. WARRANTY PERIOD: 20 YEARS.
9. What R Value is required for the insulation?
AE RESPONSE: CONTRACTOR IS TO ASSUME ALL SUBSTRATE
CONDITIONS FOR LOW SLOPE ROOFS ARE LEVEL AND THE ¼” PER 12”
IS OBTAINED BY STARTING AT THE RECESSED ROOF DRAIN AND
GOES UP TO A PICK DIVIDING THE SPACES EVENLY. SHALL PROVIDE
A INSULATION SHEET AND TAPER SHOP DRAWING SHOWING
FASTENER LOCATIONS TO ACHIEVE THE CORRECT UPLIFT.
INSULATION SHALL BE PER 07 22 00 (FLAT SURFACES USUALLY HAVE
AN R-30 WITH A COMPLETE SYSTEM TO MAINTAIN AN R-25.
MANUFACTURER TO CONFIRM OVERALL SYSTEM COMPLIANCE AND
STATE THAT SYSTEM’S ACTUAL R VALUE)
PART 2 - PRODUCTS
2.1 SYSTEM PERFORMANCE
A. INSULATION THERMAL PERFORMANCE:
1. OVERALL AVERAGE R-VALUE: RSI-57 (R-25), MINIMUM.
2. ANY LOCATION R-VALUE: RSI-17 (R-10), MINIMUM.
10. What gauge will the flashings, gutters and downspouts be if any 24 gauge?
AE RESPONSE: SEE 07 60 00 2.12 CONDUCTORS – 16 GAUGE
FABRICATE CONDUCTOR BRACKETS OR HANGERS OF SAME
MATERIAL AS CONDUCTOR,
2 MM (1/16 INCH) THICK BY 25 MM (ONE INCH) MINIMUM WIDTH.
FORM TO SUPPORT CONDUCTORS 25 MM (ONE INCH) FROM WALL
SURFACE IN ACCORDANCE WITH ARCHITECTURAL SHEET METAL
MANUAL FOR RECTANGULAR AND ROUND SHAPES.
11. Will a coverboard be required? If so, thickness?
AE RESPONSE: SEE 07 22 00
1.1 SUMMARY
A. SECTION INCLUDES:
B. ROOF AND DECK INSULATION, SUBSTRATE BOARD, COVER BOARD
ON EXISTING
CONCRETE AND METAL DECK SUBSTRATES READY TO RECEIVE
ROOFING OR
WATERPROOFING MEMBRANE.
2.5 INSULATION ACCESSORIES
C. COVER BOARD:
1. GLASS-MAT, WATER-RESISTANT GYPSUM ROOF BOARD: ASTM
C1177/C1177M, 13 MM (1/2 INCH) THICK, FACTORY PRIMED
12. Will walk pads be required? If so, how many?
AE RESPONSE: CONTRACTOR SHALL PROVIDE HEAT WELDED WALK
PADS, PEEL AND STICK ARE NOT ALLOWED. PROVED WALK PADS
FROM EGRESS POINT TO THE SERVICEABLE EQUIPMENT, FANS,
MOTORS, FILTER ACCESS, AND ANY DEVICE NEEDING SEASONAL
CARE. THE CONTRACTOR WILL PROVIDE A SHOP DRAWING FOR
APPROVAL WITH WALK PADS CONNECTING ALL POINTS OF TRAVEL
TO THE SERVICEABLE EQUIPMENT. THIS SUBMITTAL WILL ALSO
ADDRESS THAT THE WALK PADS MEET THE UPLIFT REQUIREMENTS
OF THE ROOFING SYSTEM AND COMPLY WITH THE WARRANTY
STANDARDS.
13. Will the metal decking be B-Decking? What gauge?
AE RESPONSE: ESTIMATE 16GA B-DECKING SHIMS MAY BE
REQUIRED TO ADJUST TO EXISTING CONDITIONS. WHEN POSSIBLE
MATCH EXISTING HOWEVER NOT ALL DECK FLUTES ARE AVAILABLE
SO TRANSITIONS WILL BE NEEDED.
14. Are shop drawings provided for each roof location?
AE RESPONSE: YES, THE CONTRACTOR SHALL PROVIDE A SHOP
DRAWING OF EACH SPACE. THIS SHOP DRAWING WILL BE USED AS
AN INSPECTION BOOK. 11X19 IN SIZE FOR EASY CQC ONSITE
INSPECTION, THIS BOOK WILL IDENTIFY THE VARIOUS
CONNECTIONS WITH NOTATIONS AND EACH ROOF AREA WILL BE AN
INDEPENDENT DOCUMENT.
15. The documents mentioned either PVC or TPO roofing. Is 60 Mil the standard for both membrane types?
AE RESPONSE: CORRECT, EITHER PVC OR TPO IS ACCEPTABLE. THE
BASIS OF DESIGN IS 60MIL SEE SPECIFICATIONS, HOWEVER, THE
VENDOR WARRANTY SHOULD GOVERN:
07 54 19
1.10 WARRANTY
A. CONSTRUCTION WARRANTY: FAR CLAUSE 52.246-21, "WARRANTY
OF CONSTRUCTION."
B. MANUFACTURER'S WARRANTY: WARRANT ROOFING SYSTEM
AGAINST MATERIAL AND MANUFACTURING DEFECTS AND AGREE TO
REPAIR ANY LEAK CAUSED BY A DEFECT IN THE ROOFING SYSTEM
MATERIALS OR WORKMANSHIP OF THE INSTALLER.
1. WARRANTY PERIOD: 20 YEARS.
16. There are many types of warranties available for membrane roofing. Is a 20-year Watertight warranty required for this project?
AE RESPONSE: THE BASIS OF DESIGN WAS 60MIL SEE
SPECIFICATIONS:
07 54 19
1.10 WARRANTY
A. CONSTRUCTION WARRANTY: FAR CLAUSE 52.246-21, "WARRANTY
OF CONSTRUCTION."
B. MANUFACTURER'S WARRANTY: WARRANT ROOFING SYSTEM
AGAINST MATERIAL AND MANUFACTURING DEFECTS AND AGREE TO
REPAIR ANY LEAK CAUSED BY A DEFECT IN THE ROOFING SYSTEM
MATERIALS OR WORKMANSHIP OF THE INSTALLER.
1. WARRANTY PERIOD: 20 YEARS.
17. What is the insulation R value required for the roof insulation?
AE RESPONSE: CONTRACTOR IS TO ASSUME ALL SUBSTATE
CONDITIONS FOR LOW SLOPE ROOFS ARE LEVEL AND THE ¼” PER 12”
IS OBTAINED BY STARTING AT THE RECESSED ROOF DRAIN AND
GOES UP TO A PICK DIVIDING THE SPACES EVENLY. SHALL PROVIDE
A INSULATION SHEET AND TAPER SHOP DRAWING SHOWING
FASTENER LOCATIONS TO ACHIEVE THE CORRECT UPLIFT.
INSULATION SHALL BE PER 07 22 00 (FLAT SURFACES USUALLY HAVE
AN R-30 WITH A COMPLETE SYSTEM TO MAINTAIN AN R-25.
MANUFACTURE TO CONFIRM OVERALL SYSTEM COMPLIANCE AND
STATE THAT SYSTEMS ACTUAL R VALUE)
PART 2 - PRODUCTS
2.1 SYSTEM PERFORMANCE
A. INSULATION THERMAL PERFORMANCE:
1. OVERALL AVERAGE R-VALUE: RSI-57 (R-25), MINIMUM.
2. ANY LOCATION R-VALUE: RSI-17 (R-10), MINIMUM.
18. Please provide the required gauge for flashing, gutters, and downspouts.
AE RESPONSE: SEE 07 60 00 2.12 CONDUCTORS – 16 GAUGE
FABRICATE CONDUCTOR BRACKETS OR HANGERS OF SAME
MATERIAL AS CONDUCTOR,
2 MM (1/16 INCH) THICK BY 25 MM (ONE INCH) MINIMUM WIDTH.
FORM TO SUPPORT CONDUCTORS 25 MM (ONE INCH) FROM WALL
SURFACE IN ACCORDANCE WITH ARCHITECTURAL SHEET METAL
MANUAL FOR RECTANGULAR AND ROUND SHAPES.
19. Will a coverboard be required under the membrane? If so, what is the expected thickness?
AE RESPONSE: SEE 07 22 00
1.1 SUMMARY
A. SECTION INCLUDES:
B. ROOF AND DECK INSULATION, SUBSTRATE BOARD, COVER BOARD
ON EXISTING
CONCRETE AND METAL DECK SUBSTRATES READY TO RECEIVE
ROOFING OR
WATERPROOFING MEMBRANE.
2.5 INSULATION ACCESSORIES
C. COVER BOARD:
1. GLASS-MAT, WATER-RESISTANT GYPSUM ROOF BOARD: ASTM
C1177/C1177M, 13 MM (1/2 INCH) THICK, FACTORY PRIMED
20. Will walkway pads be required? If so, what is the pad sequence?
AE RESPONSE: CONTRACTOR SHALL PROVIDE HEAT WELDED WALK
PADS, PEEL AND STICK ARE NOT ALLOWED. PROVED WALK PADS
FROM EGRESS POINT TO THE SERVICEABLE EQUIPMENT, FANS,
MOTORS, FILTER ACCESS, AND ANY DEVICE NEEDING SEASONAL
CARE. THE CONTRACTOR WILL PROVIDE A SHOP DRAWING FOR
APPROVAL WITH WALK PADS CONNECTING ALL POINTS OF TRAVEL
TO THE SERVICEABLE EQUIPMENT. THIS SUBMITTAL WILL ALSO
ADDRESS THAT THE WALK PADS MEET THE UPLIFT REQUIREMENTS
OF THE ROOFING SYSTEM AND COMPLY WITH THE WARRANTY
STANDARDS.
21. What will be the required gauge for roof decking?
AE RESPONSE: ESTIMATE 16GA B-DECKING SHIMS MAY BE
REQUIRED TO ADJUST TO EXISTING CONDITIONS. WHEN POSSIBLE
MATCH EXISTING HOWEVER NOT ALL DECK FLUTES ARE AVAILABLE
SO TRANSITIONS WILL BE NEEDED.
22. Is there a specified manufacturer of the membrane roofing?
AE RESPONSE: NO
23. Please confirm the required roofing system for each building and roof area, specifically identifying where PVC and TPO roofing are required.
AE RESPONSE: EITHER IS ACCEPTABLE. GIVEN POTENTIAL
MATERIAL PROCUREMENT ISSUES, WE ARE OFFERING EITHER
SYSTEM AS ACCEPTABLE AS LONG AS VENDOR WARRANTY IS MET.
THE PROJECT TIME LINE MAY DICTATE WHAT IS AVAILABLE TO
ACHIEVE THIS GOAL.
24. Please confirm the required phasing of the roofing work and advise if any portions are restricted to after-hours or weekend performance.
AE RESPONSE: CONTRACTOR WILL PROVIDE A PHASING PLAN FOR
APPROVAL. ANY INTERIOR WORK, ENTRANCE, EMERGENCY EXIT,
DELIVERY SHUT DOWNS, AND ANY ACTIVITY THAT HENDERS THE VA
STAFF OR CLIENTS WILL BE PREFORMED ON AN AFTER REGULAR
HOUR SHIFT. LIKEWISE, ANY WORK PREFORMED IN AREAS WITH
OVERNIGHT STAFF OR CLIENTS WILL REQUIRE LIMITED WORK
HOURS. AT NO TIME DURING YOUR PHASING PLAN ARE YOU
PERMITTED TO CLOSE MORE THAN ONE EXIT. DURING THOSE
CLOSURES INTERIOR SIGNAGE WILL BE PROVIDED AS WELL AS
EXTERIOR SIGNAGE BOTH AT THE DOOR AND AGAIN AT THE
NEAREST INTERSECTIONS. EXTERIOR SIGNAGE WILL MEET DOT
SPECIFICATION AND MUST BE READABLE FROM 50 FEET. ALL
CLOSURES SHALL BE A TASK ON THE PROJECT SCHEDULE. EACH
PHASE WILL HAVE A START TASK, CONTRACTOR AHA TASK,
CONTRACTOR INSPECTION (PUNCH LIST) CONTRACTOR PUNCH
CORRECTION DURATION USUALLY 7 DAYS, ROOFING
MANUFACTURER INSPECTION TASK. DURATION TO OBTAIN LETTER
OF WARRANTY, MILESTONE TASK FOR LETTER TO REQUEST FINAL
INSPECTION, UPON THAT REQUEST YOU WILL HAVE SUBMITTED
YOUR COMPLETE PUNCH LIST, ROOFERS LETTER OF WARRANTY. A
14-DAY DESIGN REVIEW DURATION TASK OF THE DOCUMENTS WILL
BE PROVIDED, THEN A VA/DESIGN TEAM FINAL INSPECTION TASK.
DURING THAT INSPECTION THE CONTRACTOR WILL PROVIDE
ACCESS, A LIFT, A LIFT DRIVER, PPE, AT THE CONTRACTORS EXPENSE
TO FACILITY THE FINAL INSPECTION. THE CQC WILL BE PRESENT
AND WILL REPORT ALL FINDING IN A PHOTOGRAPH ISSUED REPORT.
25. Please clarify the extent of plumbing and mechanical work included in the roofing contractor’s scope, specifically regarding penetrations, drains, curbs, and rooftop equipment.
AE RESPONSE: ALL WORK SHOULD BE COORDINATED WITH THE
LEAD CONTRACTOR AND CLARIFIED WITH VA COR. THE TYPICAL IS
FOR THE ROOFING CONTRACTOR’S SCOPE OF WORK LIMITED TO THE
FOLLOWING ITEMS DIRECTLY RELATED TO THE ROOF SYSTEM (PER
DIVISION 07 AND THE PROJECT DRAWINGS):
REMOVAL AND REINSTALLATION OF ROOF-MOUNTED PLUMBING
VENTS, PIPES, AND FLASHING BOOTS.
REMOVAL AND REINSTALLATION OF MECHANICAL CURBS,
EQUIPMENT SUPPORTS, AND DUCT PENETRATIONS THAT PENETRATE
THE ROOF MEMBRANE.
PROPER FLASHING, COUNTERFLASHING, AND SEALING AROUND ALL
EXISTING AND NEW ROOF PENETRATIONS (PLUMBING VENTS, HVAC
CURBS, EXHAUST FANS, ETC.).
COORDINATION WITH THE MECHANICAL AND PLUMBING
SUBCONTRACTORS FOR TEMPORARY
DISCONNECTION/RECONNECTION OF EQUIPMENT AS REQUIRED TO
PERFORM THE ROOFING WORK.
RAISING OF CURBS OR PIPES (IF SHOWN ON DRAWINGS) TO ACHIEVE
THE REQUIRED MINIMUM FLASHING HEIGHT (TYPICALLY 8" ABOVE
THE FINISHED ROOF SURFACE).
THE ROOFING CONTRACTOR IS NOT RESPONSIBLE FOR THE
FOLLOWING:
ANY INTERIOR PLUMBING OR MECHANICAL MODIFICATIONS.
REWORK, RELOCATION, OR REPLACEMENT OF PLUMBING LINES,
DRAINS, OR MECHANICAL DUCTWORK INSIDE THE BUILDING.
ELECTRICAL WORK ASSOCIATED WITH MECHANICAL EQUIPMENT.
FURNISHING OR INSTALLING NEW MECHANICAL EQUIPMENT,
CURBS, OR VENTS UNLESS SPECIFICALLY INDICATED AS PART OF
THE ROOFING PACKAGE.
ALL OTHER PLUMBING AND MECHANICAL WORK (BEYOND THE
ROOF PENETRATION FLASHING AND COORDINATION) SHALL BE
PERFORMED BY THE RESPECTIVE PLUMBING AND MECHANICAL
SUBCONTRACTORS UNDER DIVISIONS 22 AND 23.IF THE CONTRACT
DOCUMENTS SHOW SPECIFIC ITEMS THAT APPEAR TO CONFLICT
WITH THE ABOVE, PLEASE IDENTIFY THE DRAWING SHEET AND
SPECIFICATION SECTION SO WE CAN PROVIDE FURTHER
CLARIFICATION OR A FORMAL PROPOSAL FOR ANY ADDITIONAL
SCOPE.
26. Please clarify the exact extent of the slate roof repair/replacement scope and confirm which portions are to be excluded under the deduct alternate
AE RESPONSE: CQC SHALL PREFORM AN EVALUATION USING THE
ALLOTTED QUANTITIES. IF THE QUANTITIES EXCEED THE ESTIMATE
THEY WILL NOTIFY THE VA COR. THE WORK AREA IS CAMPUS WIDE
SLATE BUILDING.
27. Slate tiles shown during the site visit measured 7"x14". The Slate tiles indicated on the drawings show dimensions of 14"x22". Which size is correct?
AE RESPONSE: CONTRACTOR IS TO MATCH EXISTING SIZE.
28. Both TPO and PVC roofing membranes are specified in the specifications section.
Is there a schedule of which roof areas receive TPO and which receive PVC, or are we allowed to pick a system for all roof areas?
AE RESPONSE: EITHER IS AUTHORIZED. GIVEN MATERIAL
PROCUREMENT ISSUES WE ARE OFFERING EITHER SYSTEM AS
ACCEPTABLE. THE PROJECT TIME LINE MAY DICTATE WHAT IS
AVAILABLE TO ACHIEVE THIS GOAL.
Hazardous Materials:
29. Are we to assume all roofs contain hazardous material and are to be abated?
AE RESPONSE: TO BE ADDRESSED IN SUBSEQUENT RESPONSE.
30. Are there any known areas of asbestos associated with any of the areas where work is to be performed? AE RESPONSE: TO BE ADDRESSED IN
SUBSEQUENT RESPONSE.
31. Seeing as how we were not able to access all the roofs is there any core information as to what the roofs contain?
AE RESPONSE: TO BE ADDRESSED IN SUBSEQUENT RESPONSE.
32. Are we to assume all roofs described in the project document contain hazardous material, or should we provide test results for all the roofs noted for renovation?
AE RESPONSE: TO BE ADDRESSED IN SUBSEQUENT RESPONSE.AE
RESPONSE.
33. Have the roofs been checked for asbestos? AE RESPONSE: TO BE
ADDRESSED IN SUBSEQUENT RESPONSE.
34. Do the membrane roofs being removed have a built-up system under them? If so do we just remove the membrane system or everything to the deck? If the membrane system only is to be removed, what is the requirement of the insulation?
AE RESPONSE: ASSUME ALL BUILD UP MUST BE REMOVED DOWN
TO SUBSTRATE LEVEL. ASSUME ALL FLAT SUBSTRATES ARE LEVEL,
AND BUILD UP REQUIRED TO ACHIEVE SLOPE OF ¼” PER 1’.
Repairs and Site Conditions:
35. How many locations for slate repair?
AE RESPONSE: CQC SHALL PREFORM AN EVALUATION USING THE
ALLOTTED QUANTITIES. IF THE QUANTITIES EXCEED THE ESTIMATE
THEY WILL NOTIFY THE VA COR. THE WORK AREA IS CAMPUS WIDE
SLATE BUILDING.
36. Are there any wall repairs? If so, where are they located? VA RESPONSE: SEE
SHEETS C6.AE102 AND C5.AE101 FOR DETAILS.
37. There are notes throughout the plans that simply state "prep and repair existing roof deck as required for new construction". What type of roof deck "repair" should be quoted and what qty of "repair" should be included in each GC's bid for each area. This info is needed to ensure all GC's are bidding the same scope.
Currently, any roof deck repair would be considered an "unforeseen" condition unless some type of qty is provided.
AE RESPONSE: ESTIMATE 16GA B-DECKING SHIMS MAY BE
REQUIRED TO ADJUST TO EXISTING CONDITIONS. WHEN POSSIBLE
MATCH EXISTING HOWEVER NOT ALL DECK FLUTES ARE AVAILABLE
SO TRANSITIONS WILL BE NEEDED. THE GOAL IS TO MATCH THE
EXISTING.
38. Reference sheet AE004 - various details. One example in detail C1 shows compressible tube to be by others, it also shows compressible insulation to be supplied by others. Please confirm if these items are to be furnished and installed as part of the roofing scope of if they will be by others.
AE RESPONSE: THE DETAILS READ FROM A ROOFING
MANUFACTURERS PROSPECTIVE. BY OTHERS SHALL BE BY THE
CONTRACTOR SUPPLING A COMPLETE SYSTEM. WHEN POSSIBLE
MAINTAIN MANUFACTURERS SYSTEM MATERIAL WHEN THIS IS NOT
AN OPTION LIKE SAY WOOD BLOCKING THEN REMOVE EXISTING
WOOD BLOCKING AND INSTALL NEW WOOD BLOCK THAT COMPLIES
WITH THE ROOFING MANUFACTURERS REQUIREMENTS. TO ADD ALL
WOOD BLOCKING SHALL BE NEW AND SIZED TO MATCH THE NEW
INSULATION AND INSTALLATION NEEDS.
39. Please clarify the full scope of lightning protection, including which areas require new installation, repair, or removal/reinstallation. Additionally, confirm if testing or recertification is required at project closeout.
AE RESPONSE: YES, REPLACE WITH NEW AS PER DRAWINGS.
40. Please clarify the extent of “minor exterior wall repairs” and “basement wall repairs,” including locations, materials, and whether sealants, masonry repairs, coatings, or waterproofing are included.
AE RESPONSE: REFER TO DRAWING SHEETS C6.AE102 AND C5.AE101
FOR DETAILS. SEAL ALL CRACKS AND GAPS WITHIN LEAKING
ABANDONED CONDUIT BOXES AS NOTED. CONTRACTOR TO:
1. IDENTIFY THE LEAK — LOCATE CRACKS, JOINTS,
HONEYCOMBS, OR SEEPAGE POINTS ON THE CONCRETE WALL
(OFTEN FROM THE NEGATIVE SIDE, I.E., INSIDE THE
STRUCTURE).
2. DRILL INJECTION PORTS — SMALL HOLES (USUALLY ½–¾ INCH
DIAMETER) ARE DRILLED AT INTERVALS ALONG OR
STAGGERED AROUND THE CRACK (TYPICALLY 6–12 INCHES
APART, ANGLED TO INTERSECT THE CRACK).
3. INSTALL PACKERS — MECHANICAL OR SURFACE PACKERS
ARE INSERTED INTO THE HOLES TO CREATE A SEALED ENTRY
POINT FOR THE RESIN.
4. INJECT THE POLYURETHANE RESIN — A LOW-VISCOSITY
LIQUID PU RESIN IS PUMPED IN UNDER PRESSURE (LOW TO
HIGH PRESSURE, DEPENDING ON THE SYSTEM).
• IT REACTS WITH WATER/MOISTURE INSIDE THE CRACK
OR VOID.
• THE RESIN EXPANDS RAPIDLY (UP TO 20–40 TIMES ITS
VOLUME IN SOME HYDROPHILIC TYPES) INTO A
FLEXIBLE, TOUGH FOAM OR GEL THAT FILLS THE
CRACK, VOIDS, AND IRREGULARITIES.
5. CURE AND SEAL — THE FOAM CURES QUICKLY (SECONDS TO
MINUTES) TO FORM A PERMANENT, WATERTIGHT, FLEXIBLE
GASKET. EXCESS MATERIAL IS CLEANED UP, AND PORTS ARE
REMOVED OR SEALED.. CRACKS AND LEAK PATHS EXCEEDING
¼" IN WIDTH, EXPOSING REBAR, OR LONGER THAN 10 FT
DISCOVERED DURING RESTORATION SHALL BE DOCUMENTED
WITH PHOTOS AND A WRITTEN REPORT PRESENTED TO THE VA
COR.
6. BASIS OF DESIGN SIKA INJECTION (E.G., SIKAFIX HH,
INJECTION-101/201)
CQC TO DOCUMENT CRACKS AND LEAK PATHS EXCEEDING ¼" IN
WIDTH, EXPOSING REBAR, OR LONGER THAN 10 FT DISCOVERED
DURING RESTORATION AND SHALL DOCUMENT WITH PHOTOS
AND A WRITTEN REPORT PRESENTED TO THE VA COR PRIOR TO
CONSTRUCTION.
41. Please clarify if any temporary interior protection, dust protection, or occupied-space measures beyond standard temporary dry-in are required.
AE RESPONSE: IN ACTIVE CORRIDORS USE A SOLID WALL SYSTEM
OR CONSTRUCT A METAL STUD AND DRYWALL SYSTEM FLOOR TO
CEILING.
AT ACTIVE DOORS WITH WORK BEING COMPLETED OVERHEAD
PROVIDE A SCAFFOLD TUNNEL ACCESS OUT BEYOND THE HEIGHT
DISTANCE WITH ENGINEER APPROVE PLANS AND PLYWOOD TO
MAINTAIN A SAFE EGRESS ZONE. THE CQC WILL SET THESE AREAS
UP BASED ON TIME OF DAY, PHASING AND THE WORK
REQUIREMENTS. IF SHORT CLOSURES FOR LESS THAN 30 MINUTES
IN AN ACTIVE AREA MAINTAIN A WATCH INSIDE AND A SEPARATE
WATCH OUTSIDE TO DIVERT TRAFFIC. IN NON ACTIVE OR NIGHT
CLOSURES PROVIDE A COMPLETE ZIP-WALL SYSTEM WITH PLASTIC
AND WALL AND CEILING SEALS AND IF YOUR PRODUCING DUST OR
FUMES. FILL OUT THE ICRA FORM COORDINATE WITH THE VAIH AND
FOLLOW STANDARD ICRA PROCEDURES.
42. The project title mentions Wall repair. Where is the wall repair located? VA
RESPONSE: SEE SHEETS C6.AE102 AND C5.AE101 FOR DETAILS.
Mechanical and Plumbing:
43. For the plumbing stack and drain replacement. How much of the interior portion of the pipes are we to figure for replacement? AE RESPONSE: REPLACE
THE DOWN PIPE FROM THE DRAIN AND 20’ OF PIPE OR TO THE
NEAREST CONNECTION. ASSUME DUCTILE IRON PIPE AND RUBBER
NO HUB CONNECTIONS. CQC TO TORQUE 5% OF ALL NO HUB
CONNECTIONS.
44. Is the slope to the drains in the deck or the built-up? AE RESPONSE: ASSUME
ALL SUBSTRATES ARE FLAT AND BUILD UP WILL BE REQUIRED VIA
INSULATION TO ACHIEVE MINIMUM OF ¼” PER 1 FOOT.
Miscellaneous:
45. Are all the solar panels to be disposed of once removed? VA RESPONSE: YES, DISPOSE OR RECYCLE, THEY ARE PAST THEIR USEFUL LIFE.
AE RESPONSE: ONCE REMOVED THEY ARE THE PROPERTY OF THE
CONTRACTOR AND MUST BE LEGALLY HANDLED.
46. Will the original Pre-Bid Site Visit sign in sheet be posted on SAM.gov? VA
RESPONSE: WILL BE POSTED WITH RFI RESPONSES
47. Has there been any core samples done on the roofs, and if so, what are the depths, and deck types? AE RESPONSE: TO BE ADDRESSED IN SUBSEQUENT
RESPONSE.
48. What type of roof deck “repair” should be quoted and what qty of “repair” should be included in each GC’s bid for each area. This info is needed to ensure all GC’s are bidding the same scope. Currently, any roof deck repair would be considered an “unforeseen” condition unless some type of qty is provided.
AE RESPONSE: CONTRACTOR SHOULD EXPECT 10,000 SF OF ROOF
DECK REPLACEMENT DUE TO ROT. ALSO, THE CONTRACTOR
SHOULD EXPECT TO REMOVE 4’ IN ALL DIRECTIONS AROUND NEW
OR EXISTING ROOF HATCHES. ALL HATCHES SHALL BE EPOXY
PRIMED AND RECEIVE TWO COATS OF URETHANE PAINT COLOR BY
COR. THESE WILL ALSO GET NEW WOOD BLOCKING AND ANY
UNUSED HATCH COVER WILL GET FILLED WITH INSULATION OR
WILL BE REMOVED AND DECKED OVER. VA COR WILL COORDINATE
THOSE NEEDS BASED ON THE CQC EVALUATION PRIOR TO STARTING
WORK IN THAT AREA. DESTRUCTIVE REVIEW WAS NOT PERMITTED
DURING DESIGN THE CQC WILL BE MORE INVASIVE AND WILL CUT
OUT 12” X 12” DESTRUCTIVE HOLES THEN WATER TIGHT THESE
INSPECTION POINT UNTIL THAT PHASE OF WORK COMMENCES.
49. Are there any as-builts of the current roof areas?
VA Response: Utilize the plans and specifications provided in the solicitation.