08 34 46 RADIO-FREQUENCY-INTERFERENCE SHIELDING DOORS_r1.pdf
PDF 135 KB Posted
- Attached to
- Z2DA--Replace MRI 1. 5T Federal contract opportunity
- Solicitation number
- 36C24626B0001
About this file
This document is a technical specification section (08 34 46) for Radio-Frequency-Interference Shielding Doors for the Durham VA Healthcare System's MRI 1.5T replacement project. The specification requires a purpose-manufactured MRI door system with a demonstrated life cycle test rating of at least 10,000 operational cycles without loss of RF attenuation, from a manufacturer with a minimum 5-year track record. The doors must include specific hardware components such as continuous hinges, privacy lever locks, wall stops, kick plates, card readers, and thresholds, with a requirement to be compatible with the existing Physical Access Control System.
Key technical requirements include a high-pressure plastic laminate finish, a minimum Sound-Transmittance Class of STC-40, and RF shielding performance to be determined in consultation with the VA Physicist and MRI equipment manufacturer. The installation process involves precise frame anchoring using non-ferrous materials, ensuring the doors are plumb, level, and properly aligned. The specification emphasizes compatibility with existing systems, detailed hardware specifications, and precise installation requirements to maintain the RF shielding integrity of the MRI environment.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Abstract 36C24626B0001.pdf | ||
| 36C24626B0001 0006.docx | DOCX document | |
| Base Bid Cost Breakdown.xlsx | XLSX spreadsheet | |
| 36C24626B0001 0005.docx | DOCX document | |
| 36C24626B0001 0004.docx | DOCX document | |
| 36C24626B0001 0003.docx | DOCX document | |
| 36C24626B0001 0002.docx | DOCX document | |
| 08 34 46 RADIO-FREQUENCY-INTERFERENCE SHIELDING DOORS.pdf | ||
| 36C24626B0001 0001.docx | DOCX document | |
| Pre-Bid Conference-Site Vist_Replace MRI 1.5T_Attendees.pdf | ||
| Addendum 1 Narrative.pdf | ||
| A101 - ARCHITECTURAL PLANS DETAILS AND SECTIONS.pdf | ||
| 558-CSI-400 Replace MRI 1.5T Specs.pdf | ||
| 558-CSI-400 Replace MRI 1.5T Specs.docx | DOCX document | |
| 36C24626B0001_2.docx | DOCX document | |
| 558-CSI-400 Replace MRI 1.5T Drawings.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
558-CSI-400 Replace MRI 1.5T 01-01-21 Durham VA Healthcare System Addendum 01
08 34 46 - 1
SECTION 08 34 46
RADIO-FREQUENCY-INTERFERENCE SHIELDING DOORS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Radio-frequency-interference shielding doors and frames at interior locations.
1.2 RELATED WORK
A. Radio-Frequency Interference Shielding Envelope: Section 13 49 26, RADIO-FREQUENCY SHIELDING
B. Card Readers and Biometric Devices: Section 28 13 00, PHYSICAL ACCESS
CONTROL SYSTEM.
1.3 APPLICABLE PUBLICATIONS
A. Comply with references to extent specified in this section.
B. American National Standard Institute (ANSI):
A250.8-2014.............Standard Steel Doors and Frames
C. ASTM International (ASTM):
B209-14.................Aluminum and Aluminum-Alloy Sheet and Plate
B209M-14................Aluminum and Aluminum-Alloy Sheet and Plate
(Metric)
B221-14.................Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes
B221M-13................Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes (Metric)
E90-09..................Laboratory Measurement of Airborne Sound
Transmission Loss of Building Partitions and
Elements
D. National Association of Architectural Metal Manufacturers (NAAMM):
AMP 500-06..............Metal Finishes Manual
E. Military Standard (MIL-STD) MIL-STD-285 Attenuation of Measurements for Enclosures
F. Department of Veterans Affairs VA Physical Security and Resiliency Design Manual October 1, 2020
1.4 SUBMITTALS
A. Submittal Procedures: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
08 34 46 - 2
B. Submittal Drawings:
1. Show size, configuration, fabrication, and installation details.
C. Manufacturer's Literature and Data:
1. Description of each product.
2. Include schedule showing each door and frame requirements for openings.
3. Installation instructions.
D. Test reports: Certify each product complies with specifications.
1. Sound rated door.
2. MIL-STD-285 – Attenuation performance.
E. Qualifications: Substantiate qualifications comply with specifications.
1. Manufacturer with project experience list.
F. Installer: Substantiate qualifications comply with specifications.
1. Installer with project experience list.
2. Written approval to install from Manufacturer.
1.5 QUALITY ASSURANCE
A. Manufacturer Qualifications:
1. Doors to be provided by same manufacturer providing the radiofrequency wall, ceiling, and flooring panels.
2. Regularly manufactures specified products.
3. Manufactured specified products with satisfactory service on five similar installations for a minimum of five years.
a. Project Experience List: Provide contact names and addresses for completed projects.
B. Installer Qualifications:
1. Written approval to install from product manufacturer.
1.6 DELIVERY
A. Deliver products in manufacturer's original sealed packaging.
B. Mark packaging, legibly. Indicate manufacturer's name or brand, type, production run number, and manufacture date.
C. Before installation, return or dispose of products within distorted, damaged, or opened packaging.
1.7 STORAGE AND HANDLING
A. Store products indoors in dry, weathertight, conditioned facility.
B. Protect products from damage during handling and construction operations.
08 34 46 - 3
1.8 WARRANTY
A. Construction Warranty: FAR clause 52.246-21, "Warranty of
Construction."
PART 2 - PRODUCTS
2.1 RADIO-FREQUENCY SHIELDED DOORS
A. Provide door, frame, hardware and threshold as indicated with purpose manufactured MRI door system with a demonstrated life cycle test rating of at least (10,000) operational cycles without loss of specified RF attenuation, from a single manufacturer with a minimum of 5 years track record and 2 years for the products supplied. Supply assemblies complete with a rigid structural frame, hardware, seals and parts necessary for operation.
1. Door Hardware:
Description: Product: Finish: Manufacturer:
Hinge Continuous 626/US26D Falcon, or as provided by Door Manufacturer.
Lock Privacy Lever 626/US26D Falcon
Core 7-Pin, Removable Best
Stop Wall Stop 626/US26D -
Kick Plates 10” X Width of
Door
626/US26D -
Card Reader Match existing Match Existing
Door
Contact/Power
Supply
Compatible with
PACS
626/US26D Falcon, or as compatible with PACS
Silencer 3 silencers for each door
Warning Light w/ Door Switch Existing, To remain
Existing, To remain
a. Physical Access Control System (PACS): Existing to remain, including card reader.
1) New hardware to be compatible with existing PACS system, card reader, and all existing equipment listed to remain.
b. Fastening of kickplates to not interfere with attenuation performance of the door.
c. Threshold: Aluminum, ABA, low profile.
2. Size(s): As indicated on the drawings.
08 34 46 - 4
3. Finish: High-Pressure Plastic Laminate. Finish to be chosen from Manufacturer’s full spectrum of finishes.
4. Sound-Transmittance Class: STC-40, minimum, when tested according to
ASTM E90.
5. Radiofrequency Shielding:
a. Submit RF attenuation performance requirements based on VA Physicist electromagnetic interference (EMI) field measurements, and evaluation of site conditions, in consultation with the MRI equipment manufacturer. Ensure that RF shielding system fully complies with the MRI equipment manufacturer’s requirements.
PART 3 - EXUCUTION
3.1 PRE-INSTALLATION
A. Before installation, inspect job site for any nonconforming work, and report such instances to the General Contractor and VA COR.
B. Confirm working compatibility of the new door and door hardware with the existing Physical Access Control System before ordering and installation.
3.2 INSTALLATION – GENERAL
A. Install products according to manufacturer's instructions and approved submittal drawings.
1. When manufacturer's instructions deviate from specifications, submit proposed resolution for Contracting Officer's Representative consideration.
3.3 INSTALLATION - FRAMES
A. Plumb, align, and brace frames until permanent anchors are set.
B. All permanent and temporary anchors to be non-ferrous.
1. Floor anchors:
a. Anchor frame jambs to the floor with two expansion bolts.
1) 9 mm (3/8 inch) diameter bolts.
b. Power actuated drive pins are not acceptable.
2. Jamb Anchors:
a. Metal framed walls: Secure anchors to sides of studs with two fasteners through anchor tabs.
C. All fasteners are to be non-ferrous.
D. Use temporary and permanent wood spreaders and blocking as necessary.
E. Fill frames with insulation.
08 34 46 - 5
3.4 INSTALLATION - DOORS
A. Install doors plumb and level.
B. Adjust doors for smooth operation.
C. Touch up damaged factory finishes.
1. Repair galvanized surfaces with galvanized repair paint.
2. Repair painted surfaces with touch up primer.
3.5 CLEANING
A. Clean exposed door and frame surfaces. Remove contaminants and stains.
3.6 PROTECTION
A. Protect doors and frames from traffic and construction operations.
B. Remove protective materials immediately before acceptance.
C. Repair damage.
- - - E N D - - -
| SECTION 08 34 46 radio-frequency-interference shielding doors |
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| 1.2 RELATED WORK |
| 1.3 APPLICABLE PUBLICATIONS |
| 1.4 SUBMITTALS |
| 1.5 QUALITY ASSURANCE |
| 1.6 DELIVERY |
| 1.7 STORAGE AND HANDLING |
| PART 2 - PRODUCTS |
| 2.1 Radio-Frequency Shielded Doors |
| PART 3 - exucution |
| 3.1 Pre-Installation |
| 3.2 installation – general |
| 3.3 INSTALLATION - frames |
| 3.4 installation - doors |
| 3.5 CLEANING |
| 3.6 PROTECTION |
File details come from the government source that posted it. Updated .